HomeMy WebLinkAboutLINCOLN EAST PUD - OVERALL DEVELOPMENT PLAN - 40-94B - REPORTS - RECOMMENDATION/REPORT W/ATTACHMENTSthe introduction of the Phase 1 portion of the Lincoln East PUD, this intersection will continue to operate acceptably with no roadway or intersection improvements required. The site access intersections will also operate acceptably. By 2000, given development of Phase l of the proposed Lincoln East PUD and significant adjacent retail development, the Lincoln/Lemay intersection will continue to operate acceptably with geometric improvements. The additional lanes on Lemay Avenue are primarily due to the increase in background traffic. The site access intersections will operate acceptably with stop sign control. By 2015, with the projected traffic volumes, the key intersections will operate acceptably, with the mitigating improvements. TABLE 5 Long Range Peak Hour Intersection Operation Intersection Lincoln/Lemay (signal) Lemay/Access 1 (stop sign) EB LT/T/RT WB LT/T/RT NB LT SB LT Lincoln/Access 2 (stop sign) SB RT Lemay/Access 3 (stop sign) WB LT WB RT SB LT Lincoln/Access 4 (stop sign) SB LT SB RT -. EB LT Level of Service AM PM C D D D F F B B A B B C E F A B A B E F B D B B TABLE 3 Existing Plus Parcels A & B Traffic Peak Hour Intersection Operation Intersection Lincoln/Lemay (signal) Lemay/Access 1 (stop sign) EB LT/T/RT WB LT/T/RT NB LT SB LT Lincoln/Access 2 (stop sign) SB LT/RT EB LT Level of Service AM PM B B C B C C A A A B A B A A TABLE 4 Short Range Peak Hour Intersection Operation Intersection Lincoln/Lemay (signal) Lemay/Access 1 (stop sign) EB LT/T/RT WB LT/T/RT NB LT SB LT Lincoln/Access 2 (stop sign) SB RT Level.of Service AM PM C C C C C D A A A B A B Using the traffic volumes shown in Figure B, the key intersections operate as indicated in Table 3. Calculation forms for these analyses are provided in Appendix D. The Lincoln/Lemay signalized intersection will operate similarly to the current acceptable operation. The site access intersections operate acceptably. Using the short range peak hour- traffic volumes shown in Figure 9, the key intersections operate as indicated in Table 4. Calculation forms are provided in Appendix E. The key intersections are expected to operate acceptably. With this level of background 'traffic, the westbound left turns at the Lincoln/Lemay intersection will preclude full turn access at Access 2. This access will become "covered" a number of times during the peak hours. In order- to provide a safer environment, this access should be changed to right-in/right-out. While this change is shown to occur by the year 2000, it is in actuality a function of traffic volumes. This condition could occur sooner than or later than that year. Traffic should be monitored to determine when this change should be made. In order to achieve acceptable operation, Lemay Avenue should have 2 northbound and 2 southbound through lanes. Geometry and signal phasing schemes are indicated on the calculation forms provided in Appendix E. Using the traffic volumes shown in Figure 10, the Lincoln/ Lemay intersection operates in the long range future as indicated in Table 5. Calculation forms are provided in Appendix F. Acceptable operation is achieved with the warranted geometric, phasing and cycle length changes indicated on the calculation forms. The site access intersections operate acceptably, except for minor street left turns. The delays associated with these left turns are normal at stop sign controlled intersections along arterial streets. V. CONCLUSIONS This study assessed the traffic impacts of the development of the Lincoln East PUD on the existing, short range (1996) and long range (2015) street system in the vicinity of the proposed. development. As a result of this analysis, the following is concluded: - The completion of the Lincoln East PUD is feasible from a traffic engineering standpoint. The Lincoln East PUD is expected to generate approximately 1570 trip ends daily in the short range future and 2910 trip ends daily in the long range future. A portion of the Phase 1 generated traffic will be from passby traffic. Based upon current traffic volumes and existing geometry/ control, the Lincoln/Lemay intersection operates acceptably. With i r 5 I 1� LO n �� �LO o - 15/20 `O - C" + NOM. �-- 35/35 5/5 -1 + I NOM. 5/15 --, �n Ln o tn NO "-, 0 rn co O Wj1=_ 230/450 1n u°'+$ 195/470 180/290 r— f 590/1195 35/90 845/840 290 305 rn 105/185 N!� O LONG RANGE (YEAR 2015) PEAK HOUR TRAFFIC C� AM/PM Rounded to the Nearest 5 Vehicles. Figure 10 N KAWULOK PROJECT 5/5 --- NOM. 5/15 --� B 10/15 t �- NOM. -- - /- 30/30 1 O �1Ca CD C, _--� r N� to I A I.__. \---165/325 - 140/340 ,r-130/225 25 65 -� 210 220-� 75/135- Lo 5/10 ) 420/875 615/605 - AM/PM Rounded to the Nearest 5 Vehicles. SHORT RANGE (YEAR 2000) PEAK HOUR TRAFFIC Figure 9 N KAWULOK PROJECT w J Lo B �-10/15 Ito UD +Nom. l_ /— 24/23 O NOM. a � ^" 2/13 — c � M^� A 2 _w N g - 46/170 a N — 92/190 27/96 fit-- 5/6 �- ..