Topic: Landscape Plans
Comment Number: 1
Comment Originated: 09/13/2017
Address more thoroughly landscape area treatment. Will need to see a more
comprehensive plan including turf, ground cover (including shrubs, grasses,
perennials, flowerbeds, and slope retention).
Topic: Lighting Plan
Comment Number: 8 Comment Originated: 09/13/2017
Please indicate kelvin temperature choice for lamps.
Comment Number: 9 Comment Originated: 09/13/2017
Overall parking area light levels seem to be lacking. Are there other light
sources coming from the neighboring buildings? Minimum parking area light
levels should be 1 footcandle.
Topic: Site Plan
Comment Number: 2 Comment Originated: 09/13/2017
Include pedestrian access area of trash enclosure on elevation.
Comment Number: 4
Comment Originated: 09/13/2017
Please locate mechanical equipment (RTUs, meter, vents, conduits, vents,
boxes, etc.) on site plan and elevations and provide information on screening.
Comment Number: 5 Comment Originated: 09/13/2017
Sidewalk ramps to accommodate handicap parking spaces and at the internal
sidewalk need to be clearly shown on the site plan.
Comment Number: 6
Comment Originated: 09/13/2017
Sidewalk from adjoining east property needs continuation onto the site.
Handicap parking space ramp/loading area can be moved to line up with the
above mentioned sidewalk connection.
Comment Number: 7 Comment Originated: 09/13/2017
Northeast sidewalk connection to align with landscaped area.
09/12/2017: Some of the right of way descriptions shown are incorrect. If they
are going to stay on the plan, they should match what is shown on the
Subdivision Plat.
Topic: Landscape Plans
Comment Number: 4 Comment Originated: 09/12/2017
09/12/2017: There are line over text issues. See redlines.
Topic: Site Plan
Comment Number: 1 Comment Originated: 09/12/2017
09/12/2017: There are line over text issues. See redlines.
Comment Number: 2 Comment Originated: 09/12/2017
09/12/2017: Please revise the legal description as marked. See redlines.
Comment Number: 3 Comment Originated: 09/12/2017
09/12/2017: Some of the sheet titles in the sheet index do not match the sheet
titles on the noted sheets. See redlines.
Department: Traffic Operation
Contact: Nicole Hahn, 970-221-68209 nhahn@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/12/2017
09/12/2017: The BIRO driveway seems pretty large, seems there will be higher
speed ins, crossing the sidewalk given the large radius?
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/13/2017
09/13/2017: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Department: Water -Wastewater Engineering
Contact: Heather McDowell, 970-224-6065, hmcdowell@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 09/12/2017
09/12/2017: To meet separation requirements between trees and the
proposed water and sewer service lines, I would suggest moving the water and
sewer services slightly.
Department: Zoning
Contact: Missy Nelson, mnelson@fcgov.com
Topic: Building Elevations
Comment Number: 3 Comment Originated: 09/13/2017
Comment Number: 5 Comment Originated: 09/11/2017
09/11 /2017: Please provide a detail of the proposed bike racks to be used.
Department: Stormwater Engineering
Contact: Basil Hamdan, 970-224-6035, bhamdan@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 09/12/2017
09/12/2017: The site disturbs more than 10,000 sq. ft., therefore Erosion and
Sediment Control Materials need to be submitted. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted do not meet requirements. Please submit; an Erosion Control Plan,
an Erosion Control Report, and an Escrow / Security Calculation. If you need
clarification concerning the erosion control section, or if there are any questions
please contact Basil Hamdan 970-224-6035 or email @ bhamdan@fcgov.com
Contact: Heather McDowell, 970-224.6065, hmcdowell@fcgov.com
Topic: Drainage Report
Comment Number: 4 Comment Originated: 09/12/2017
09/12/2017: LID/WQ requirements: A variance to the water quality requirement
was noted in the drainage report. We will accept that runoff from basin D cannot
be treated for water quality because this basin was always anticipated to drain
to the public roadway. However, we will not accept a variance for basin C.
