HomeMy WebLinkAboutHARMONY RIDGE PUD, PHASE ONE - FINAL - 49-95B - SUBMITTAL DOCUMENTS - ROUND 1 - STORMWATER-RELATED DOCUMENTSEARTH ENGINEERING
CONSULTANTS, INC.
June 25, 1997
Positive Environments, Inc.
P.O. Box 98
Fort Collins, Colorado 80522
Attn: Mr. Joe Vansant
Re: Subsurface Hydrogeologic Study
Harmony Ridge P.U.D.
Fort Collins, Colorado
EEC Project No. 1972027
Mr. Vansant:
It is our opinion that a groundwater hydrologic study will not be required for the Harmony Ridge
development. The groundwater study is required when designing an underdrain system to mitigate
high groundwater levels. We do not anticipate the need to install an underdrain system for the
Harmony Ridge project.
We appreciate the opportunity to be of service to you on this project. If you have any additional
questions concerning this project, please do not hesitate to contact us.
Very truly yours,
Earth Engineering Consultants, Inc.
Lester L. Litton, P.E.
Principal Engineer
LLL/dmf
cc: Rich Dvorak - TST, Inc.
CENTRE FOR ADVANCED TECHNOLOGY
2301 RESEARCH BOULEVARD, SUITE 1 04
FORT COLLINS, COLORADO 80526
(970) 224-1522 (FAX) 224-4564