November 30, 1999
Mr. Ted Shepard
Chief Planner
Current Planning
City Fort Collins
281 North College Avenue
Fort Collins, CO 80524
Fort Collins
P.O. Box 2127 (80522)
2620 E. Prospect Road, Suite 100
Fort Collins, CO 80525
(9701493-8747
(970) 493-5869 FAX
RE: New Belgium Brewing
Fermentation Tank Expansion
Dear Ted:
Denver
Eighteenth Street Atrium
1621 18th Street, Suite 250
Denver, CO 80202
(3031 296-0383
(303) 296-0382 FAX
Colorado Springs
P.O. Box 1478
Colorado Springs, CO
80901-14 78
(719) 633-4713
(719)633-9508 FAX
Pursuant to our conversation regarding the expansion of New Belgium Brewing, I am confirming that
under the current City Plan Criteria we will be allowed to install 75 foot fermentation tanks without a
height variance. The industrial zone allows up to 4-story structures with stories less than 25 feet for a
total allowed height of 100 feet.
The fermentation tanks will be Phase 2 Tank Farm identified on the FDP approved on October 16, 1997.
Priority of Phase 2 and Phase 3 has been revised, with the Phase 3 Warehouse being previously
completed. Phase 2 will also be completed in smaller increments with approximately one-half of the
tanks as first phase. We will review expansion with Storm Water and we will be applying for an
Administrative Amendment for approval of each sub -phase.
le
Please call if questions or if you have any concerns/comments on this phase.
Sincutly,
V
j K. Merl Itworth
Architect