Runoff from this basin will need to be captured in some way to be treated for
water quality.
Comment Number: 5 Comment Originated: 09/12/2017
09/12/2017: There are some minor comments noted in the redlined report.
Please address.
Topic: General
Comment Number: 2 Comment Originated: 09/12/2017
09/12/2017: It looks like the northernmost storm inlet is supposed to have an
open grated top. Please note this on the plans.
Comment Number: 3 Comment Originated: 09/12/2017
09/12/2017: Where will the underdrains for the permeable paver system be
located? Please ensure that the depth of these underdrain lines will work to tie
into the storm sewer system.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Construction Drawings
Comment Number: 5 Comment Originated: 09/12/2017
09/12/2017: Please revise the sub -title as marked. See redlines.
Comment Number: 6 Comment Originated: 09/12/2017
09/12/2017: Please correct the elevation of benchmark 48-01. See redlines.
Comment Number: 7 Comment Originated: 09/12/2017
identify the structure.
Comment Number: 6
09/11/2017: LANDSCAPE PLAN
Comment Originated: 09/11/2017
The proposed Landscape Plan indicates that tree canopy diameters may
encroach on the fire lane over time. PFA would like to ensure the integrity of the
EAE remains as the trees mature and a canopy develops. The EAE shall be
maintained to 14' in height. This comment is aimed to preserve the trees and
the fire apparatus.
Department: Planning Services
Contact: Clay Frickey, 970-224-6045, cfrickey@fcgov.com
Topic: Building Elevations
Comment Number: 6
Comment Originated: 09/11/2017
09/11/2017: The elevations for the trash and recycling enclosure show a
pedestrian access door next to the main service gate. The site plan shows a
separate pedestrian access point on the east side of the enclosure which is not
reflected in the elevations. Please make these two documents consistent.
Comment Number: 7
Comment Originated: 09/11/2017
09/11/2017: Please provide a perspective rendering of the building from the
northeast corner of the building looking southwest so staff can get a better
sense of the projections and recesses proposed for the east building elevation.
Comment Number: 8 Comment Originated: 09/11/2017
09/11/2017: While the building elevations as proposed meets 3.5.1 and 3.5.3,
staff recommends continuing the CMU for the base of the building except for the
corner of JFK and Boardwalk and the building entry. This would establish a
stronger base for the building and emphasize the brick portions of the building
more.
Comment Number: 9 Comment Originated:
09/11/2017
09/11/2017: The keynote legend on the elevations has several notes that say,
"refer to detail." None of the details were included in the building elevation set.
Please add these details to the elevations for your next submittal.
Topic: Landscape Plans
Comment Number: 1 Comment Originated:
09/11/2017
09/11/2017: The scale on the landscape plan is incorrect. The scale should be
labeled as 1 in. being equal to 20 ft.
Comment Number: 2 Comment Originated:
09/11/2017
09/11/2017: The legend on the landscape plan does not include the symbol for
shrub plantings. Please add this label to the legend.
Comment Number: 3 Comment Originated:
09/11/2017
09/11/2017: Please add a hydrozone table to the landscape plan.
Topic: Site Plan
Comment Number: 4
Comment Originated: 09/11/2017
09/11/2017: Where in the building will the enclosed bicycle parking be located?
Please identify this location more specifically on the site plan.
submitted plans.
> Be visible by painting and/or signage, and maintained unobstructed at all
times. Sign locations or red curbing should be labeled and detailed on final
plans.
Comment Number: 3 Comment Originated: 09/11/2017
09/11/2017: WATER SUPPLY
Hydrant spacing and flow must meet minimum requirements based on type of
occupancy. A hydrant is required within 300' of any Commercial Building as
measured along an approved path of vehicle travel.
