HomeMy WebLinkAboutLIND PROPERTY, 2ND FILING - PDP - 39-94D - DECISION - FINDINGS, CONCLUSIONS & DECISIONS
r
Lind Phase II PDP
Administrative Hearing
Findings, Conclusions, and Decision
July 13, 2004
Page 5 of 5
Urban Development Contiguity Requirements
The Staff Report outlines the Project's compliance with Section 3.7.2 of the LUC
concerning contiguity to existing urban development and there was no evidence
introduced at the hearing to contradict the Staff Report.
Adequate Public Facilities
Section 3.7.3 of the LUC is intended to ensure that public facilities and services
needed to support the development are available concurrently with the impacts of
such development.
As noted above, based on the evidence presented at the hearing by the City
Engineer, the Project complies with Section 3.7.3 of the LUC.
SUMMARY OF CONCLUSIONS
A. The Lind Phase II Project Development Plan is subject to administrative review
and the requirements of the Land Use Code (LUC).
B. The Lind Phase II Project Development Plan complies with all applicable district
standards of Section 4.4 of the Land Use Code, (LMN) Low Density Mixed Use
Neighborhood zone district.
C. The Lind Phase II Project Development Plan complies with all applicable General
Development Standards contained in Article 3 of the Land Use Code.
DECISION
The Lind Phase II Project Development Plan #93-94D, is hereby approved by the
Hearing Officer subject to the following condition:
The Applicant shall enter into an agreement with the underlying mineral rights owners
concerning the location and access of future extraction activities within the development
plan. Such agreement shall be completed prior to approval of the Final Plan.
Dated this 16th day of July 2004, per authority granted by Sections
1.4.9(E) and 2.1 of the Land Use Code.
Cameron Gloms
Current Plan ng Director
Lind Phase II PDP
Administrative Hearing
Findings, Conclusions, and Decision
July 13, 2004
Page 4 of 5
3. Compliance with Article 3 of the Land Use Code — General Development
Standards
The project development plan complies with all applicable sections of Article 3 of
the LUC as explained below.
Landscaping and Tree Protection. The staff report outlines the Project's
compliance with Section 3.2.1 concerning landscaping and tree protection and
there was no evidence introduced at the hearing to contradict the Staff Report.
Parking and Access. The staff report outlines the Project's compliance with
Section 3.2.2 concerning access, circulation and parking. The Project provides
residential off-street parking spaces exceeding the number required under the
LUC.
Site Lighting
The Hearing Officer finds that the Project is in conformance with the site lighting
standards specified in Section 3.2.4. The Project does not propose exterior
lighting, with the exception of porch lights and other accessory lighting.
Building and Project Compatibility
Section 3.5.1 of the LUC requires that new developments be compatible with the
established character of the area. Pursuant to this section, the proposed single
family housing, of one- to two-story heights, is compatible with neighboring single
family development.
Residential Building Standards
The staff report outlines the Project's conformance with Section 3.5.2 concerning
the design of residential buildings. Specifically, the Project will comply with the
"garage door" standards found in the LUC.
Master Street Plan '
The Hearing Officer finds that the Project is in substantial compliance with the
City's adopted Master Plan.
Transportation Level of Service (LOS) Requirements
Section 3.6 of the LUC imposes standards for all modes of transportation. Public
testimony provided at the hearing by the City's Traffic Engineer indicated that the
Project is in compliance with Section 3.6.4 of the LUC. This was substantiated
by a letter submitted into the record which clearly stated the City's commitment to
reserving capacity for traffic impacts associated with the Lind development plan
in an amount sufficient to find compliance with the LOS Standards at key
intersections.
Lind Phase II PDP
Administrative Hearing
Findings, Conclusions, and Decision
July 13, 2004
Page 3 of 5
FACTS AND FINDINGS
1. Site Context/Background Information
The surrounding zoning and land uses are as follows:
N: LMN — undeveloped
S: LMN — single family residential
E: LMN — undeveloped
W: LMN — single family residential
The property was annexed in 1984 as part of the Country Club North First
Annexation.
The first phase of the Lind PDP was approved in May 2003.