- 151/442 21 /47 - 20 15 -� 346O47 -� 163/86 -�- a, 37/39--� �Ln ca w AM/PM EXISTING PLUS PARCELS A AND B PEAK HOUR TRAFFIC Figure 8 FULL DEVELOPMENT SITE GENERATED TRAFFIC Figure 7 M PARCELS A AND B SITE GENERATED TRAFFIC Figure 6 Trip Assignment Trip assignment is how the generated and distributed trips are expected to be loaded on the street system. The assigned trips are the resultant of the trip distribution process. Figures 6 and 7 show the assignment of the generated trips in the respective short and long range future conditions. The cited traffic impact study was used to develop the background traffic. The initial phase of development included the existing traffic plus the Kawulok Lemay Project and Parcels A and B of Lincoln East PUD. This traffic forecast is shown in Figure 8. The short range peak hour traffic is shown in Figure 9. This forecast includes the expected traffic from a Power Center development that is being considered east of Lemay Avenue, between -Mulberry Street and Lincoln Avenue. This Power Center will likely include discount retail, general retail, movie theaters, and restaurants. The short range traffic shown in Figure 9 includes Parcels A and B of the Lincoln East PUD. Figure 10 shows the morning and afternoon weekday peak hour traffic from full development of the Lincoln East PUD and the background traffic in the long range future (2015). The forecasts shown in Figures 9 and 10 give a reasonable representation of nearby development. When other development proposals are put forth for other properties, -'additional traffic studies should be performed. IV. TRAFFIC IMPACTS AND ANALYSIS Signal Warrants As a matter of policy, traffic signals are not installed at any location unless warrants are met according to the Manual on Uniform Traffic Control Devices. From the short and long range forecasts (Figures 9 and 10), no additional signals will likely be warranted. Operation Analysis Capacity analyses were performed on the key intersections in the vicinity of the proposed Lincoln East PUD. The key intersections are the Lincoln/Lemay intersection and the four site access intersections described earlier. Analyses were performed for the existing plus site traffic, short range (2000) traffic, and the long range (2015) traffic conditions. 4 N 20%-25% 25%-30% RETAIL USES 0 I L0 Lo Lo I 0 U" LINCOLN 5%-10% 0%-5% INDUSTRIAL / EMPLOYMENT USES TRIP DISTRIBUTION 4 N Figure 5 lam I I I I I I I I I I ` I � o I 1 I I 11 -1— - - 1 ham. 0 4 4 l l LINCOLN A VENUE A& N NO SCALE PARCELS A AND B SITE PLAN Figure 4 of the access intersections are numbered.for easy reference later in this report. It is expected that Lincoln East PUD will be implemented in a phased development program. Parcels A and.B will comprise the first phase. These two buildings will be built as soon as possible after the approvals are secured. A site plan of Parcels A and B is shown in Figure 4. Full development will occur sometime between the year 2000 and the year 2015.. The long range (2015) future assumes full development of the Lincoln East PUD. Trip Generation �1 Trip generation is important in considering the impact of a ( development such as this upon the existing and proposed street system. A compilation of trip generation information was prepared by the Institute of Transportation Engineers and is presented in Trip Generation 5th Edition, updated in February 1995. These documents were primarily used to project trips that would be generated -by the proposed uses at this site. Table 2 shows the expected trip generation on a weekday and a weekday peak hour basis. Land use code 846 (Gasoline/Service Station with Convenience Market with a Car Wash) and Code 833 (Fast Food Restaurant without a Drive -Through Window) were used in developing the trip generation forecasts for Parcel A. The cited reference does not address quick lube facilities. Data for this use was obtained from a local 3-bay facility. This data covered an eight month period from October 1995 to May 1996. The use on Parcel C will be auto -oriented retail/service. Code 840 (Auto Care Center) was used to develop the trip generation for this parcel. Parcels D and E will be employment uses similar to the Airport Industrial Park. Code 110 (General Light Industrial) was used to develop this trip generation. I Trip Distribution Directional distributions were determined for the auto related service/retail uses and the industrial/employment uses. These distributions considered trip attractions and productions in Fort Collins, and existing travel patterns in the area. Figure 5 shows the trip distribution used in the traffic assignment process. Institute.of Transportation Engineers' research indicates that the convenience/gas store and fast food restaurant land uses draw approximately 40-60% of their patrons from the background traffic on the adjacent streets. Therefore, a passby factor of 0.40 was applied to the peak hour generated traffic. This factor does not affect the trip generation. The passby traffic is determined based upon the actual volumes on the adjacent streets. 