The hydrant located at the existing secondary access drive to the east of the
proposed development will meet the hydrant location requirements with the
establishment of a fire lane within the site.
There currently is a hydrant deficiency along JFK of roughly 3000'. The
developer will be responsible for the hydrant requirement (every 600') along
JFK and shall install one hydrant along JFK.
COMMERCIAL REQUIREMENTS
> IFC 507.5 and PFA Policy: Hydrants to provide 1,500 gpm at 20 psi residual
pressure, spaced not further than 300 feet to the building, on 600-foot centers
thereafter
Comment Number: 4 Comment Originated: 09/11/2017
09/11/2017: FIRE CONTAINMENT or AUTOMATIC SPRINKLER SYSTEM
The proposed building exceeds 5,000 square feet (proposed 7,351 square
feet) and shall be sprinklered with a NFPA13 system or fire contained into fire
area of less than 5000 square feet.
>If containment is used, the containment construction shall be reviewed and
approved by the Poudre Fire Authority prior to installation.
>If an automatic sprinkler system is used, please contact Assistant Fire Marshal
Joe Jaramillo at 970.416.2868 with questions.
Comment Number: 5
Comment Originated: 09/11/2017
09/11/2017: PREMISE IDENTIFICATION: ADDRESS POSTING &
WAYFINDING
The address shall be posted on the proposed structure.
Code language follows:
> IFC 505.1: New and existing buildings shall have approved address numbers,
building numbers or approved building identification placed in a position that is
plainly legible, visible from the street or road fronting the property, and posted
with a minimum of six-inch numerals on a contrasting background. Where
access is by means of a private road and the building cannot be viewed from
the public way, a monument, pole or other sign or means shall be used to
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investmen
t-development-fees/electric-development-fee-estimator
Department: PFA
Contact: Cal Sheesley, 970416-2599, csheeslev@poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 09/11/2017
09/11/2017: FIRE LANES
Fire access is required to within 150' of all exterior portions of any building as
measured by an approved route around the perimeter. For the purposes of this
section, fire access cannot be measured from an arterial road (JFK and
Boardwalk).
To provide perimeter access to the proposed building, the proposed drive lane
(24' wide) shall serve as the fire lane within the site. See comment #2 for fire
lane specifications. If the fire lane ties into either of the existing private drive
outside of the property, it shall extend to the limits of the property, tying into the
existing private drives. Fire lanes shall be included on future plans for review
and approval.
Code language follows:
> IFC 503.1.1: Approved fire Lanes shall be provided for every facility, building
or portion of a building hereafter constructed or moved into or within the
jurisdiction. The fire apparatus access road shall comply with the requirements
of this section and shall extend to within 150 feet of all portions of the facility and
all portions of the exterior walls of the first story of the building as measured by
an approved route around the exterior of the building or facility. When any
portion of the facility or any portion of an exterior wall of the first story of the
building is located more than 150 feet from fire apparatus access, the fire code
official is authorized to increase the dimension if the building is equipped
throughout with an approved, automatic fire -sprinkler system.
Comment Number: 2 Comment Originated: 09/11/2017
09/11/2017: FIRE LANE SPECIFICATIONS
A fire lane plan shall be submitted for approval prior to installation. In addition to
the design criteria already contained in relevant standards and policies, any
new fire lane must meet the following general requirements:
> Shall be designated on the plat as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed width & 14 foot minimum
overhead clearance.
> Be designed as a flat, hard, all-weather driving surface capable of supporting
40 tons.
> Dead-end roads shall not exceed 660' in length without providing for a second
point of access.
> Dead-end fire access roads in excess of 150 feet in length shall be provided
with an approved area for turning around fire apparatus.
