HomeMy WebLinkAboutEAST RIDGE - FDP - 33-98F - SUBMITTAL DOCUMENTS - ROUND 2 - APPLICANT COMMUNICATIONMr. Steve Dush
January 12, 2009
Page 4
If you should have questions with regard to this matter, please do not hesitate to
call me. I appreciate your consideration of our request. Thank you.
Sincerely,
Is/Jim Martell
James A. Martell
JAM:bkr
cc: Ms. Darlene Schuster
Mr. Jeff Strauss
Mr. Matt Blakely
Mr. Steve Dush
January 12, 2009
Page 3
• Delay resulting from development of plans to provide non -potable water
service to the park designated by the City.
• Delay by the City in finalizing its determination of the Timberline Road
right-of-way.
• Delay by East Larimer County Water District in determining the final
alignment and configuration of its 16-inch water line.
• Various issues, including pedestrian and drainage issues involving adjacent
properties.
• Delay by the City in finalizing its determination of the curb and gutter
needs in the first phase of East Ridge to meet the City's connectivity
requirements.
• Delay caused by the coordination and independent review of emergency
access to the East Ridge Property for both the interim and ultimate
buildout.
• Delay resulting from the necessity to resolve issues arising out of recorded
agreements/easements during the plan review phase instead of during the
development agreement review phase.
The consultants for East Ridge have made two submittals of the final plans and are
currently prepared to re -submit for a third round of review. The first final submittal was
made on March 5, 2007, and the second final submittal on May 6, 2008. East Ridge
Consultants have been making diligent and concerted efforts to keep the project moving
toward final approval in as timely a manner as possible. Based on the foregoing, East
Ridge respectfully requests that you grant the extension of six month provided for in
Section 2.2.11(C) of the Land Use Code and if, notwithstanding continuing good faith
efforts on the part of East Ridge to obtain final approval, a final plan is not approved
within the six month period, East Ridge be granted further extensions as necessary.
Mr. Steve Dush
January 12, 2009
Page 2
• Delay by the City in making a final decision on the alignment and
configuration of the future potential overpass on Timberline Road
necessitating multiple redesigns after review by the City Staff.
• Delay by the City in making a final decision on the lane configuration /
alignment and layout of Timberline Road. The most recent change in the
configuration occurred during the current round of comments,
notwithstanding that the transportation department had previously approved
the alignment and configuration proposed by East Ridge and its engineers,
TST, after three meetings with representatives of the Transportation
Department.
• Delay by City Departments in reaching agreement on the designation of
wetlands areas and mitigation. Representatives of the Natural Resources,
Parks and Stormwater Departments have expressed varying preferences
with regard to designation of the wetlands areas and possible mitigation.
• Delay by City Departments in reaching agreement on stormwater detention
facilities and park areas. Representatives of the Parks, Engineering and
Stormwater Departments have expressed varying preferences with regard to
the most appropriate configuration of the park and stormwater detention
areas.
• Delay resulting from approval of the new City of Fort Collins Stormwater
Master Drainage Plan during the most recent round of review and
comments on the East Ridge final plan, which affects stormwater flow,
alignment of conveyance pipes, discharge points and easements.
• Delay by the City in finalizing the direction and flow of the 100 year flood
from property north of the East Ridge Property.
• Delay by Boxelder Sanitation District in finalizing its plan for the location
and size of a sanitary sewer line to serve the entire basin, including the East
Ridge Property as a result of the inability of the owners of surrounding
properties to finalize plans for their properties.
• Delay caused by revision of the Timberline Road Pedestrian Sidewalk
Connectivity by the City Staff after having approved the Pedestrian
Connectivity proposed for the Timberline Project.
- LILEY, ROGERS & MARTELL, LLC -
ATTORNEYS AT LAW
January 12, 2009
VIA E-MAIL
Mr. Steve Dush
Current Planning Director
City of Fort Collins
281 N. College Avenue
Fort Collins, CO 80521
Re: East Ridge gubdivision
Dear Steve:
I represent East Ridge of Fort Collins, LLC, a Colorado limited liability company
("East Ridge"). East Ridge is the owner of a parcel of property consisting of `
approximately 153 acres located at the southeast corner of the intersection of Vine Drive
and Timberline Road ("the East Ridge Property"). A Project Development Plan for the
East Ridge Property was approved on January 12, 2006 ("the East Ridge PDP").
Section 2.2.11(C) of the Land Use Code provides in part as follows:
Within a maximum of three years following approval of a project
development plan, the applicant must proceed by obtaining the Director's
approval of a final plan for all or part of the project development plan....
The Director may grant one extension of the foregoing three-year
requirement, which extension may not exceed six (6) months in length....
East Ridge and its consultants have acted in good faith and used all reasonable
efforts to obtain approval of a final plan within the three year period described in the
Land Use Code. There are significant issues that have arisen affecting the East -Ridge
Property since approval of the East Ridge PDP. Many of the issues and resulting delay`s
may be directly attributable to either City Staff comments or other service providers. In
either case, the delays have been beyond the control of East Ridge. The following is a
summary of some, but not all, of the issues that East Ridge and its consultants believe
have been beyond East Ridge's control:
LUCIA A. LILEY ■ JAMES A. MARTELL ■ TODD W. ROGERS ■ JOSHUA C. LILEY
THE PETER ANDERSON HOUSE ■ 300 SOUTH HOWES STREET ■ FORT COLLINS, COLORADO 80521
TELEPHONE (970) 221-4455 0 FAX: (970) 221-4242