Loading...
HomeMy WebLinkAboutJEFFERSON COMMONS PUD - FINAL - 50-95A - CORRESPONDENCE - REVISIONSMA'r' 01 '96 12:0e FR JPI 214 556 3260 TO 919702230511-084 P.09/0'3 13. Stormwater Utility 1. Edge grading and drainage conditions have been clarified on the revised plans. JPI will obtain agreements for easements for off -site conditions. 2. The area outside the building evelopes has been shown as a drainage easement. Therefore a specific drainage easement to Skyline Mobile Home Park is not needed. 3. The channel side slopes have been revised accordingly. 4. The basin widths and calculations have been modified accordingly. 5. The discrepancy has been clarified to be consistent with the master plan. 6. Basin 66 and the proposed grading have been revised to match. 7. The detention pond overflow spillways have been clarified with cross -sections. 8. Further details of the pond outlet structures have been shown. Plans have been revised accordingly. y. Swale cross -sections have been provided. 10. Utility crossings have been shown with the appropriate clearances_ 11. The construction note list has been completed. 12. The existing wetlands is less than I acre and does not require a permit. The proposed wetlands landscaping is shown on the landscape plans. 13. Erosion protection for the channel has been shown. Off --site easements will be provided as discussed previously. 14. An additional cross-section of the proposed channel upstream of the culvert has been provided. 15. Please see landscape plans for the seeding methods and types for the proposed channel. 16. The 100-year flood plain has been plotted on the final plat. 17. The proposed detention ponds have been included within drainage easements, 18, The location of erosion control measures have been shown on sheet 8. MAY 01 '96 12:08 FR JPI 214 556 3860 TO 919(02230511-084 P.08/09 regarding no.w. dedications, vacations and easements. * See prior comment regarding letter agreement with the owner of Sunray Apartments regarding the Plum Street cul-de-sac. A driveway off the Plum Street cul-de-sac has been included for access to the site. * Comments regarding Orchard Place are no longer applicable. MAY 01 '96 12:07 FR JPI 214 55G 38GO TO 910702230511-084 P.07i09 Sheet 1 /18 * Sidewalk has been revised to the new city standard. * See prior response regarding r.o.w. dedications, vacations and easements. A 9' utility easement has been shown around the proposed .Plum Street cul-de-sac. Please see the letter agreement with the owner of the Sunray Apartments indicating his willingness to cooperate with JPI in the dedication of the Plum Street cul-de-sac. The letter agreement with the owner of Sunray Apartments was submitted previously to Mike Ludwig. See prior comment regarding off -site dedications, vacations and easements. * A 15' utility easement has been included along the Elizabeth Street r.o.w. in front of the site. * See prior comment regarding off -site dedications, vacations and easements. Sheet 2/18 * Orchard Place comments are no longer applicable. Sheet 3/18 * Details requested regarding design have been included. Sheet 4/18 * Details requested regarding design have been included. Sheet 5118 - 8/18 * See Stormwater Department comments. Sheet 9/18 * Details requested regarding design have been included. Sheet 10/18 * Orchard Place comments are no longer applicable. * Driveway details have been included. * True lengths in horizontal curves have been included. * Orchard Place comments are no longer applicable. * Orchard Place comments are no longer applicable. Sheet 11/18 * Details requested regarding design have been included. * Details requested regarding design have been included. * See prior comment regarding off -site dedications, vacations and easements. Sheet 12 - 14/18 * Details requested regarding design have been included. Sheet 15/18 * See Water Utility Department's comments. Sheet 16 - 18/18 * All applicable current City of Fort Collins standard details have been used. * References to where the various details apply have been included. 3/15/96 Comments * As discussed previously there is no need for additional r.o.w. dedication for the improvements along Elizabeth. * Details of the striping and transition of Elizabeth Street have been included with the submittal package. * See letter agreement with John Narum (property owner who's house faces the proposed Plum Street vacation) regarding his willingness to accept the vacation of Plum Street. This letter agreement was submitted to Mike Ludwig with a previous submittal. See prior comment MAY 01 '96 12:07 FR JPI 214 556 3860 TO 919702230511-084 P.05/09 12. Engineering Department Site Plan: * The r.o.w. line has been revised as requested. * Striping plans submitted with this package show the turn lane into the site. Sidewalks have been revised to reflect the new City standard as requested. * Dimensions have been provided for the sidewalk and parkway along Elizabeth. * Existing and proposed improvements have been distinguished on the Site Plan. * Areas for off -site r.o.w. dedications and vacations and off -site easements have been determined by the changes made with this submittal. Additional coordination with the city is required regarding the Orchard Place no.w. and the bike trail dedications and vacations_ With this information JPI and its attorney will gather the necessary easements and dedications prior to the May 20 Planning and Zoning Board meeting. See prior comment regarding r.o.w. dedications and vacations. # N/A. * Details concerning the Elizabeth Street r.o_w. in front of the site have been