3 I AI OVERALL SITE PLAN Figure 3 TABLE 1 S' 1996 Peak Hour Intersection Operation Level of Service Intersection AM PM i! Lincoln/Lemay (signal) B B TABLE 2 Trip Generation Daily A.M. Peak P.M. Peak Land Use Trips Trips Trips Trips Trips in out in. out PARCEL A Gas/Convenience Store Gas - 8 Positions 1170 44 43 50 50 Quick Service Restaurant 400 11 8 11 9 0.5 KSF Subtotal Parcel A 1570 55 51 61 59 PARCEL B Quick Lube - 3 bays 150 3 3 7 7 PARCEL C Auto Related Retail/Service 250 9 5 6 9 6.0 KSF PARCEL D Light Industrial - 58.0 KSF 400 44 9 7 50 PARCEL E Light Industrial - 77.0 KSF 540 59 12 9 66 TOTAL 2910 170 60 92 191 Aw N } a W J S, �� co o o �-- 45/170 1 — 88/187 /-19/89 19/45 —� 155/80 - 37/39 `N7 w� wn cn 1996 PEAK HOUR TRAFFIC LINCOLN AM / PM Figure 2 existing cross section in this area has one lane in each direction. There are designated. left -turn lanes approaching the Lincoln/Lemay intersection. This intersection is signalized. The postedspeed limit is 35 mph .east of Lemay Avenue and 30 mph west of Lemay Avenue. Sight distance is generally not a problem. There are bike lanes on Lincoln Avenue to the west of Lemay Avenue. North Lemay Avenue borders the site on the west. It is designated as a major (4 lane) arterial. However, it currently has a two lane cross section with designated. left -turn lanes approaching the Lincoln/Lemay intersection. The south leg has a designated right -turn lane also. The posted speed limit is 30 mph on North Lemay Avenue. There are bike lanes on both sides of Lemay Avenue. Long range transportation plans indicate that North Lemay Avenue will be realigned north of this site. The plans show.Lemay Avenue angling to the northeast. It will pass east of the aforementioned residential area, and probably cross the railroad and Vine Drive on a grade separation. Timing of this realignment is not known. It is assumed that it will not occur prior to the year 2010. A draft of the "Structure Plan" of the Fort Collins City Plan does not show this realignment of Lemay Avenue. Existing Traffic Weekday morning and afternoon obtained on January 10;• 1996 at the The peak hour turning movements are traffic data is presented in Appendix Existing Operation Using the traffic signal control, the indicated in Table 1. provided in Appendix during the peak hours. of service D or better. in Appendix C. III peak hour traffic data was Lincoln/Lemay intersection. shown in Figure 2. All raw A. volumes shown in Figure 2 and the existing Lincoln/Lemay intersection operates as Calculation forms for these analyses are 1. This intersection operates acceptably Acceptable operation is defined as level Level of service definitions are provided PROPOSED DEVELOPMENT The initial phase of the Lincoln East PUD will be a convenience/gas store, proposed to be located in the northeast quadrant of the Lincoln/Lemay intersection in Fort Collins. Figure 3 shows a schematic of the overall site plan of the Lincoln East PUD. Two accesses are proposed to Lemay Avenue and one access is proposed to Lincoln Avenue. An "off -site" access is shown just east of the site. This is expected to be a public street access that will also serve the Airport Industrial Park to the east. All 2 mm - - - � two 0 (.�I. c,.D 3 hn.Dy ^'f j o" L.I. �t1 • . J 1 ���,�Jw'„«I,� �, aka • 1 S.. iiiiiiii \ 1 1 W •_,.1, LINCOLN EAST PUD w sx .IUCOLN �� a Q111--li rr [ 1 11 ` \\ I •■ aI Y per ! f�. ( l• (1. •. Y aafr \�``\\" Y i D^�• Ia =� 6•�1:•11 =[ II .11 [I .r i^ /I%�A�x� NO SCALE SITE LOCATION Figure 1 I. INTRODUCTION This traffic.impact study addresses the capacity, geometric, and control requirements at and near a proposed commercial development known hereinafter as the Lincoln East PUD. It is proposed to be located north of Lincoln Avenue and east of North Lemay Avenue in Fort Collins, Colorado: During the course of the analysis, numerous contacts were made with the project planning consultant (Cityscape Urban Design), and the Fort Collins Transportation Division. This study conforms with typical traffic impact study guide.lines. The study involved the following steps: - Collect physical, traffic, and development data. - Perform trip generation, trip distribution, and trip assignment. - Determine peak hour traffic volumes. - Conduct capacity and operational level of service analyses on key intersections. - Analyze signal warrants. The "Kawulok Lemay Avenue Project, Traffic. Impact Study," July 1995, was also reviewed as part of this analysis. II. EXISTING CONDITIONS The location of the Lincoln East PUD site is shown in Figure 1. Since the impact in the short range, as well