HomeMy WebLinkAboutUNIVERSITY CENTER PUD (UNIVERSITY MALL REDEVELOPMENT) - FINAL - 2-96A - CORRESPONDENCE - REVISIONS (3)f , ,
18. Screening of parking areas has been shown on PUD and detailed on the
Landscape Plans.
19. Final size sheets will be submitted at 2406 (at time of filing), which will
provide a scale of 1"=60' for the PUD and Landscape Plan.
Sincerely,
Michael G. Mulhern
Principal
MGM/kap
AN96031\pud
1730 Blake Street, Suite 435 Denver, Colorado 80202 TEL: (303) 297-3334 FAX: (303) 292-2601
8. Fire Department comments are noted:
a. The complex is to be fully sprinklered.
b. Each tenant shall be on a separate fire sprinkler system-
C. Each unit shall have its own alarm dialer for the sprinkler system.
9. Light and power comments are noted.
10. Bucher, Willis & Ratliff has addressed water/wastewater departments in an
attached letter (in drainage report). Redlined drawings are included in this
submittal.
11. Per Jim Clark's comments a note has been added to the Landscape Plan stating
that irrigation plans shall be submitted to the City for review and approval.
12. Again, engineering comments have been addressed by Bucher, Willis & Ratliff.
See attached letter. As previously stated, previously redline comments are
attached.
13. Stormwater comments have been addressed in the attached civil engineering
letter.
14. Per Tim Buchanan's comments the aristocrat pear has been changed to autumn
blaze pear. And the note, re: transplanting, has been noted on the Landscape
Plan.
15. The South College ROW has been shown on the Site Plan.
16. The storage buildings shall meet the Code requirements in force at the time of
permitting. Should this require sprinklering it shall be done.
17. It is our intention that all development work will proceed concurrently.
However, as you know, it may be difficult to complete all leases concurrently.
Therefore, we propose that the following building work trigger the site work
as listed.
Building Department Site Development
a. Renovation of existing mall All improvements north
of Center Drive
b. Expansion of King Soopers
c. Addition of Tenant A
d. Storage Buildings
All improvements south
of Center Drive and
north of South Drive.
All improvements east
and south of said user.
All improvements
adjacent to said
buildings.
1730 Blake Street, Suite 435 Denver, Colorado 80202
TEL: (303) 297-3334 FAX: (303) 292-2601
3. The sidewalk plans at the east arcade show retention of the arcade and existing
planter beds in order to save the trees and maintain a 30' drive, which, due to
the parking lot layout, will be extensively utilized. As you will note in the
revised elevations we have strived to create pedestrian interest in the spirit of
the big box guidelines by varying the massing of the arcades, breaking up the
length of the arcades by introducing suspended canopies and stepping back major
signage facades, introducing multiple display windows along the arcade and,
finally, introducing street furniture and pedestrian lighting at all major entries.
4. Contrary to the previous submittal, we are committed to renovate the exterior
of the King Soopers store in accord to our proposed elevations throughout the
center. This is seen in our attached elevations. Accordingly, the landscape in
front of the grocer will also be upgraded and renovated.
5. Finally, as the mature trees, which we are seeking to save, will effectively
screen much of our building signage we are proposing to locate monument signs,
per City standards, adjacent to South College.
In addition to malting these revisions in our submittal we have sought to address your
comments of June 14, 1996, as well as any other outstanding issues. These items have been
addressed as follows:
A utility easement has been shown on the plat and PUD plan at the west
property line as well as south of proposed Tenant A.
2. The developer will bear the cost of the gas line relocation as well as provide
an easement for this service from South College to the rear of the building. See
the plat and PUD plan for the proposed relocation and easement. Information
on gas requirements will be forwarded to PSCo as major space leases are
finalized.
5. Per conversation with you and Ed Zdenek it is our understanding that the bus
stop as presently located is acceptable to transport. Therefore, the PUD plan
shows it in its present location.
6a. Building envelopes for the storage buildings have been clearly identified on the
PUD plan.
6b. Site dimensions for the location of the tenant "A" have been noted on the PUD
plan.
6c. Building elevation drawings have been included for the east and south building
renovations including King Soopers. Also typical drawings for the exterior
elevations of the storage buildings are also included.
7. Building Department comments are noted.
1730 Blake Street, Suite 435 Denver, Colorado 80202 TEL: (303) 297-3334 FAX: (303) 292-2601
r1 HE MULHERN GROUP, LTD
AF. CHI TECTU RE•G LA NNI146•IN TERI ORC
September 11, 1996
Community Planning and Environmental Services
City of Fort Collins
281 North College Ave.
Fort Collins, CO 80522-0580
ATTN: Mr. Stephen Olt, Project Planner
RE: University Center PUD - Final
Project #: 96031
Dear Steve:
Thank you for your letter of August 28, 1996, which detailed submittal requirements for the
University Center PUD - Final. We have worked feverishly to prepare the attached submittal
which, per your letter, includes the following:
25 Site Plans
10 Landscape Plans
3 sets of Building Elevations (with Arcade plans)
21 subdivision plats
10 sets of Utility Plans
3 revised Drainage Reports and associated plans
3 revised Traffic studies
Our work was all the more complex as J.R. Engineers was unable to meet our schedule,
however, we were able to engage Bucher, Willis & Ratliff who, as you will see, has revised
all civil work and addressed several outstanding:'issues identified by Engineering.
As you know, we are proposing several changes to the PUD plan. The documents have been
revised accordingly. These changes are as follows:
1. The freestanding Building "E" has been relocated north joining with the
previously proposed King Soopers expansion to create a new 30,000 s.f. Tenant
"A" with 2,100 s.f. of small shops sitting adjacent to a newly created pedestrian
plaza. As you will note, both plan and elevation have been designed to meet
the big box guidelines for distributed parking, multiple entries, building
articulation, height and arcades and awnings. All utility and drainage plans have
been revised accordingly and a subdivision plat included to eliminate tract "B"
to a$ow for said building. (Note: King Soopers will expand to the north into
the existing building and has plans to remodel the store in its entirety).
2. Areas of expansion on the west side of the center (loading area) have been
slightly reconfigured. (Do note that there has been no change in the proposed
square footage total of additions).
1730 Blake Street, Suite 435 Denver, Colorado 80202 TEL: (303) 297-3334 ' FAX: (303) 292-2601