> The required turning radii of a fire apparatus access road shall be a minimum
of 25 feet inside and 50 feet outside. Turning radii shall be detailed on
2015 International Building Code (IBC)
2015 International Residential Code (IRC)
2015 International Energy Conservation Code (IECC)
2015 International Mechanical Code (IMC)
2015 International Fuel Gas Code (IFGC)
2015 International Plumbing Code (IPC) as amended by the State of Colorado
2017 National Electrical Code (NEC) as amended by the State of Colorado
Fort Collins has amendments to most of the codes listed above. See the
fcgov.com/building web page to view them.
Accessibility: State Law CRS 9-5 & [CC/ANSI A117.1-2017.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 129vult or 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Commercial: 2015 IECC commercial chapter.
Department: Light And Power
Contact: Clint Reetz, 970-221-6326, creetz@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 09/08/2017
Single phase power is readily available along the east side of JFK parkway.
Three phase power is in the area on the west side of JFK parkway and the
south side of Boardwalk drive.
Comment Number: 2
Comment Originated: 09/08/2017
Development charges, electric Capacity Fee, Building Site charges and any
system modification charges necessary will apply to this development.
Comment Number: 3 Comment Originated: 09/08/2017
As your project begins to move forward please contact Light and Power
Engineering to coordinate the transformer and electric meter locations, please
show the locations on the utility plans.
Comment Number: 4
Comment Originated: 09/08/2017
Street trees will need to be adjusted based on the location of the streetlights.
Forty feet of clearance to the streetlight will need to be maintained by shade
trees and fifteen feet by ornamental trees.
Comment Number: 5
Comment Originated: 09/08/2017
Please provide a one line diagram and a C-1 form to Light and Power
Engineering. The C-1 form can be found at:
hftp://zeus.fcgov.com/utils-procedures/files/EngWikiMikiPdfs/C/C-1 Form.pdf
Comment Number: 6 Comment Originated: 09/08/2017
You may contact FCU Light & Power, project engineering if you have questions.
(970) 221-6700. You may reference Light & Powers Electric Service
Standards at
hftp://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar
ds_FI NAL_18Novem ber2016_Amendment.pdf
You may reference our policies, development charge processes, and use our
fee estimator at
front and sides of the block face) in the center of all such parkway areas.
Comment Number: 4 Comment Originated: 09/14/2017
09/14/2017:
Please add the method of transplant (i.e. B&B or container) and tree sizes in
the Plant List. Canopy shade trees at 2', ornamental trees at 1.511, evergreen
trees at 6' height, and shrubs in 5 gallon.
Comment Number: 5
Comment Originated: 09/14/2017
09/14/2017:
Show location of any stop signs and street lights. Identify these fixtures with a
distinct symbol. Adjust distance of street trees to meet code requirement.
Stop Signs: 20 feet from sign
Street Light: 40 feet for canopy shade trees and 15 feet for ornamental trees
Comment Number: 6
Comment Originated: 09/14/2017
09/14/2017:
Include locations of any water or sewer lines on the landscape plan. Please
adjust street tree locations to provide for proper tree/utility separation.
10' between trees and public water, sanitary, and storm sewer main lines
6' between trees and public water, sanitary, and storm sewer service lines
4' between trees and gas lines
Comment Number: 7 Comment Originated: 09/14/2017
09/14/2017:
According to Land Use Code (LUC) 3.2.1 Section E.5, canopy shade trees
must be used in parking lot islands. In place of the Chanticleer Pears, please
use a suitable canopy shade tree in the parking lot, such as Catalpa or
Kentucky Coffeetree.
Comment Number: 8
Comment Originated: 09/14/2017
09/14/2017:
In addition to using unique symbols for each species, please also directly label
the species on the landscape plans.
Department: Internal Services
Contact: Clay Frickey, 970-224-6045, cfrickey@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 08/25/2017
08/25/2017: Comment from Neighborhood Services -Can you provided the
dimensions of the trash/recycling enclosure? The community recycling
ordinance which was passed last year requires all businesses and multi -family
complexes have recycling service that is equal to at least 1/3 of their service
volume (bin capacity x service frequency) by 2020. Consider building a larger
enclosure that will allow for adequate space to meet the requirements of this
ordinance.