as, the long range is of concern, it is important that a thorough understanding of the existing conditions be presented. Land Use This area of Fort Collins primarily has various light industrial and commercial uses. However, there is a small residential area approximately 1200 feet north of the site. Land uses to the east are light industrial. Land to the south of Lincoln Avenue is vacant and will likely be developed as commercial/retail. Land on the west side of Lemay Avenue has some light industrial uses. The center of Fort Collins lies to the west of the Lincoln East PUD. Roads The primary streets near the Lincoln East PUD Avenue and North Lemay Avenue. Lincoln Avenue borders East PUD site on the south. It is an east -west street as a minor arterial on the Fort Collins Master Street 1 are Lincoln the Lincoln designated Plan. Its e!�Wf 7- L/n1 Co 1- Al (40iR/) a p-14AP7440x NEIGHBORHOOD INFORMATION MEETING Did you receive Correct zipwritten notification Address? CODE of this meeting? NAME ADDRESS YES7 NO YES NO A/ 11, r— L_—DOA,l SC C— A LWL&J A , RO K cam° s� �Ec-pjl )3as ,4A R D -77 7 GYI Cr s L CONCEPTUAL DRAINAGE: OVERALL UTILITY: THE SUBJECT PROPERTY IS LOCATED IN A FLOOD HAZARD ZONE AE ACCORDING TO THE LATEST F.I.R.M. THE SUBJECT PROPERTY DRAINS EAST AND SOUTHEAST TO THE EXISTING DITCH ALONG THE NORTH R.O.W. OF LINCOL.N AVENUE. STORMWATER DETENTION SHOULD BE EVALUATED FOR EACH INDIVIDUAL SITE AS THE SITES ARE DIVIDED FROM THE OVERALL PARCEL. DEVELOPMENTS SHALL CONFORM WITH ITY STORMWATER REGULATIONS IN EFFECT AT THE TIME OF P.U.D. SUBMITTAL. CITY SANITARY SEWER MAIN EXISTS FLOWING SOUTH TO NORTH THROUGH THE SUBJECT PROPERTY. DEVELOPMENT MAY BE SERVED BY THIS MAIN SUBJECT TO THE MAIN'S CAPACITY, CITY WATER MAINS EXIST IN LEMAY AVENUE AND LINCOLN AVENUE. AS FUTURE SITES DEVELOP, THEY MAY BE SERVED BY THESE MAINS. IF DEVELOPMENT WARRANTS, NEW WATER MAINS MAY BE INSTALLED THROUGH THE SUBJECT PROPERTY ALONG INTERNAL ACCESS ROADS TO LOOP THE CITY MAINS, THE NECESSITY OF NEW WATER MAINS SHOULD BE EVALUATED BASED ON THE NEEDS OF FUTURE DEVELOPMENT AND ADEQUATE FIRE PROTECTION. LINCOLN EAST ODP and PHASE I PRELIMINARY PUD Statement of Planning Objectives August 26, 1996 The proposed Lincoln East development, located at the intersection of East Lincoln Avenue and North Lemay Avenue, is anticipated to comprise up to 164,000 t sq. ft. of mixed Business Services, Industrial, and Auto Related Convenience uses. The business service and auto related uses will complement the retail shopping center anticipated to be constructed immediately south of the subject property to provide the surrounding industrial, residential, and recreational properties with a variety of goods and services not readily available at this time. The project is within walking distance of the existing transit route #8 (Vine and Lemay); and is planned in keeping with the concept of encouraging the efficient utilization of existing and proposed street and utility systems. The proposed development is consistent with adopted City Land Use Policies which promote development near transportation facilities, and where existing infrastructure is in place. Specific applicable Land Use Policies including 3.a, 3.b, 3.d, 15, 18, 20, 21, 22, 25, 26, 29, 39, 40, 50, 51, 55, 57, 59, 60, 61, 62, and 74. The convenience store proposed with the first phase of development will comply with the Model Energy Code as adopted by the State of Colorado. The store will utilize double pane windows, wall and ceiling insulation, an HVAC economizer to "free cooling" air during early morning or late day operations, and/or other standard techniques. Construction is anticipated to begin in 1997. 200 to 300 people are projected to be employed in this development. LINCOLN EAST OVERALL DEVELOPMENT PLAN ESTIMATED LAND USE BREAKDOWN August 26, 1996 PARCEL POSSIBLE LAND USE GROSS AREA A BUSINESS SERVICES/AUTO RELATED 1.7 ACt B BUSINESS SERVICES/AUTO RELATED .7 ACt C BUSINESS SERVICES/AUTO RELATED .7 ACt D BUSINESS SERVICES/INDUSTRIAL 5.3 ACt E BUSINESS SERVICES/INDUSTRIAL 7.1 ACt TOTALS: MAXIMUM FLOOR FLOOR AREA AREA RATIO 15,000 SF 1:5 t 6,000 SF 1:5 t 8,000 SF 1:4 t 58,000 SF 1:4 t 77,000 SF 1:4 t 15.5 ACt 164,000 SF * ACTUAL MIX OF USES IS TO BE DETERMINED WITH SPECIFIC DEVELOPMENT PLANS FOR EACH PARCEL. LINCOLN EAST OVERALL DEVELOPMENT PLAN PROPERTY DESCRIPTION August 26, 1996 A PARCEL OF LAND SITUATED IN THE NW 1 /4 OF SECTION 7, T.7N., R.68W., OF THE 6TH P.M., LARIMER COUNTY, COLORADO, MORE PARTICULARLY DESCRIBED AS FOLLOWS: COMMENCING AT THE SW CORNER OF THE NW 1 /4 OF SAID SECTION 7; THENCE NO2'04'03" E ALONG THE WEST LINE OF SAID NW 1 /4 A DISTANCE OF 40.01 FEET; THENCE S89'27'44" E PARALLEL WITH THE SOUTH LINE OF SAID NW 1 /4 A DISTANCE OF 75.01 FEET TO A POINT LYING AT THE INTERSECTION OF THE NORTHERLY R.O.W. LINE OF EAST LINCOLN AVENUE AND THE EASTERLY R.O.W. LINE OF NORTH LEMAY AVENUE