May 9, 1995
Jim Sell Design
117 E. Mountain Avenue
Fort Collins, CO 80524
Dear Jim,
Per your request on May 5, 1995, this letter will serve as
confirmation of -the conversation you had with Mike Herzig on
regarding the City's utility plan submittal requirements for the
DALCO P.U.D.
The off -site street improvement final designs are not required as
part of the Preliminary P.U.D. Utility Plan submittal.
The City will not require off -site sanitary sewer final designs,as
part of the Preliminary P.U.D. Utility Plan submittal. However,
the proposed alignment of the off -site sanitary sewer should be
shown on the Preliminary P.U.D. Utility Plan submittal. Final
designs for the off -site street improvements and off -site sanitary
sewer will be required at the time of Final P.U.D. submittal.
This letter addresses the submittal requirements of the City of
Fort Collins only. The DALCO property will be served by the South
Fort Collins Sanitation District and the Fort Collins/Loveland
Water District. Please contact Terry Farrill at 226-3104 to
discuss the design submittal requirements of the water and sewer
districts.
Please feel free to contact me at 221-6206 with any questions or
concerns regarding this letter.
Sincerely,
A0, 17
Michael Ludwig
Project Planner.
xc: Mike Herzig, Engineering
Tom Vosburg, Transportation
Glen Schlueter, Stormwater Utility
Roger Buffington, Water and Wastewater Utility
Terry Farrill, South Fort Collins Sanitation District
File
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (303) 221-6750