HomeMy WebLinkAboutNEW BELGIUM, 4TH FILING, PACKAGING HALL & BUCKINGHAM ST. - PDP & AMENDED ODP - 1-95F - CORRESPONDENCE - STAFF'S PROJECT COMMENTS (7)Topic: F/oodplain Comments
Number: 2 Created: 8/29/2005
[12/28/05]
[8/29/05]
Because the packaging facility and associated chemicals already exist on the site, per City
Code Section 10-46, a non -conforming critical facility can be relocated with in the same
parcel of land and not lose its legal non -conforming status. To document this, please
complete a floodplain use permit ($25 permit fee). The Hazardous Materials Impact
Analysis will be attached to the permit as this documentation. It is recommended that any
chemical storage be at an elevation above the 500-year flood. Please contact Marsha
Hilmes-Robinson at 224-6036 for questions.
Topic: Irrigation Line
Number: 3 Created: 8/29/2005
[12/28/05]
[8/29/05] The proposed plan would enclose the existing Coy Ditch irrigation ditch into a
pipe. Please provide a signature on the plans from representatives of the ditch company.
Check how the tree on the south side of Buckingham will be affected.
Topic: Landscape Plan
Number: 81 Created: 12/28/2005
[12/28/05] The street trees along Buckingham look to be only 4 feet from the proposed
storm sewer that parallels Buckingham. A 10-foot separation is required. It is
recommended that a meeting between Stormwater, Engineering, Planning and the
applicant's engineer and landscape architect be set up to try to come up with an acceptable
solution. It is suggested that the storm line be realigned to be in between the Coy Ditch line
and the trees. Special care should be taken to place manhole lids outside of the sidewalk
area.
Topic: Storm Sewer Profiles
Number: 64 Created: 12/20/2005
[12/20/05] At final please provide storm sewer profiles. Check at this point and see whether
the existing. utilities in 1st Street would conflict with the proposed storm lines.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Water/WW
Number: 19 Created: 9/1/2005
[12/21/05] We just need to remember to address the pipe bridge crossing the sewer
easement:
[9/1/05] We will attempt to work with the pipe bridge as shown. I will check with the City
Attorney's office to see if there may be any special requirements such as hold harmless
agreements, etc.
Number: 65 Created: 12/21 /2005
[12/21/05] Provide easement for the re -located fire hydrant.
Number: 66 Created: 12/21 /2005
[12/21/05] Connect the domestic water service and the fire line to the 12-inch main.
Page 4
Department: PFA Issue Contact: Ron Gonzales
Topic: Fire
Number: 82 Created: 12/28/2005
[12/28/051 Corrosives, flammable liquids, or reactive or toxic materials (as defined in the
Uniform Fire Code), if used, stored or handled on this site, must have a Hazardous Materials
Impact Analysis (HMIA) completed and supplied to the Fire Department and the Planning
Department.
Department: Transportation Planning Issue Contact: David Averill
Topic: Buckingham Street Plans
Number: 34 Created: 9/13/2005
[12/21/05] Repeat comment. You may have included this on the utility plans but it does not
show up on the site plan I was routed. Thanks.
[9/13/05] Buckingham Road Improvements plan set - show a Type III barricade at the east
end of the 8' walk where it terminates. Thanks.
Topic: General
Number: 8 Created: 8/30/2005
[12/21/05] The amended TIS is still lacking in analysis with regards to Pedestrian Level of
Service Standards. Only one destination area (Other) was included. At a minimum, the
consulting engineer needs to include Old Fort Collins Heritage Park, Buckingham Park, and
the residential neighborhood to the south of this project as likely pedestrian destinations. If
a PIED LOS standard cannot be met, it must be stated as to why that standard cannot be
met - be it hardship, constructability, etc.
[8/30/05] The TIS as submitted is incomplete. There is a narrative that addresses
Bike/Ped/Transit LOS but none of the worksheets to support those conclusions are included.
Please have your consulting traffic engineer contact me directly so that we can adequately
address this issue. Thanks.
Department: Stormwater-Water-Wastewater Issue Contact: Basil Hamdan
Topic: Drainage Plan
Number: 62 Created: 12/20/2005
[12/20/05] At final a drainage easement will be required for the area on the south side of
Buckingham that will be used as temporary detention.
Number: 63 Created: 12/20/2005
[12/20/05]
Please make sure that off -site flows are not directed through the temporary detention pond.
Currently the design shows two storm lines discharging into the temporary pond.
Topic: Drainage Report
Number: 80 Created: 12/28/2005
[12/28/05] In calculating the required detention for the off -site pond, the output from the on -
site detention pond is factored into the design, however the 4.4 cfs coming from the inlets on
Buckingham Street were not included in the analysis. Since these inlets will be draining into
that pond their contribution should be added to the input to the off -site pond.
Page 3
Topic: General
Number: 23 Created: 9/2/2005
[12/21/05] This does not appear to have been addressed.
[9/2/05] Show the eastern lot line boundary on the site plan, landscape plan, and
construction plans to verify how the improvements coincide with the eastern boundary of Lot
1 of this development.
Number: 24 Created: 9/2/2005
[12/21/05] Please clarify beyond the note provided with limits of where the under -grounding
is proposed. Is it along the PDP boundary only, all of Buckingham, etc.?
[9/2/05] Provide information regarding the under -grounding of the overhead line as it lies
within the proposed street improvements.
Number: 27 Created: 9/2/2005
[12/21/05] Appears to be unrevsolved.
[9/2/05] A letter of intent is required from the Coy Ditch Company for the work proposed by
the development.