BEING THE SOUTHEASTERLY CORNER OF THAT PARCEL OF LAND DESCRIBED IN BOOK 1974 AT PAGE 581 OF THE LARIMER COUNTY, COLORADO RECORDS, SAID POINT BEING THE POINT OF BEGINNING; THENCE N12'51'17"W ALONG SAID EASTERLY R.O.W. LINE AND THE EASTERLY LINE OF SAID PARCEL DESCRIBED IN BOOK 1974 AT PAGE 581 A DISTANCE OF 174.69 FEET TO THE NORTHERLY CORNER OF SAID PARCEL DESCRIBED IN BOOK 1974 AT PAGE 581; THENCE NO2'04'03"E PARALLEL WITH THE WEST LINE OF SAID SECTION 7 AND CONTINUING ALONG SAID EASTERLY R.O.W. LINE A DISTANCE OF 782.79 FEET; THENCE S87'55'57"E A DISTANCE OF 791.00 FEET; THENCE S02'04'03"W PARALLEL WITH THE WEST LINE OF SAID NW 1 /4 A DISTANCE OF 971.68 FEET TO A POINT LYING ON THE SOUTH LINE OF SAID NW 1 /4, SAID POINT ALSO LYING ON THE NORTHERLY R.O.W. LINE OF EAST LINCOLN AVENUE AS SHOWN ON THE LARIMER COUNTY, COLORADO ASSESSOR MAPS; THENCE N89'27'44'W ALONG SAID NORTHERLY R.O.W. LINE AND THE SOUTH LINE OF SAID NW 1 /4 A DISTANCE OF 159.58 FEET TO A POINT LYING NON -TANGENT ON A CURVE; THENCE ALONG A CURVE TO THE LEFT WHOSE CHORD BEARS N82'03'47"W A DISTANCE OF 310.62 FEET AND CONTINUING ALONG SAID NORTHERLY R.O.W. LINE, SAID CURVE HAVING A CENTRAL ANGLE OF 14747'53", A RADIUS OF 1206.00 FEET, AN ARC LENGTH OF 311.48 FEET TO A POINT OF TANGENT; THENCE N89'27'44"W ALONG SAID TANGENT AND CONTINUING ALONG SAID NORTHERLY R.O.W. LINE PARALLEL WITH THE SOUTH LINE OF SAID NW 1 /4 A DISTANCE OF 277.60 FEET TO THE POINT OF BEGINNING. PARCEL CONTAINS (751 ,962 SQUARE FEET) 17.263 ACRES. euerEee eRnvlr<e . � aD aaximaE GENERAL NOTES III I i / �\ 1 r-, III I II III � I I I I ' I I I I I I I I I i I / ' I _ ' •rn• .r.wrx • I.ww s r ®p+s s a'r a K � I. ,K.m�a wwMnnb�Im:.m,.. a t. w l a� �,',� '1. a. l.s..l. a r :..wa .., ..s. .em.�d �o sDs. �. a..y....,.aL±r.+lr .•r x, «...r o° r : °r. a ..,xx ..«.�,� w:, •�=..•••. •D EffTWTED LAW UM IIEAIO)OMM a. 4*ry amp 4 I - JM xww1M Mn a •U.D, avM,m. PM L PoSSIBIF IANO USE GIG55 MG ..u. `.W _ "'"••. aoo• Mu axu wno .smr•"' `"' ` "wa ••°i' a eu° slresz /aY�',.J RL ) an !i u.000 sr .s a eJvluss scmncEs//wmurzo icx e800 .s�E i i °'^pn�'n •'ym'u^. ' uv m4L ^'� a^'^•^•. a tdi� D E BULMESS SEINYtY/iMV51RLLL n11SINESS SERVES/IIpV51RNt 9.J M3 ),I Kd Y,DCO Y )),DCU $ 1:. S 1 � 4 twv uM��n cmv .r•� I�w[L a ou,�'wfa• �Yu�� NLNS 13! M! IN.WD 4 • /LIWL IW pE Y9E5 9 N BE RIEIBIWfp WIIX 9PECIi1C UEYEIOWEMf %MIS fUR FMM VAW:R. LEGAL DESCRPTION x.xm r..• I+si.r m.. an �.aw.,a VICINITY MAP CONTEXT DIAGRAM D4 rvn� �,,, oEvaovL�Nr -B.A V.A. 2 i • � IEIOMBONIDODS A oR rxE E I-AIVONT `- DEveLDrNKJ j NDueTRAL NXIBTWAL � TgANBPORTAIIDN LMfb •'oPS�I'.R m < aM a •`G i F ��� FiIiUNE 1 I GOLF COWBE — R?TAA ' O HlHH(c(aHlEko]PUB � OVERALL DEVELOPMENT PLAN T Y �=4 — • SIGNATURE BLOCK r�saw.=.•o �+��a.rr.. ar.r... wr ar. rsaray•xn or. =. 9�rI > w M1•Iq w aay M. IP Buckin ham Street OUT L ur IL Z W a W J x Z ■ ■ ■ rq C /Iyca�N A�FNv 4`3 0 T F Link-N-Greens i Golf Course by VICINITY MAP 09/06/96 #40-9413 LINCOLN EAST PUD " Overall Development Plan 1"= 300' 11 oM ,! li]lik�q>4, i� Dvarall 13 Lincoln East P.U.D. - Overall Development Plan, #40-94B October 28, 1996 P & Z Meeting Page 8 ► Staff does not feel that the proposed ODP is inconsistent with the letter and spirit of the Land Use Policies Plan, or any of the specific policies contained therein; ► The proposed ODP is consistent with the existing, underlying it (Limited Industrial with a P.U.D. condition) zoning, and the proposed land uses are compatible with those that were anticipated at the time of annexation.; and, ► The Lincoln East ODP is feasible from a transportation perspective and meets City policies regarding transportation. RECOMMENDATION: Staff is recommending approval of the Lincoln East P.U.D. Overall Development Plan, #40- 94B. Lincoln East P.U.D. - Overall Development Plan, #40-94B October 28, 1996 P & Z Meeting Page 7 4. Transportation: The Transportation Department has reviewed the Site Access Study that was submitted with this ODP request and finds that the proposal is feasible from a transportation standpoint and meets City policies for transportation. The Site Access Study (Delich, August, 1996) that was submitted with this ODP request concluded that: ► "The completion of the Lincoln East PUD is feasible from a traffic engineering standpoint. The Lincoln East PUD is expected to generate approximately 1570 trip ends daily in the short range future and 2910 trip ends daily in the long range future. A portion of the Phase 1 generated traffic will be from pass by traffic." ► "Based upon current traffic volumes and existing geometry/control, the Lincoln/Lemay intersection operates acceptably. With the introduction of the Phase 1 potion of the Lincoln East PUD, this intersection will continue to operate acceptably with no roadway or intersection improvements required. The site access intersections will also operate acceptably." ► "By 2000, given