shown on the plans. T1ie is no additional Elizabeth Street r.o.w. dedication required in front of the site. (A 50' no.w. has already been dedicated.) * The no.w. required for the construction of Elizabeth to the east aid west of the site has already been dedicated. An off site construction and grading easement will be required to construct the sidewalk in front of the two houses to the east of the site since the north edge of the sidewalk coincides with the edge of the r.o.w. All constriction for Elizabeth Sheet to the west lies within the already dedicated r.o.w. Coordination with all four property owners will be required since driveway reconstruction will occur in the dedicated r.o.w. area. However no dedications or construction easements will be required since the driveway construction occurs entirely in the already dedicated r.o.w- * See comments from 3/15/96 * Coordination with Kern Ashbeek and Transfort determined that a connection for buses through the site to Plum Street was not desired. Drainage Report: * The water coming from the existing ditch lateral along Elizabeth Street will be conveyed into the storm drainage system for the site. Upstream users of the ditch are unaffected by the improvements on our site. There are no downstream users. Utility Plans: Title Sheet * The plan set has been titled "Utility Plans" to match the City Code and Development agreement references. * Sheets have been renumbered as requested. * A reference copy of the plat has been included with the Utility Plans. * The vicinity map has been revised to show Orchard Place and Ponderosa. * The benchmark has been noted and is part of the City's "Black Bolt" system. * A City approval block has been included on all sheets except the plat. MANY 01 '96 12:06 FR JPI 214 556 :3860 TO 91a-02230511-084 P.85/09 drive aisles. The additional maintenance building has been shown on the revised plans. q/- A separate Site Plan sheet has been provided for the vicinity map, land use data, general )cotes, signature blocks, legal description and prgject team information as sheet 1. f✓ The existing site plan (less the information on sheet 1) has been revised to accurately show all adjacent land uses including houses along W. Elizabeth and Ponderosa, Skyline Mobile .Home Park and Sunray Apartments and the property line between West Elizabeth Plaza and the existing single family house. The plan sheets have been numbered as requested. A trash enclosure has been added near building one_ i. Project notes have been reviewed for grammatical and spelling errors. j. "See Lighting Plan (Sheet..." has been added to site plan note 42. k. As requested, additional landscaping has been added along the eastern property boundary. street trees are included along West Elizabeth Street and additional landscaping has been included near Building 1 to screen it from West Elizabeth Street. As discussed with Mike / Ludwig, additional trees are not needed between the sidewalks adjacent to parking and the buildings. These trees were shown on the detail landscaping plans for each building. All trees have now been shown on the overall landscaping plan. Please continue to refer o the detail plan for shrubs, planter beds and foundation plantings. 1. Elevation Sheet Redlines i. Colors of building materials are shown on the building elegy rvo+ ii. Roofing materials have been labeled as 'Ugh profile, eav dimensional shingles". iii. As discussed with Mike Ludwig, brick has been included at the breezeway entrances to the buildings, the remainder of the first floor elevation is a 4" siding. The second and third floor siding is 8" and is a lighter color than the first floor siding. The different siding widths are separated by a decorative band which matches the trim around the doors, windows, eaves, etc, m. A typical drawing for the wood fence has been provided. Brick columns are used at strategic points along the fence. WV4 iS W n_ The turn ane at iizabeth aoes not impact the existing spruce tr e. The location of the turn lane has been coordinated with Kerrie Ashbeck. o. The redline sheets are included with the plan revisions. MAY fit ' 96 12: [5 FR JPI 214 556 3860- TO 919 ? 02230511-084 P. 04/09 7. TCi of Ft. Collins - JPI will coordinate with the cable tv provider regarding construction coordination, details and easements as discussed at the April 25 utility coordination meeting. 8. Light and Power Utility a. Water lines have been relocated as discussed at the April 25 utility coordination meeting. b. A gas aquathenn system heating system will be used to heat the -apartments. 9. Mapping Department a. Building Envelope ##7 has been revised so that it does not extend into the sanitary sewer asement. The point of beginning has been labeled on the Plat. c. This issue has been corrected on the Final Plat. d. A statement of dedication for the West Elizabeth Street is not necessary as a 50' right-of- way has already been dedicated for Elizabeth Street. A 15' utility easement has been added along Elizabeth Street as requested. 10. Water and Wastewater Utility a. JPI will still connect the two existing dead end mains in Orchard Place. Therefore the concerns regarding water pressure are unwarranted. The water lines will be connected to the existing points of termination and routed beneath paved areas in the parking lot. b. Our calculations show that we have adequate domestic and fire flow as based upon the water pressures supplied by the City. No fire pumps will be necessary. c. A note has been added to the landscape plans regarding a ten foot separation distance for trees and a four foot separation distance for shrubs to be maintained from water / sanitary sewer mains and services. d. Landscape drawings have been coordinated with civil drawings. 