Number: 83 Created: 12/28/2005
[12/28/05] The storm sewer manholes behind the curb along Buckingham Street appear to
be partially in the Buckingham sidewalk; there needs to be a separation from the sidewalk
as prescribed in Figure 16-1 of LCUASS.
Topic: Plat
Number: 29 Created: 9/2/2005
[12/21/05] Appears to be unresolved. The plat shows an irrigation easement while the
certificate of dedication states easements are conveyed to the City and the irrigation line is
not the City's.
[9/2/05] The plat indicates an "irrigation easement" which appears to be dedicated with the
plat. As the dedication statement dedicates all easements to the City, it appears this ditch
easement should be indicated otherwise. More than likely, an easement will need to be
dedicated to the Coy Ditch Co. by separate document, with the recording information
provided on the plat.
Department: Natural Resources Issue Contact: Doug Moore
Topic: Existing Trees
Number: 73 Created: 12/21 /2005
[12/21/05] Contact Tim Buchanan, the City Forester to see if any existing trees are
considered to be significant and if they will need to be preserved or mitigated.
Number: 74 Created: 12/21 /2005
[12/21/05] Please add the tree preservation standard to the general note on the utility plans.
Make sure to show the location of the protective fence on the appropriate plans and provide
a detail showing how the fence is to be installed.
Number: 75 Created: 12/21 /2005
[12/21/05] The construction of the temporary detention pond on the parcel to the south of
the project site is allowed within the buffer zone of the existing riparian forest. NRD will not
require this disturbance within the buffer zone to be re-vegbtated with Fort Collins native
species since this is just a temporary location that will be relocated in the near future.
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
BHA DESIGN, INC. Date: 01/04/2006
LUKE OLDENBURG
4803 INNOVATION DR.
FORT COLLINS, CO 80525
Staff has reviewed your submittal for NEW BELGIUM BREWERY, PACKAGING HALL &
BUCKINGHAM ST PDP & AMENDED ODP - TYPE ll, and we offer the following comments:
ISSUES:
Department: Engineering Issue Contact: Marc Virata
Topic: Buckingham Street Plans
Number: 35 Created: 9/13/2005
[12/21/05] This appears to be unresolved.
[9/13/05] We will need buy off from the utility companies that the 9' utility easement behind
the irrigation easement is acceptable given that the utility easement is no longer joined by
street right-of-way.
Number: 41 Created: 9/13/2005
[12/21/05] The profile sheet for the Coy Ditch does not show a proposed grade line to see if
this issue was resolved.
[9/13/05] The amount of cover over the crossing in which the realigned ditch ties into is less
than standard. That combined with the structure being corrugated metal raises a general
concern. We would want to see the corrugated metal pipes removed and replaced with twin
elliptical pipes (RCP?) to achieve better cover and provide a pipe type that is to standard.
Number: 42 Created: 9/14/2005
[12/21/05] The issue is unresolved. Ideally the plat would establish a lot line to coincide
with the PDP boundary and the limit of public improvements on Buckingham Street so that it
appears the limit of public improvements was not arbitrarily decided.
[9/14/05] Please show lot lines and PDP boundaries on the street plans (such as to help
illustrate that the sidewalk along Buckingham Street ends at a property line).
Number: 44 Created: 9/14/2005
[9/14/05] At time of final plan, provide cross sections along Buckingham Street at 50'
intervals.
Number: 46 Created: 9/14/2005
[12/21/05] Appears to be unresolved. With the curb extensions, this information is needed.
[9/14/05] Provide flowline curve/line table data for verification. The inset parking narrowing
appears fine bt I'd like to see the radii specified just to be sure.
Number: 71 Created: 12/21 /2005
[12/21/05] The curb extensions with the flowline passing behind the curb extensions is an
issue as it is a maintenance concern for the City.
Number: 72 Created: 12/21 /2005
[12/21/05] The notes from bha seemed to state of variance request would be submitted for
the curb extensions, this apparently was not received.
Page 1
Number: 67 Created: 12/21 /2005
[12/21/05] Add notes regarding depth of water service and fire line through the detention
pond area.
Number: 68 Created: 12/21 /2005
[12/21/05] Show the water/sewer lines on the grading plan (at least in detention pond area).
Number: 69 Created: 12/21 /2005
[12/21/05] Is there a conflict between water service/fire line and the NWCWD 24-inch main?
Pothole now.
Number: 70 Created: 12/21 /2005
[12/21/05] Show water/sewer lines in the Coy Ditch profile.
Number: 76 Created: 12/21 /2005
[12/21/05] Add note to locate and protect all valve boxes and manholes during the
pavement milling operations.
Number: 77 Created: 12/21 /2005
(12/21/05] Show electric duct bank on utility plans. Is there any conflict with sewer service?
Number: 78 Created: 12/21 /2005
[12/21/051 See plans for other comments.
Comments from Current Planning
One of the objectives of the Lighting Plan should be to protect the Buckingham
neighborhood from glare. All the proposed fixtures appear to be appropriate with one
exception. The fixture described as E3 does not appear to be full cutoff. The
specification sheet indicates that the UCM-H3 includes a "sag lens" which reveals the
light source. Please check to make sure that the illumination in the area where the E3
fixtures are indicated does not produce glare. Should another fixture type be selected?
Perhaps the UCM-H3 can be equipped with the "house side shield" which is listed as
an available option.
2. The W3 and W4 fixtures look fine can be tilted after installation. Please add to General
Note number 4: "Any exterior lighting fixture that comes factory -equipped with
adjustable brackets shall maintain a 90-degree cutoff angle."
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
Sincerely:
7
Ted Shepard
Chief Planner