development of Phase 1 of the proposed Lincoln East PUD and significant adjacent retail development, the Lincoln/Lemay intersection will continue to operate acceptably with geometric improvements. The additional lanes on Lemay Avenue are primarily due to the increase in background traffic. The site access intersections will operate acceptably with stop sign control." ► "By 2015, with the projected traffic volumes, the key intersections will operate acceptably, with the mitigating improvements." In summary, The proposed Lincoln East ODP is feasible from a transportation standpoint and meets City policies for transportation. FINDINGS OF FACT/CONCLUSIONS: In evaluating the request for the Lincoln East P.U.D. Overall Development Plan, staff makes the following findings of fact: ► The proposed Lincoln East P.U.D. Overall Development Plan is supported by policies 3a, 3b, 3d, 14, 15, 20, 21, 22, 26, 29, 39, 40, 50, 59, 60, 61, 62, and 74 of the Land Use Policies Plan (L.U.P.P.); Lincoln East P.U.D. - Overall Development Plan, #40-946 October 28, 1996 P & Z Meeting Page 6 #61) Industrial development should locate within the City or consistent with the phasing plan for the urban growth area, where the proper sizing of facilities such as water, sewer, and transportation has occurred or is planned. The property is an infill site where the provision of water and sewer, light and power, street capacities, and emergency response services could be accommodated without imposing undue stress on existing systems. Also, the site accesses the future Lemay Avenue bypass which will be built with adequate capacity. The traffic study done for this proposal demonstrates that the existing capacities of the transportation network would not be exceeded. #62) Neighborhood service centers may locate in less hazardous flood plain classifications provided proper mitigation of the flood hazard is provided ... This proposal would place neighborhood services in the floodplain, provided the City's Stormwater Utility and Flood Plain Administrator find that the development plans provide for proper mitigation of the flood hazard. #74) Transitional land uses or areas should be provided between residential neighborhoods and commercial areas in order to enhance the concept of a mixture of land uses. The Andersonville Subdivision and the San Cristo P.U.D., both of which are residential developments, are located approximately five -hundred feet to the north of this site. With this ODP, these residential developments would now be located close to employment and shopping facilities. Also, this site is surrounded on three side by industrial/light industrial lands. The business service uses will provide needed goods and services to the surrounding areas, while also providing an appropriate transition to the residential areas to the north and the planned business areas to the south. Staff does not feel that the proposed ODP is inconsistent with the letter and spirit of the Land Use Policies Plan, or any of the specific policies contained therein. 3. Neighborhood Compatibility: A neighborhood meeting was held on June 13, 1996 to discuss the proposed Lincoln East Overall Development Plan. As almost all of the surrounding properties are owned by various industries and businesses, attendance was minimal. In fact, a total of four (4) affected property owners attended, and none of them voiced opposition to the proposal. In addition, a "Development Proposal Under Review" sign has been posted on the subject property for more than two months, and the Planning Department has not been made aware of any opposition to the project. The proposed uses are found to be compatible with the surrounding area. Lincoln East P.U.D. - Overall Development Plan, #40-94B October 28, 1996 P & Z Meeting Page 5 #26) Availability of existing services shall be used as a criteria in determining the location of higher intensity areas in the City. The proposed ODP will be adequately serviced with water and sewer, light and power, street capacities, and emergency response services without imposing undue stress on existing systems. #29) City provided services and facilities shall be utilized as a tool to direct or discourage development in desired directions. The proposed ODP will be adequately serviced with water and sewer, light and power, street capacities, and emergency response services without imposing undue stress on existing systems. #39) The City should direct efforts to promote improved traffic and pedestrian circulation and public transit to areas north and northeast of the City. The project is within walking distance of the existing transit route #8 (Vine and Lemay). Also, street improvements will be subject to the new street standards, thus bike lanes and detached sidewalks will be required. #40) The City should promote the utilization of existing vacant land in the northeast ... The