January 6, 2004 Administrative Hearing
Page 6
RECOMMENDATION:
Staff recommends approval of the Poudre Valley Health Systems — Harmony
Campus, Infrastructure Project Development Plan, #32-98D
Poudre Valley Health System - Harmony Campus, Infrastructure PDP, #32-98D
January 6, 2004 Administrative Hearing
Page 5
upstream, passing through the existing drainage channel, will be
addressed.
3. Public Sites, Reservations and Dedications Section [3.3.1](C) —
Rights -of way for public streets, drainage easements and utility
easements are being dedicated on the subdivision plat. These
rights -of -way meeting the City's design standards, including 9
(nine) foot -wide utility easements abutting the street. A
drainage easement is located within Tract D.
5. Neighborhood Information Meeting
Pursuant to Section 2.2.2(B), a neighborhood information meeting is not
required with this application.
FINDINGS OF FACT/CONCLUSIONS
After reviewing the Poudre Valley Health Systems — Harmony Campus,
Infrastructure Project Development Plan, #32-98D, staff makes the following
findings of fact and conclusions:
1. The proposed PDP meets the procedural requirements located in Division
2.1 - General Procedural Requirements, Division 2.2 - Common
Development Review Procedures for Development Applications, and
Section 2.4 - Project Development Plan located in Article 2 -
Administration.
2. The Project Development Plan is consistent with the Poudre Valley Health
Systems — Harmony Campus, Overall Development Plan.
3. The Project Development Plan complies with the Harmony Corridor
Design Standards and Guidelines.
4. The Project Development Plan complies with all applicable district
standards of Section 4.21 of the Land Use Code, the HC — Harmony
Corridor zone district.
5. The Project Development Plan complies with all applicable General
Development Standards contained in Article 3 of the Land Use Code,
including Section 3.3.1 - Plat Standards.
Poudre Valley Health System - Harmony Campus, Infrastructure PDP, #32-98D
January 6, 2004 Administrative Hearing
Page 4
d. Transportation Level of Service Requirements
A Transportation forecast memorandum (attached), including a
roundabout analysis, was developed based on build out of the
entire site and analyzed 4 intersections:
- Harmony Road and Timberline Road;
- Harmony Road and future Snow Mesa Drive entrance and
the entrance to the Harmony Road Community mobile home
park;
- Timberline Road and the main project entrance at
Timberwood Drive; and,
- Harmony Road and the proposed right-in/right-out access.
The study indicated that with future improvements, all intersections
affected by this PDP, would continue to operate at acceptable
levels.
The roundabout analysis concluded that the Timberline/
Timberwood intersection would be a candidate for a roundabout in
the future. However, the improvement is not likely in the near term
as new signal equipment was recently installed at this intersection.
E. Subdivision Requirements
1. Plat Standards [3.3.1] —As required, the general layout of the
lots, roads, driveways, utilities, drainage facilities, and other
services within the proposed development are designed in a
way that enhances an interconnected street system within and
between neighborhoods. Proper right-of-way has been
dedicated for public streets, and drainage easements, and utility
easements have been provided as needed to serve the area
being platted. Each tract has direct vehicular access to a public
street
2. Water Hazards [3.3.3] — The Stormwater Department has
reviewed the application and has indicated that it satisfies the
requirements of this standard. It is anticipated that a detention
pond will encompass most of the land within Tract D. As future
phases develop within the PVH Harmony Campus, the size and
design details to accommodate all on -site flows, including flows
Poudre Valley Health System - Harmony Campus, Infrastructure PDP, #32-98D
January 6, 2004 Administrative Hearing
Page 3
Note that the building design standards (building orientation and build -to
lines) do not apply in this case since this is a "campus" development.
Campus developments are one of two exceptions to this criterion. An
exception to the building design and orientation standards was granted at
the time the ODP was approved. As such, the site has been master
planned as a "campus" meaning that the development will be unified by an
internal framework of pedestrian -oriented, non -vehicular outdoor spaces
and walkways that function as an alternative to street sidewalks by
organizing and connecting building. The Infrastructure PDP continues the
campus -style layout defined in the original master plan; therefore, the
street and tract layout is considered compliant with the requirements of
this section.
