Cetacean Minor Subdivision
Page 2
The runoff calculations and the detention pond mass diagram as well as the grading,
drainage and erosion control plan are enclosed as a part of this report.
This drainage report and the design of the drainage system are in compliance with the City
of Fort Collins Storm Drainage specifications and criteria to the best of my knowledge.
ffyou have any questions regarding this report and drainage plan, please call.
Sincerely,
.pRO
� : • ��GI STEgFG'Pit�� Y
Richard A Rutherford, P.E. & L.S. • o
President _*: 5 028
?
s
rsc �. osl-
�a`_a L. - ..�
enclosures
ii
STEWART&ASSOCIATE$
Consulting Engineers and Surveyors
August 24, 1995
Mr. Basil Hamdan
Stormwater Utility
City of Fort Collins
P.O. Box 580
Fort Collins, CO 80522
Dear Basil:
This is the final drainage report for Cetacean Minor Subdivision, which is a one lot in -fill
subdivision on the South side of Harvard Street between South College Avenue and McClelland
Drive. The one lot contains 20,000 square feet. It is bounded on the North by Harvard Street, on
the East by an existing car wash, on the South by an undeveloped lot and on the West by an
existing office building and its parking lot. The site drains from Southwest to Northeast at an
approximate slope of 1.0%.
The owner proposes to construct a retail building containing 7,000 square feet and a
parking lot for eleven cars. The difference between the two year frequency historic storm runoff
and the 100 year frequency developed storm runoff will be detained in the landscaped area and
parking lot area at the North end of the lot. The historic discharge will be metered out through a
pipe into the Harvard Street south gutter.
The outlet pipes from the detention pond on the adjacent parking lot to the West simply
daylight onto the site midway along the West property line. The two four inch diameter pipes will
be extended to Harvard Street. The historic runoff from the undeveloped lot to the South of the
site will be allowed to continue to sheet flow through the site to Harvard Street. The detention
pond will not be sized to detain the offske flows. The runoff from the South half of Harvard
Street will not discharge into the detention pond, but the detention pond was sized to include that
runoff
EROSION CONTROL: The site is in a moderate rainfall zone and a moderate wind zone.
The site will be rough graded and the detention pond will be used as a sediment trap. A silt fence
will be placed along the East property line and along the North line of the two segments of the
detention pond. The foundation will be constructed immediately after the grading is completed.
The landscaping and the paving will be done when the building is nearing completion. The gravel
sediment trap will be placed in the pond as soon as the pond is graded.
James H. Stewart
and Associates, Inc.
103 S. Meldrum Street
P.O. Box 429
Ft. Collins, CO 80522
303/482-9331
c..., anoinc�_a�n�
s)
FINAL STORM DRAINAGE REPORT
FOR
CETACEAN MINOR SUBDIVISION
PREPARED FOR
THOMAS D. MURPHY, JR.
AUGUST 249 1995
STEWART & ASSOCIATES, INC.
103 SOUTH MELDRUM STREET
FORT COLLINS, COLORADO 80521
970/482-9331