requested ODP proposes development in the northeast that cannot be characterized as "leapfrog" development. #50) Mass transit should be used as a tool which leads development patterns, rather than following growth. The project is within walking distance of the existing transit route #8 (Vine and Lemay). #59) Industrial uses may locate in less hazardous flood plain classifications provided proper mitigation of the flood hazard and water quality is preserved... This proposal would place industrial uses in the floodplain, provided the City's Stormwater Utility and Flood Plain Administrator find that the development plans provide for proper mitigation of the flood hazard and preservation of water quality. #60) Industrial uses should locate near transportation facilities that offer the required access to the industry but will not be allowed to create demands which exceed the capacity of the existing and future transportation network of the City. The project is within walking distance of the existing transit route #8 (Vine and Lemay). The traffic study done for this proposal demonstrates that the existing capacities of the transportation network would not be exceeded. Lincoln East P.U.D. - Overall Development Plan, #40-9413 October 28, 1996 P & Z Meeting Page 4 #3b) The City shall promote alternative transportation modes. The project is within walking distance of the existing transit route #8 (Vine and Lemay). Also, street improvements will be subject to the new street standards, thus bike lanes and detached sidewalks will be required. #3d) The City shall promote the location of residential development which is close to employment, recreation, and shopping facilities. The Andersonville Subdivision and the San Cristo P.U.D., both of which are residential developments, are located approximately five -hundred feet to the north of this site. With this ODP, these residential developments would now be located close to employment and shopping facilities. #14) Urban development standards shall apply to all development within the urban growth area. The new street standards will apply to this development; Water and sanitary sewer service will be provided through the existing mains adjacent to each parcel; fire hydrants and street lighting will be installed. #15) Development in the urban growth area should be consistent with development policies set forth in this plan. The explanation/discussion of this policy states that "such development should occur in a logical fashion in a manner which justifies the cost of service extensions." This development is wholly within the city limits and will be served by existing street and utility systems. #20) Land use, site planning, and urban design criteria shall ... promote pleasant, functional and understandable inter -relationships through and between land uses. This site is surrounded on three side by industrial/light industrial lands. The business service uses will provide needed goods and services to the surrounding areas, while also providing an appropriate transition to the residential areas to the north and the planned business areas to the south. Urban design criteria will be applied as individual development proposals are submitted and reviewed. #21) All levels of commercial development ... will be discouraged from gaining their primary access from College Avenue. This ODP does not, in any way, access College Avenue. #22) Preferential consideration shall be given to urban development proposals which are contiguous to existing development within the city limits or consistent with the phasing plan for the City's urban growth area. The proposed ODP is contiguous to urban development within the city limits, and will be served by existing utility and street systems. Lincoln East P.U.D. - Overall Development Plan, #40-94B October 28, 1996 P & Z Meeting Page 3 The proposed ODP's business service and auto -related uses will complement the retail shopping center anticipated to be constructed immediately south of the subject property to provide the surrounding industrial, residential, and recreational properties with a variety of goods and services not readily available at this time. The site is within walking distance of the existing transit route #8 (Vine and Lemay), and is planned in keeping with the concept of encouraging the efficient utilization of existing and proposed street and utility systems. The proposed ODP is consistent with the underlying il, Limited Industrial, zoning. Further, the proposed land uses are the same as those that were anticipated at the time of annexation. Therefore, it can logically be concluded that the Lincoln East ODP is appropriate at the proposed location. Consistency with the City's Land Use Policies Plan: The adoption of the Land Use Policies Plan was based on the Existing Land Use Report (November, 1977) that contains detailed statistics on the functional and