5. Article 3 of the Land Use Code — General Development Standards
The Project Development Plan complies with all applicable General Development
Standards as follows:
a. Landscaping and Tree Protection
The PDP provides significant canopy shading to reduce glare and
heat build-up. Visual quality and continuity within and between
developments are addressed by provision of street trees along
Harmony Road (consistent with the Harmony Corridor Plan), and
newly dedicated extensions to Snow Mesa Drive and Timberwood
Drive.
b. Access and Circulation
The street circulation system will accommodate the movement of
vehicles, bicycles, pedestrians and transit safely and conveniently
throughout the site and to and from surrounding areas.
C. Master Street Plan
There are no streets internal to the site identified on the Master
Street Plan.
Poudre Valley Health System - Harmony Campus, Infrastructure PDP, #32-98D
January 6, 2004 Administrative Hearing
Page 2
COMMENTS:
Background
The surrounding zoning and land uses are as follows:
N: HC; Harmony Road, Harmony School Shops PUD, Harmony Community
Mobile Home Park
S: RL; Timber Creek PUD
E: HC; Wildwood Townhomes
W: HC; Harmony Center PUD
The property was annexed in February, 1986 as part of the South Harmony
Annexation. The 95-acre Poudre Valley Health Systems — Harmony Campus
Overall Development Plan was approved in January, 1999.
2. Article 2 - Administration
Development of an infrastructure plan and subdivision plat is subject to
administrative review. The PDP complies with the applicable requirements of the
LUC, specifically the procedural requirements located in Division 2.1 - General
Procedural Requirements, Division 2.2 - Common Development Review
Procedures for Development Applications, and Section 2.4 - Project
Development Plan located in Article 2 - Administration.
3. Compliance with the Overall Development Plan
The PDP encompasses all of the land area defined by the Poudre Valley Health
Systems — Harmony Campus ODP. Proposed public streets, including an
extension of existing Snow Mesa Drive, connecting to Harmony Road, and
extensions to Timberwood Drive, are consistent with the general alignments
shown on the ODP (see attached).
4. Division 4.21 of the Land Use Code, HC — Harmony Corridor Zone District
Development Standards specific to the HC-Harmony Corridor zone district are
defined in Article 4.21 of the LUC.
The PDP meets the applicable Land Use Standards as follows:
a. Campus layout
ITEM NO.
MEETING DATE DPI
STAFF 6ftjeW14L' sip
Citv of Fort Collins HEARING OFFICER
STAFF REPORT
PROJECT: Poudre Valley Health System — Harmony Campus,
Infrastructure Project Development Plan, #32-98D
APPLICANT: BHA Design, Inc.
c/o Luke Oldenburg
4803 Innovation Drive
Fort Collins, CO 80525
OWNER: Poudre Valley Health System
2809 E. Harmony Road, Suite 200
Fort Collins, CO 80528
PROJECT DESCRIPTION:
This is a request for a Project Development Plan to accommodate future utility
and street infrastructure serving the projected medical office and care facilities
within the approved Harmony Campus Overall Development Plan. The
subdivision plat included with this application creates 4 tracts and dedicates
public rights -of -way and easements necessary to serve future development. The
site is 72.585 acres in size and located at the southeast corner of Timberline
Road and Harmony Road. The property is zoned HC — Harmony Corridor.
RECOMMENDATION: Approval
EXECUTIVE SUMMARY:
The proposed infrastructure design is consistent with the approved Poudre Valley
Health Systems — Harmony Campus Overall Development Plan (ODP). The
PDP complies with the Harmony Corridor Standards and Guidelines, the District
Standards contained in Section 4.21 of the Land Use Code (the HC — Harmony
Corridor zone district) and Article 3 of the Land Use Code (the General
Development Standards), including the plat standards of Section 3.31.