HomeMy WebLinkAboutREGISTRY RIDGE, 4TH FILING - PDP - 32-95G - CORRESPONDENCE -4
This completes the staff comments at this time. Additional comments could be
forthcoming as they are received from City departments and outside reviewing
agencies. The project is essentially ready to be scheduled for an administrative
public hearing. No "formal" resubmittal of revisions or another round of review
is necessary; however, there .are concerns expressed by the Engineering and
Stormwater Departments that must be addressed prior to scheduling the
hearing. Please contact those departments directly to resolve their concerns.
Please contact me at 221-6341 if you have questions or concerns related to
these comments. I would like to schedule a meeting with you as soon as
possible, if necessary, to discuss these comments.
Si cerely,
Steve Olt
Project Planner
xc: Engineering
Zoning
Stormwater Utility
Light & Power
Poudre Fire Authority
Transportation Planning
Traffic Operations
Natural Resources
DALCO LAND, LLC
Northern Engineering
Sear -Brown
Project File #32-95G
23. To ensure that future builders and home owners in the development are
aware that there must be some variation in the buildings, per City Code,
it may be appropriate to indicate the building types and colors (from the
building elevations) on the subdivision plat. At least, reference the Site
Plan and Building Elevations that are to be recorded and of record in the
City.
24. The road designs are not at 90% as required to go to public hearing.
Transportation Planning (Kathleen Reaves
25. There should be a trail connection from Bataan Circle in this
. development south to the trail in the Registry Ridge, Third Filing.
Stormwater Utility (Wes Lamarque)
26. The street capacity calculations need to be provided to the City for
review.
27. There are other minor comments as stated on the Stormwater Revisions
Comment Sheet.
Plannine
28. Please check with Ron Gonzales of the Poudre Fire Authority to make
sure that he has not got a concern about the orientation and addressing
for Building #4.
29. Will parking be allowed on Bon Homme Richard Drive adjacent to this
development?
30. Some garage door setbacks from sidewalks are of concern, being less
than the required 19' - 20'.
31. The building types (AB, CD, DD) should be shown in the building
footprints on the Site Plan.
32. The alleys should be labeled on the Site and Landscape Plans and noted
on the Site Plan as to being public or private.
33. Additional comments are on red -lined plans that are being forwarded to
the applicant.
b. Any existing landscaping that needs to be replaced in order to
install electric facilities will be done so at the developer's expense.
C. Service to Building #4 will need to be coordinated between Light &
Power and other utilities.
d. The applicant needs to coordinate street trees with street lighting,
providing the proper separation.
Please contact Janet, at 224-6154, if you have questions about these
comments.
The following comments and concerns were expressed at the weekly Staff
Review meeting on May 2, 2001:
Engineering (Marc Virata)
14. , Off -site easements are needed prior to going to public hearing. A letter of
intent will be sufficient with this PDP review; however, the actual signed
easement(s) must be provided with the Final Compliance submittal.
15. Check with Rick Richter in Engineering Pavement for information about
process and cost of any necessary cuts on Bon Homme Richard Drive.
16. Straighten out road rights -of -way.
17. Are the sight distances at the corners adequate?
18.. Show how the flowlines for Nimitz and Enterprize Drives tie into the
flowline on Bon Homme Richard Drive.
19. There may be an issue with the radii at the intersections with Bon
Homme Richard Drive. They should be consistent with existing
intersections.
20. Show the vertical curve on the eyebrows.
21. Bataan Circle needs to be renamed due to a duplicate or sound -alike
concern.
22. Has the sizing been done for the under -walk drains?
9. Representatives of the Technical Services Department offered the
following comrfients:
a. Tlie.le'gal description and the subdivision plat do close.
b. The South Fort Collins easement is unlocatable.
C. The, private drives need to be in ,a tract.
d. Registry Ridge, Third Filing is not yet recorded. It needs to be filed
prior to recording this plat or the. legal descriptions and subdivision
map for this filing must be changed.
e. The Bataan Circle street name must be changed due to conflicts
with other street names.