11. Transportation Department a. The width and radii of the drive have been increased to accommodate bus and fire turning movements without the need to remove parking spaces in front of the clubhouse as discussed with Kerri Ashbeck and Transfort. The parking spaces in front of the clubhouse include handicapped spaces. b. Access to the site has been provided at both Plum and Orchard Place on the east side of the site. c. A turn lane has been provided into the site from W. Elizabeth Street as shown on the revised striping plans. 12. Engineering Department - Please see the attached responses to the Engineering Department Conunents. 13. Stormwater Utility - Please see the attached responses to the Stormwater Utility comments. 14. Natural Resources Department - The trash enclosures have been designed to be large enough to accommodate recycling. 15. Water Conservation Specialist - The Landscape Plan has been revised to include a schedule of the landscape water use categories and associated square footage. 16. Current Planning Department a. Additional pedestrian connections have been added to the Site Plan as discussed with Mike Ludwig. b. Sidewalks adjacent to parking lots are shown as 6 feet wide to accommodate vehicle overhang. The widths of all sidewalks are shown on the plans. c. Patterned concrete has been shown at the pedestrian crossings through the parking lot: MAY 01 '96 12:05 FR JPI 214 _`b 3,860 TO 91' r02230511-034 P.07J, 09 Jefferson Commons PUD Ft. Collins, CO 1 2 3. 0 5 on Responses to Final Plan Review I Transfort a. The entrance from Elizabeth Street has been desig/izeth mmodate bus traffic including appropriate turning radii and pavement b. A concrete pad has been added to the west side of or the bus shelter. Police Department - Build ng address locations haven on the revised elevations. Site lighting has been shown on a separate plan includbmittal and provides good security for our residents without significantly overdoneighboring properties. In addition, "house" lighting will be included at the building breezeways which provide entrances to the units. These house lights will be included in the electrical plans submitted to the Cite for building permit. Poudre Fire Authority - Since all structures are to be equipped with an automated fire suppression system, we request that the preference for 28' wide drive aisles be waived. Zoning :Department a. Building envelope dimensions and setback distances of the building envelopes to the property lines have been shown on the Site Plan. Please refer to sheet 2 in this submittal t'pr this information. b. The words "on -site" have been removed from Landscape Plan Note #4. c. A note regarding the Planning and Zoning Board's decision on April 8, 1996 to approve an increase of the number of unrelated persons who may reside in individual dwelling units from three to four, for each of the 120, four bedroom units has been added to the Site Plan. d. "Required Parking" and "Parking Provided" data have been provided on the revised Site Plan. e. A legend has been added to the Site Plan. f. The building envelopes shown on the plat are substantially larger than the building footprints. Building Inspections Department a. Apartments will comply with the appropriate sections of building codes regarding hwidicapped accessibility/adaptability. The building and twit plans are being reviewed by the Building Inspections Department as part of the building permit process. b. The site plan is accessible to persons with disabilities in accordance with the appropriate sections of the building codes. Accessible routes of travel have been shown on the site plan. Public Service Company a. Paving will occur after the installation of utilities. b. The structure across the West Plum Channel is designed to include sleeving for the natural gas line as discussed at the April 25 utility coordination meeting. e. There are no permits to obtain for the construction of utility lines through the West Plum Channel. Only the approval of the City of Ft. Collins Departments of Natural Resources and Stormwater Management are required. MAY 01 '96 12:04 FR JPI 214 55.6 3860 TO 9:19702230511-004 P.02/09 JPz P.C. BOX 619208 • DA.LLAS, TEXAS 75261 9208 May 1. 1996 Michael G. Ludwig City of Fort Collins Current Planning Department 281 North College Avenue P.O. Box 580 Fort Collins, CO 80522-0580 Dear Mike: Please find the attached responses to the comments from your initial review of the Jefferson Commons PUD Final Plan, Based upon the revisions we are submitting for review today, JP1 and our attorney, Brad March, will be securing the dedications, vacations and easements as required by the revised plans over the next couple of weeks. We will forward these agreements to you as they are received. We appreciate your efforts in coordinating issues regarding this project with us, the neighborhood group and other City departments. If you should have any questions or problems concerning today's Submittal, please call me immediately at 214-556-3782 or 214-532-6600. Thanks again for your help. Sincerely, J. Patrick Rhamey attach. cc: Ric Hartman, Gefroh Hattman Brad March, March & Myatt Scott Queen, Ayres & Associates Dave Frick, Ayres & Associates Ocie Vest, Bury & Pittman Jorge Munoz, Kaufman & Meeks Daryl Benkendorfer, Land Design Partners 600 EAST ;_AS COUNAS B_VC. • CIGNA TpWER, SUITE 1600 • IRVING, TEXAS 75039 0 (214) 556.17oo 9 FAX (214) 556 3784