HomeMy WebLinkAboutWATERFIELD P.U.D, 2ND FILING - FINAL - 7-95D - CORRESPONDENCE - TRANSPORTATION ISSUE(either as a Type I or II review). In addition, the project would be required to
meet the standards in both Article 3 and Article 4 to the maximum extent
feasible.
Conclusion
While we do not have alternative designs to comment on, the options that have
been mentioned include losing two buildings, moving the affected buildings to
other portions if the property and adding units to approved buildings. Any of
these options, and other options which staff has speculated on, would require a
major amendment review process and likely require a modification which would
be heard by the Planning and Zoning Board.
Planning: Redesign of the project would require processing through the
development review process. Three processes could be considered: a
new application could be submitted under the Land Use Code; changes
could be determined to be a minor amendment; or, changes could be
determined to be a major amendment.
Other:
Process:
As a new submittal under the Land Use Code, the project would be starting over
with a new application which would be required to meet all the criteria of the
Land Use Code.
If the applicant would propose amending the approved PUD, one of two
processes would be followed: it would be either a minor or major amendment
Since the project was approved under the LDGS, in the case of the Waterfield
PUD, an amendment could be considered minor when:
The minor amendment results in an increase or decrease by 1 % or less in
the approved number of dwelling units; or,
The minor amendment results in an increase or decrease in the amount of
square footage of a nonresidential land use or structure that does not
change the character of the project; or,
The minor amendment results in a change in the housing mix or use mix
ratio that complies with the requirements of the zone district and does not
change the character of the project; or,
The minor amendment does not result in a change in the character of the
development.
Minor amendments can be approved by the Director provided the development
plan, as so amended, continues to comply with the standards of the Land Use
Code at least to the extent of its original compliance (so as to preclude any
greater deviation from the standards of the Land Use Code by reason of the
amendment).
If the amendment is determined to be a major amendment, it would be required
to be processed according to the provisions of Article 4 of the Land Use Code
July 30, 1999
Internal Distribution Only
ISSUES REGARDING WATERFIELD PUD/NE TRUCK ROUTE
Facts regarding the Waterfield PUD:
At the time of the appeal of the preliminary PUD, Council approved Ordinance
52-1996 which:
Rezoned the southern 60 acres IL with a PUD condition
Rezoned the northern 80 acres RLP with a PUD condition
Required any residential development to occur at a minimum density of 6
du/net developable acre (as defined in the ordinance)
While the Preliminary PUD and Bull Run were approved under the LDGS subject
to these limitations, the property is now zoned LMN. Any amendments to the
approved PUD will be reviewed under the amendment provisions of the Land
Use Code.
Approved preliminary PUD:
Gross acreage.........................................140.09
Net acreage..............................................79.6
Single Family...........................................187
units
Senior Cottages........................................120
units
Bull Run Apartments..................................176
units //. s 4101e
Gross Density..............................................3.45
du/acre
Net Density.................................................6.06
du/acre
Bull Run Apartments:
176 du on 15.5 acres = 11.55 du/A
Issues
If the Northeast Truck Route is approved for Vine Drive, several hundred feet (?)
of additional right of way will be required to be taken from the southern portion of
the Waterfield PUD significantly affecting the approved Waterfield First Filing
PUD (Bull Run Apartments). Several issues associated with the approved
project will be required to be addressed:
Stormwater: A major drainage ditch runs along the north side of Vine
Drive which drains this and adjacent property. Drainage issues will need
to be reconsidered which could require a significant redesign of the
project which would include amending the recorded plans including
revisions to the drainage plans.