HomeMy WebLinkAboutNOVOVESKY GARDEN CENTER PUD - PRELIMINARY - 13-95A - CORRESPONDENCE - STAFF'S PROJECT COMMENTS11. Please provide a bike rack near the front entry. A note
should be state that the bike rack is to be permanently
anchored in concrete and not interfere with pedestrian access.
12. There should be a sidewalk connection from Timberline Road
into the site, preferably aligned with the .front entry. This
sidewalk will need a ramp and may cause removal of one parking
space.
13. Please be cautioned that the location of the monument sign is
right next to the proposed location of the fire hydrant.
14. Please provide setback dimensions of the new buildings from
property lines.
15. Please provide building square footage information within the
building envelopes.
16. The site plan should indicate that the sidewalk along
Timberline Road will be.equipped with ramps.
17. Please revise Project Note #3 and correct the zoning
designation. The property is now zoned I-P, Industrial Park..
18. Please indicate that the shaded area in front of the garden
center will be annuals.
19. Will "container stock" be a typical for all triangular areas
along Timberline? Please clarify.
20. Please note on the P.U.D. that the existing house will be used
as a residence. This is how points are earned for "mixed -
use".
21. Please provide more detail on exterior materials and colors on
the architectural elevations.
This concludes Staff comments at this time. Please note the
following deadlines for the July 24, 1995 Planning and Zoning Board
hearing:
Plan revisions are due July 5, 1995.
P.M.T.'s, 10 prints, renderings are due July 17, 1995.
As always, please feel free to call. our office to discuss these
comments or to set up a meeting with the appropriate Staff to
discuss these comments in depth.
Sincerely:
Te Shepard
Senior Planner
Consequently, the applicant must obtain an access easement
from the intervening property owner for access to Caribou
Drive in order for the P.U.D. to proceed. This property
owner, Mr. K. Bill Tiley, is aware of the access and
circulation issues.
2. The existing curb cut on Timberline Road may be retained as an
emergency second point of access but should be designed with
a chain and/or bollard system to control access.
3. There are problems with the Business Service Uses Point Chart
as submitted. Without a shared access drive to Caribou,
points cannot be earned for "part of a planned center". This
results in a reduced score of 4801 which does not exceed the
minimum required score of 50 (The maximum applicable points
is 50, not 54 since the "historic preservation" criterion is
not. applicable.) If a shared access drive is provided north
to Caribou, then points can be earned for both ."part of a
planned center" and "joint access". This results in an
improved score of 72%.
4. A new sanitary sewer line will be extended south from Caribou
along the Timberline Road frontage. Please coordinate with
Stewart and Associates so that landscape materials are not
planted over the line. Also, please be.sure that shade trees
along Timberline Road are kept 40 feet from streetlights.
Ornamentals may be placed within 15 of a streetlight.
S. Light and Power cautions that the existing electrical service
line to the house may have to be relocated. Be sure that the
electrical transformer is sensitively located or properly
screened so..it does not work against the attractive
landscaping along Timberline Road. The revised plans should
indicate the approximate location of the transformer.
6. Comments from the Stormwater Utility will be forwarded to
Stewart and Associates under separate.cover.
7. Please delete the reference to "net acres" on the plat.
8. The fire and maintenance access road must be a minimum of 15
wide. Poudre Fire Authority will not accept a 12 foot wide
road.
9. The parking stalls are shown to be 17 feet in length which is
fine if there is at least two feet for vehicle overhang. Will
the 12 inch high timber retaining wall prevent cars from
overhanging? Please note that the timber wall is to be
setback a minimum of two feet to allow for overhang, or
provide 19 foot stalls.
10. According to the U.B.C., a total of three handicap parking
stalls are required.
Commur , Planning and Environmental F vices
Current Planning
City of Fort Collins
June 15, 1995
Mr. and Mrs. Michael and Florence Novovesky
c/o Jim Sell Design
117 East Mountain Avenue
Fort Collins, CO 80524
Dear Jim:
Staff has reviewed the request for Novovesky Garden Shop
Preliminary and Final P.U.D. and offers the following comments:
1. The primary comment.has to do with access off Timberline Road.
Based on previous planning efforts which resulted in an
Amended Overall Development Plan, access must be gained via
Caribou Drive, not Timberline Road.
Staff has consistently advised the previous owner that a
further intensification of the property would require joint
Access to be obtained north to Caribou Drive and not to solely
rely on Timberline Road for continued access. Staff
represented to Mr. Chandler that if the property remained
single family, then direct access off Timberline Road would be
acceptable. Conversion of the property to a retail use is
considered to be an intensification of the property.
During deliberations on Timberline Storage P.U.D., Staff
required the Calendula Business Park Overall Development Plan
to be amended to include the 17 acres south of Caribou Drive.
This area has been divided into three parcels labeled Phases
Six, Seven and Eight. The purpose of the O.D.P. was to
describe the internal circulation pattern with Automation Way
and Caribou Drive, and to indicate the location of the
wetlands. As a result of this amendment, Automation Way now
terminates at Caribou and will not be extended further south.
According to the O.D.P., all three phases are designed to take
access off Caribou Drive. The proposed P.U.D. is located on
Phase Eight and is therefore expected. to take access off
Caribou. Access off Timberline is not in conformance with the
Amended O.D.P. and is not consistent with previous
communications with Mr. Chandler.
As mentioned at Conceptual Review, left turn exits onto
Timberline Road will be increasingly difficult. The
intersection of Timberline and Caribou will be signalized
allowing safe turn movements for garden shop customers going
north.
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (970) 221-6750
FAX (970) 221-6378 TDD (970) 224-6002