HomeMy WebLinkAboutEVERGREEN PARK, LOTS 18 & 19 - IL SITE PLAN REVIEW - 53-94 - SUBMITTAL DOCUMENTS - ROUND 2 -PROJECT
COMMENT SHEET
Nlannlna
DATE:
29
December 1994
DEPARTMENT: Pub Svc
PROJECT:
53-94
EVERGREEN
PARK, Lot 17
PLANNER: Mike Ludwig
Here are the revised plans you requested -
AII comments must be received by: - Fripay, 6 Jan 19951
1.
❑ No Problems
Problems or Concerns (see below)
�/V
Date: ZV 2,0 �Si Signature: Z�5/
CHECK IF YOU WISH TO RECEIVE ❑ PLAT
COPIES OF REVISIONS: ❑ SITE
❑ LANDSCAPE
❑ UTILITY
DEVELOPMENT SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 80522-0580
PLANNING DEPARTMENT (303)221-6750
City of Fort Collins
Plannina
PROJECT
COMMENT SHEET
DATE: 29 December 1994 DEPARTMENT: Water Cons
Jim Clark
PROJECT: 53-94 EVERGREEN PARK, Lot 17
PLANNER: Mike Ludwig
Here are the revised plans you requested -
AII comments must be received by: Friday, 6 Jan 1995
a No Problems
❑ Problems or Concerns (see below)
Date: Signature:
CHECK IF YOU WISH TO RECEIVE ❑ PLAT
COPIES OF REVISIONS: ❑ SITE
❑ LANDSCAPE
❑ UTILITY
DEVELOPMENT SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 80522-0580
PLANNING DEPARTMENT `(303(221-6750
If Lot 17 (phase 2) is to included in the final approval, then all proposed details must be shown
(e.g. proposed grading, all proposed drainage facilities, finished floor elevation, etc.), ultimate
build -out conditions should also be considerate in detention sizing.
Please include the following on the grading and drainage plans: a vicinity map, a legend
(labeling existing and proposed contours, storm sewers, project boundaries, basin
boundaries, etc), all proposed contours tieing -in to existing contours and a description of all
proposed drainage facilities (including pans).
Please note that dedicated easements (by separate document) will be required for the
detention area. This should be done prior to plan approval.
From the drainage plans, it appears that flows from the south of lot 19 will not entirely be
intercepted by the swale, but continue onto lot 20. Please show a basin break with more
grading, along with high points, that will prevent greater than historic flows from entering
lot 20.
Please describe flows entering the property from the North. If off site flows enter,
calculations might need to be adjusted.
The plans show that the release from the detention pond is to exit through a 15" RCP and
flow along Red Cedar to manhole No. 1. What happens to the flow after this point? How
does it enter the existing system?
Please clarify the direction of the 70' contour. It appears to split and incorrectly tie into the
existing contour. Since this contour is the HWL of the pond, this contour must be clearly
defined to contain the pond within the project boundaries.
Please show a cross section of the swales entering the pond.
Please label the pond spillway along with a cross section.
Show details, on the drainage plans, of the proposed flow pan in the west alley. How much
flow will be carried in the alley and exit onto Conifer Street?
Please adjust the erosion control estimate to include installation costs.
Please see the redlined plans and report and the consultant checklist form for additional
comments.
evg171819.fin
City of Fort Collins
anninLz
PROJECT
COMMENT SHEET
DATE: 15 DEC 1994 DEPARTMENT: 4fm VM Jff--
PROJECT: Lots 18 & 19, Block 3, Replat #1, Evergreen Park
PLANNER: Kerrie Ashbeck
All comments must be received by: Friday December 30, 1994
❑ No Problems
Problems or Concerns (see below)
Please add a cover letter to the drainage report which includes a transmittal date.
Reports need to be stamped and signed by a registered PE in the State of Colorado.
There are no basins shown on the drainage plans. Please delineate and add a detailed
hydrology summary table.
Adjacent half -streets should be included in your detention requirements.
Please note that these are standard items requested routinely on ALL drainage reports.
Please use a drainage plan that is not loaded with the extraneous information present on the
site plan. As presently presented the drainage plan is essentially a site plan with some grading
and drainage information super -imposed onto it. (OVER)
Date: — 14 2 Lr — Signature:
CHECK IF YOU WISH TO RECEIVE ❑ PLAT
COPIES OF REVISIONS: ❑ SITE
❑ LANDSCAPE
❑ UTILITYii
DEVELOPMENT SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 80522-0580 (303)221-6750
PLANNING DEPARTMENT
City of Fort Collins
annine
PROJECT
COMMENT SHEET
DATE: 15 DEC 1994 DEPARTMENT: -�ifq fj
PROJECT: Lots 18 & 19, Block 3, Replat #1, Evergreen Park
PLANNER: Kerrie Ashbeck
All comments must be received by: Friday December 30, 1994
N
❑ No Problems
FlProblems or Concerns (see below)
CU. cc"-,Li�C` 3�
V
Date: 1 Z-Z y Signature.
CHECK IF YOU WISH TO RECEIVE ❑ PLAT
COPIES OF REVISIONS: ❑ SITE
❑ LANDSCAPE
❑ UTILITY
DEVELOPMENT SERVICES 281 NORTH COLLEGE P.O.BOX 580 FORT COLLINS, COLORADO 80522-0580 (303)221-6750
PLANNING DEPARTMENT