Please contact Jim Hoff, at 221-6588, or Wally Muscott, at 221-6605, if
you have questions about their comments.
10. Laurie D'Audney, the City's Utility Education Specialist, indicated that
she has no concerns or comments at this time regarding the City's
irrigation and water conservation standards.
11. Ward Stanford of Traffic Operations offered the following comments:
a. The proposed alley access at Bon Homme Richard Drive needs to
be evaluated for City sight distance requirements and easements
must be placed as needed.
b. All crosswalks are to be painted.
Please contact Ward, at 221-6820, if you have questions about these
comments.
12. Mike Spurgin of the Post Office has indicated that they have no
concerns or comments regarding this development .proposal.
13. Janet McTague of Light & Power offered the following comments:
a. Light & Power will need to coordinate meter locations for electric
and gas.
remain at service level A for the next 5 years. Loveland High School
is currently at and is expected to remain at service level C for the
next 5 years: This area is expected to experience some of the
highest growth in the District during the next 5 years.
4. Peter Barnes of the Zoning Department. -has one repeat comment. It
states:
r
Remove the Building Envelopes from the Site Plan (Sheet 1 of 8).
Replace them with the lot lines since each building is on its own
lot. Since none of the lots have frontage on a public street, all of
the lot lines are side lot lines by definition. The setbacks as set
forth in Section 3.5.2(D) of the LUC apply to the setback distance
for "lot lines". If the developer and/or applicant do not plan on
complying with the setbacks, which appears to be the case, then
they must submit a modification request and go to the Planning
and Zoning Board for a decision.
Please contact Peter, at 221-6760, if you have questions about these
comments. A meeting with the applicant, Zoning, and Current Planning
may be in order. This should be done soon so that.the project may move �-
to public hearing.
5. A copy of the comments received from Marc Virata of the Engineering
Department is attached to this comment letter. Additional comments
may be found on red -lined plans that are being forwarded to the
applicant. Please contact Marc, at 221-6750, if you have questions about
his comments.
6. A copy of the comments received from Wes Lamarque of the Stormwater
Utility is attached to this comment letter.. Additional comments may be
found on red -lined plans and reports that are being forwarded to the
applicant. Please contact Wes, at 221-6681, if you have questions about
his comments.
7. Kathleen Reavis of the Transportation Planning, Department indicated
that a trail should be provided from Bataan Circle to the trail from
Intrepid Court in Registry, Ridge, Third Filing, to the south. Please
contact Kathleen, at 224-6140,, if, you have questions about her
comment.
8. GayLene Rossiter of Transfort has indicated that they have no concerns
or comments regarding this development proposal.
Commu / Planning and Environmental " Vices
Current Planning
City of Fort Collins
May 11, 2001
VF Ripley Associates, Inc.
c/o Rachel Linder
401 West Mountain Avenue, Suite 201
Fort Collins, CO. 80521
Dear Rachel,
Staff has reviewed your revisions documentation for the Registry Ridge,
Fourth Filing - Project Development Plan (PDP) that was submitted to the
City on April 5, 2001, and would like to offer the following comments:
Len Hilderbrand of Public Service Company (Excel Energies) stated
that they are concerned with some tree locations. Trees may not be
planted within 4' of gas lines.
2. A copy of a comment letter received from Terry Farrill of the Fort
Collins -Loveland Water District and the South Fort Collins
Sanitation District is attached to this comment letter. Please contact
Terry, at 226-3104 - ext. 14, if you have any questions about his
comments.
3. New comments from Thompson School District R24 have not been
received. To reiterate their previous comments:
A copy of the Thompson School District R2-J Development Impact
Report that was received from Kate Browne of the District is
attached to this comment letter. In summary, this development
could cause district enrollment to exceed service level C (Extended
Utilization). The proposed 44 dwelling units are within the current
-attendance boundaries of Centennial Elementary School, Lucile
Erwin Middle School, and Loveland High School. Centennial
Elementary School is currently at service level A and is expected to
move into (and may exceed) service level C during the next 5 years.
Lucile Erwin Middle School is currently at and is expected to