economic uses of land within the City. The report's basic purpose was to establish an understanding of the existing pattern of land and to present an analysis of land use problems to be utilized in the land use planning process. The Land Use Policies Plan is divided into three chapters: ► Chapter I presents definitions of the terms and phrases which are commonly used in the document. ► Chapter II presents the policies of the enabling resolution and an explanation/discussion of the intent of each policy. ► Chapter III presents a listing of additional policy packages, programs, and projects, along with a schedule for completion of the items required by the policies presented in the document. The policies contained in the Land Use Policies Plan are intended to provide decision - makers with initial guidelines to evaluate land use issues in a manner which will assure a continued high quality of life in Fort Collins. The proposed Lincoln East ODP is consistent with the following land use policies: #3a) The City shall promote maximum utilization of land within the City. The Lincoln East ODP proposal would provide the surrounding industrial, residential, and recreational properties with a variety of goods and services not readily available at this time, as well as efficient utilization of existing and proposed street and utility systems. Lincoln East P.U.D. - Overall Development Plan, #40-94B October 28, 1996 P & Z Meeting Page 2 COMMENTS: 1. Background: The surrounding zoning and land uses are as follows: N: OUT & IL; an undeveloped, unincorporated parcel and undeveloped Fort Collins Business Center land. S: bp; vacant/undeveloped; E: IL; undeveloped Fort Collins Business Center; W: IL; North Lemay (industrial) Subdivision, Second Filing (partially developed). This 17.263 acre site was annexed into the City of Fort Collins as the "East Lincoln Third Annexation and Zoning," Ordinance Numbers 164 and 165, 1994. When annexed, the site was zoned it - Limited Industrial with a P.U.D. condition. The Agenda Item Summary that recommended the adoption of Ordinances 164 and 165, 1994, stipulated that the applicant anticipated the following uses to be developed on the property: "a convenience store, other convenience related retail uses, and, possibly, some light industrial uses." 2. Land Use: This is a request for approval of an Overall Development Plan (ODP) for a 17.263 acre parcel located at the northeast corner of East Lincoln Avenue and North Lemay Avenue. The ODP is anticipated to comprise up to 164,000 square feet of mixed business services, industrial, and auto -related convenience uses. The proposed Lincoln East Overall Development Plan contains five parcels with the following Land Use Breakdown': IPARCELI POSSIBLE LAND USE GROSS AREA MAXIMUM FLOOR AREA A Business Services/Auto-Related 1.7 acres f 15,000 square feet B Business Services/Auto-Related .7 acres t 6,000 square feet C Business Services/Auto-Related .7 acres f 8,000 square feet D Business Services/Industrial 5.3 acres f 58,000 square feet E Business Services/Industrial 7.1 acres t 77,000 square feet TOTALS: N/A 15.5 acres f 164,000 square feet i Actual mix of uses is to be determined with specific development plans for each parcel. Churches, schools, and public or private community services, including day care centers, and multi -family residential uses are to be allowed as alternative land uses in all parcels. ITEM NO. 2 MEETING DATE 10/28/96 STAFF Mitch Haas City of Fort Collins PLANNING AND ZONING BOARD STAFF REPORT PROJECT: Lincoln East P.U.D. - Overall Development Plan, # 40-94B APPLICANT: Diamond Shamrock Refining and Marketing, Inc. % Cityscape Urban Design, Inc. 3555 Stanford Road, Suite 105 Fort Collins, CO 80525 OWNER: Webster Associates 60 East Service Road 1-25 Cheyenne, WY 82007 PROJECT DESCRIPTION: This is a request for approval of an Overall Development Plan (ODP) for a 17.263 acre parcel located at the northeast corner of East Lincoln Avenue and North Lemay Avenue. The ODP is anticipated to comprise up to 164,000 square feet of mixed business services, industrial, and auto -related convenience uses. The ODP is bounded by North Lemay Avenue to the west, East Lincoln Avenue to the south, and the Fort Collins Business Center (largely undeveloped) to the east and north. The entire ODP site is in the it - Limited Industrial, with a P.U.D. condition, Zoning District. RECOMMENDATION: Approval EXECUTIVE SUMMARY: This request for approval of the Lincoln East O.D.P.: ► is supported by policies 3a, 3b, 3d, 14, 15, 20, 21, 22, 26, 29, 39, 40, 50, 59, 60, 61, 62, and 74 of the Land Use Policies Plan (L.U.P.P.); is consistent with the existing it (Limited Industrial) zoning; and, ► is feasible from a transportation standpoint and meets City policies for transportation. COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 (303) 221-6750 PLANNING DEPARTMENT