and the Parks Department. Stormwater indicated to us that they would
like to have the revised report prior to the Hearing date. All other
comments regarding onsite flows can be accommodated in final design.
We also discussed with Kerrie Ashbeck the extent of the revisions to be
resubmitted. She indicated that the revised site plans from Jim Sell
would address the majority of Engineerings' concerns. She said that we
will not need to resubmit a revised copy of the Preliminary Plat, or
revised Preliminary Utility plans, other than those required to be
resubmitted by Stormwater. Kerrie also indicated that a meeting should
be set up with City Engineering regarding the proposed street rotaries.
This will be set as soon as a revised site plan is developed. Other than
that, all engineering issues can be addressed at time of Final Design.
This should address all of the engineering related comments and
concerns regarding the Registry Ridge ODP and Preliminary PUD.
Response to other comments will be addressed and resubmitted by
Northern Engineering or by others at a later date to insure a September
hearing date. Please call if you have any questions regarding this letter.
Sincerely,
Roger'A. Curtiss P.E.
cc: Jim McCory, Colorado Land Source
Jim Sell, Jim Sell Design
Kerrie Ashbeck, City of Fort Collins
Basil Hamdan, City of Fort Collins
Mike Bryant, Larimer County
Terry Ferrill, Ft. Collins/Loveland Water District
Lucia Liley, March and Myatt
Northern Engineering Services, Inc.
July 31, 1995
Mr. Michael Ludwig
Community Planning and Environmental Services
City of Fort Collins
PO Box 580
281 North College Avenue
Fort Collins, Colorado 80522-0580
RE: Registry Ridge Preliminary
Response to City Comments
Dear Michael,
This letter is in response to the comments regarding engineering issues
Northern Engineering Services Inc. (NES) received regarding the
Registry Ridge CDP and Preliminary PUD.
The applicant has requested to postpone the Planning and Zoning Board
hearing on Registry Ridge from August 21, 1995 to the September
meeting of the Board (letter Dated July 28, 1995 from Lucia Liley).
I have reviewed comments regarding the onsite and off site utilities with
Terry Ferrill from Fort Collins/Loveland Water and Sewer District. All of
the comments and concerns that the District expressed with the
preliminary submittal can be addressed at the time of final design. The
off site sewer is currently being prepared and will be submitted to the
District as a separate project.
A copy of the letter from Elaine Spencer at Larimer County concerning
Traffic issues has been forwarded to Matt Delich. Matt should respond to
all of Elaine's concerns. NES is currently working on the arterial designs
of South Shields Street and Trilby Road. These arterial roadway plans
will be submitted to the City as a separate project, and at that time the
plans will also be submitted to Larimer County for their review and
approval.
I met with City of Fort Collins Stormwater Utility to review their
comments, and to determine the extent of our resubmittal package.
Stormwater indicated that they would like us to resubmit our Preliminary
Drainage and Erosion Control Study, as this will serve as a Master Plan
for the Registry Ridge ODP. NES is prepared to revise this study, along
with the Drainage and Erosion Control Plan (sheets 2 and 3 of 13) as soon