Contact: Sarah Carter, 970-416-2748, scarter@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 2
Comment Originated: 09/19/2017
09/13/2017: Construction shall comply with adopted codes as amended.
Current adopted codes are:
Additionally, isn't there also grading occurring on both Landings Office Park
PUD and Landings Bay requiring easements?
Comment Number: 4 Comment Originated:
09/12/2017: There appears to be an existing pedestal between the sidewalk
and curb along Boardwalk Drive. The plans should indicate the relocation of this
pedestal to a location behind the sidewalk.
Comment Number: 5 Comment Originated:
09/12/2017: Is the porkchop median intended to be irrigated with a native seed
mix? It would seem that a hardscape median is easier for long term
maintenance.
Comment Number: 6
09/12/2017
09/12/2017
Comment Originated: 09/12/2017
09/12/2017: The repay for sidewalk and access ramp improvements along
Boardwalk Drive will be monumented in the development agreement and
required prior to a building permit.
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak@fcgov.com
Topic: Landscape Plans
Comment Number: 2
Comment Originated: 09/12/2017
09/12/2017: Unclear on landscape plans where native seed mix is to be
applied versus turf. Let's discuss during staff review 9/13/17
Topic: Lighting Plan
Comment Number: 1 Comment Originated: 09/12/2017
09/12/2017: Thank you for including luminaire schedule and selecting 3000K or
less LED fixtures thus supporting City Night Sky Objectives.
Department: Forestry
Contact: Molly Roche, mroche@fcgov.com
Topic: Landscape Plans
Comment Number: 1
Comment Originated: 09/14/2017
09/14/2017:
If there are any existing trees on -site, please contact City Forestry (Molly Roche
— mroche@fcgov.com) to schedule an on -site meeting to obtain tree inventory
and mitigation information.
Comment Number: 2
Comment Originated: 09/14/2017
09/14/2017:
Please use the most recent version of the City of Fort Collins General
Landscape Notes. These are available from Molly Roche at
mroche@fcgov.com.
Comment Number: 3 Comment Originated: 09/14/2017
9/14/2017:
Please use an accurate scale on landscape sheet 1. Currently, a 200 foot scale
is being used. City Forestry needs to measure the distance between
right-of-way trees. According to Land Use Code (LUC) 3.2.1 D.2.a, wherever
the sidewalk is separated from the street by a parkway, canopy shade trees
shall be planted at thirty-foot to forty -foot spacing (averaged along the entire
Fort Collins
Community Development and
Neighborhood Services
261 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
kgov. com/developmentreview
September 21, 2017
Cathy Mathis
TB Group
444 Mountain Avenue
Berthoud, CO 80513
RE: Boardwalk Office Building, PDP170032, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Clay Frickey, at 970-224-6045 or cfrickey@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcqov.com
Topic: General
Comment Number: 1
Comment Originated: 09/12/2017
09/12/2017: In general I'd like to coordinate with Planning to discuss with the
applicant how the proposed project may be able to tie into existing interior
sidewalks from existing development to the north and to the east. It appears that
there are opportunities to allow this project to feel more integrated into the
pedestrian network of the overall commercial network. As currently proposed
the project would appear to not be integrating into the existing network.
Comment Number: 2 Comment Originated: 09/12/2017
09/12/2017: I'd like to coordinate with Planning to discuss with the applicant the
pedestrian access off of Boardwalk Drive utilizing steps and the potential
concerns with this access from the public street system not being as accessible
for handicap pedestrians. Is there an ability to remove the stairs with
switchbacks or other design considerations?
Comment Number: 3
Comment Originated: 09/12/2017
09/12/2017: Part of the work shown on the plans specific to the six parking
spaces on the northeast comer of the site appears to be occurring
predominantly on property platted with the Landings Office Park PUD. Is the
work occurring to build this with permission from that property owner?