2. Compliance with Article 4 and the LMN — Low Density Mixed Use
Neighborhood District Standards:
The Project Development Plan complies with all applicable requirements of
Article 4 and the LMN zone district. The Staff Report summarizes the PDP's
compliance with these standards and no specific evidence was presented to
contradict or otherwise refute the compliance with Article 4 or the LMN District
Standards. In particular, the single-family residential use is permitted within the
LMN zone district subject to an administrative review. While the project provides
4.8 units/acre, which is less than the required minimum average net residential
density of 5.0 units/acre, the applicant has committed to provide the requisite
number of additional units when the balance of the property is developed under
future phases. According to the staff report, the Project is also in conformance
with Section 4.4(D)(2), standards relating to the mix of housing types, Section
4.14(D)(3) that requires at least 90% of the units to be located within % mile and
including central feature or gathering place, Section 4.4 (D)(7) that requires all
residential units to be within 1/3 mile of a neighborhood park, Section 4.4 (E)(1)
requiring a street network with blocks that are less than 12 acres in area and no
more than 700 feet in length, and Section 4.4(E)(3) calling for a maximum
building height of 2'/2 stories.
There was no direct testimony or evidence presented at the public hearing to
contradict the Project's compliance with these standards.
Lind Phase II PDP
Administrative Hearing
Findings, Conclusions, and Decision
July 13, 2004
Page 2 of 5
STAFF RECOMMENDATION: Conditional approval
NOTICE OF PUBLIC HEARING: Evidence presented to the Hearing Officer established
no controversy or facts to refute that the hearing was
properly posted, legal notices mailed and notice
published.
The Hearing Officer, presiding pursuant to the Fort Collins Land Use, Code, opened the
hearing at approximately 5:00 on July 13, 2004 in Conference Room A at 281 North
College Avenue, Fort Collins, Colorado.
HEARING TESTIMONY, WRITTEN COMMENTS AND OTHER EVIDENCE:
The Hearing Officer accepted during the hearing the following evidence: (1) Planning
Department Staff Report; (2) application, plans, maps and other supporting documents
submitted by the applicant and the applicant's representatives to the City of Fort Collins;
and (3) a tape recording of public testimony provided during the hearing. The LUC, the
City's Comprehensive Plan (City Plan), and the formally promulgated policies of the City
are all considered part of the evidence considered by the Hearing Officer.
The following is a list of those who attended the meeting:
From the City:
Bob Barkeen, City Planner
From the Applicant:
Terrance Hoaglund, Vignette Studios
Yvonne Seaman, Centex Homes
Jamie Hendrickson, Vignette Studios
From the Public:
Marybeth Sobel, Krug & Sobel, LLC Attorneys
Written Comments:
Letter from Eric Bracke, City Traffic Engineer to TST Consulting Engineers dated
February 15, 2002 outlining the reservation of intersection capacity at the Vine
and Lemay intersection.
City of Fort Collins
Commi y Planning and Environmental rvices
Current Planning
CITY OF FORT COLLINS
ADMINISTRATIVE HEARING OFFICER
TYPE I ADMINISTRATIVE HEARING
FINDINGS, CONCLUSIONS AND DECISION
ADMINISTRATIVE HEARING DATE:
PROJECT NAME:
CASE NUMBER:
APPLICANT:
OWNER:
HEARING OFFICER:
PROJECT DESCRIPTION:
July 13, 2004
Lind Property Phase II, Project
Development Plan
#93-94D
Vignette Studios
144 Mason Street, Suite 2
Fort Collins, CO 80524
Centex Homes, Inc.
9250 East Costilla Avenue, Suite 200
Greenwood Village, CO 80112
Cameron Gloss
Current Planning Director
The Applicant has submitted a Project Development Plan (referred to herein as the
"Project" or the "PDP") for Phase II of the Lind Overall Development Plan. This phase
includes 129 single-family residential units and 30 attached single family residential
units (townhomes) on 44 acres located at the northeast corner of North County Road
(NCR) 11 and County Road (CR) 52. The PDP also includes a future neighborhood
center to serve the project and the surrounding neighborhood. The project provides
additional open space area and a connection to the City's proposed regional recreation
trail.
The PDP includes a site for a future oil well. This location was agreed upon by the
applicant and the owners of the underlying mineral rights. A separate application must
be filed to construct the well.
SUMMARY OF HEARING OFFICER DECISION: Conditional approval