HomeMy WebLinkAboutLIND PROPERTY - FDP - 39-94C - LEGAL DOCS - RESPONSE TO STAFF REVIEW COMMENTSinto the ditch at this point, it should be noted that there is no agreement in place allowing the
discharge of any developed storm water into our ditch.
Respectfully submitted,
Mn
fayo
MS/j ra
cc: Yvonne Seaman
Donn Engel
TIMOTHY J. DOW, MBA, JD
PATRICIA T. DOW, CPA, JD, LLM*
MAYO SOMMERMEYER, PC**
OF COUNSEL
• ALSO ADMrfrED TO PMCTICE LAW IN NEBMSKA
••ALSO ADMITIED TO PIIAMCE LAW IN WYOMING
THE DOW LAW FIRM, LLC
ATTORNEYS AND COUNSELORS AT LAW
P.O. BOX 1578
FORT COLLINS, COLORADO 80522-1578
(970)498-9900
Via Hand Delivery
Bob Barkeen
City of Fort Collins Current Planning
281 N. College Avenue
Fort Collins, CO 80524
FAX: (970) 498-9966
E-MAIL: dow@dowlawfirm.com
July 16, 2003
4 7 CLOCK TOWER SQUARE
323 SOUTH COLLEGE AVENUE
FORT COLLINS, COLORADO 80524
2312 CAREY AVENUE
CHEYENNE, WYOMING 82001
(307)634-1541
Re: Project #39-94B Lind Property PDP Final Compliance — Type I (LUC)
Our Clients: Windsor Reservoir & Canal Company
Larimer & Weld Irrigation Company
Dear Mr. Barkeen:
I have reviewed your Revision Comment Sheet submission dated June 26, 2003. I
appreciate this is Filing 1 and the total storm water management for the whole project may not
yet be developed.
We have worked closely with the developer from time to time concerning storm water
management and discharge. I cannot tell from the referenced submission whether any storm
water from Filing 1 is planned to be discharged into our client's ditch. There have been some
discussions about retaining all of the developed storm water in Filing 1 and as other filings are
developed toward completion of the whole project, a storm water system would be developed
which will detain and discharge into the ditch at a modest rate.
I have previously corresponded with Storm Water concerning retention issues, which
may or may not be relevant when we're looking just at Filing 1, but I thought you should be
aware of that.
The issue here is that I cannot tell from the submission whether the developer plans to
discharge any portion of the developed storm water into the ditch in conjunction with just Filing
1. If the developer is going to retain all of the water, then we have no further comment other
than what has already been mentioned. If the developer is planning on discharging any water