-ratio of exterior wall area to interior
floor area is less than 1.5
0.3 points
-mass of exterior building walls greater
than 30 pounds per square foot
0.2 points
-overall wall U-value is less than 0.2
1.0 points
-overall roof U-value is less than 0.6
0.3 points
-automatic spark ignition used for heating 0.2
points
-there will be no electric resistance
heating used
0.2 points
-florescent lamps and electronic ballasts
will be used in the building
0.2 points
-low leakage outside and exhaust air
dampers used (1% leakage maximum at 5" W.C.)
0.3 points
-variable air volume system used, with
inlet vanes or variable speed drives
0.5 points
-furnace efficiency greater that 82%
0.2 points
TOTAL ENERGY CONSERVATION POINTS 3.4 POINTS
These energy conservation items listed above total 3.4 points. We will incorporate items into
the detailed building design that maintain a point total of at least 2.6 from these items. This will
"score" three of the four available points in this point chart line item. We realize that the City
of Fort Collins has adopted a new Model Energy Code and we anticipate that additional details
regarding this item will be required.
A.5. Development Phasing Schedule
The critical development phasing for this proposal is to coordinate the proposed changes with
the presently planned street changes at this intersection. Specifically, the proposed access and
frontage road changes to the east side of College Avenue and the south side of Drake Road can
be completed cooperatively with presently planned changes to minimize traffic inconvenience.
We anticipate this project to start approximately mid -August. We would like to provide the City
of Fort Collins Engineering department with some direction as to how best to proceed with the
proposed traffic safety improvements based on this PUD plan review. We want to avoid an
unnecessary delay or extension of the street improvement project schedule.
sandwich shop incorporated into the Schrader Oil facility near the new Fort Collins high school.
The QSR will be managed by a designated food service manager at the facility. We anticipate
that the customer base will be from our gasoline customers and the QSR will generate a very
limited customer base on it's own.
We will limit window signage for the building to company issued, professional quality, printed
posters in the extreme south and north window panels of the building. We will have one 3 foot
by 4 foot restaurant wall sign in addition to the 2 foot by 3 foot Sinclair wall sign. A portion
of our allowable sign square footages of each street sign will be dedicated to the food chain.
A.4.b-Statement of proposed ownership of public and private open space areas: We
expect to maintain ownership of all private open space areas (landscaping) within the subject
property. We have no intentions of changing the ownership of these areas in the future.
A.4.c-Estimate the number of business employees: 10-12 full and part time employees,
we presently employ 4 part time and 2 full time employees.
A.4.d-The assumptions for the business employees are based on similar company
operations and facilities with 24 hour operations.
A.4.e-Point Chart "D" for "Auto -Related and Roadside Commercial" activities has been
completed is attached as part of this application.
Variance Description
We are requesting a variance,in the "point chart criteria". Specifically, based on the extensive
cooperation of the adjacent property owners to significantly improve traffic flow in the area, we
request that this PUD be considered as "Part of a Planned Center" for an additional six points.
As a second variance, we will achieve three of the four possible points for "Energy
Conservation". Using the appropriate multiplier of two, we request a variance of two points.
Considering these two variances, we will earn 24 of the 48 maximum applicable points in Point
Chart D.
A.4.f-The potential conflicts between adjacent land uses are avoided because of the
inherent site design of the facility. Our clientele does not need long term parking, therefore,
we are not "robbing" space from adjacent uses. We have incorporated 3 employee parking
spaces into the site design to satisfy the long term parking needs on site. We are limiting the
site lighting and incorporating specific fixtures to minimize light spillage from the site onto
adjacent properties. We anticipate that our noise level will be significantly less than the typical
street noise associated with College Avenue and Drake Road.
A.4.g-As a part of the "Point Chart D" in item a above, we calculated the number of
energy conservation points to be awarded using the Energy Conservation Worksheet. We used
Method Two from Appendix "E" with the specific "energy conservation methods" that we will
implement listed below.
Statement of Planning Objectives
PUD Plan Submittal
Redevelopment Proposal for Sinclair Station ##05013
2600 South College
Southeast corner College Avenue and Drake Road
Fort Collins, Colorado
June 24, 1996
(August 20 revision including interior sales area discussion)
A.4.a-A formal Statement of City Land Use Policies is not appropriate for this submittal
because this project is strictly to redevelop an existing property consisting of infill within an
established area.
There are street and storm drainage improvements planned to the College Avenue and Drake
Road intersection as part of the Choices 95 Project scheduled to start in August of 1996. These
improvements include an 11 foot right of way acquisition from our existing property along Drake
Road. This right of way is for street widening, divider installation, bicycle lane installation and
a landscaping area addition. This right of way will essentially make our north fuel dispensing
island unusable. Because of other existing site conditions, the realistic relocation of this island
is not possible. There will be changes to our College Avenue frontage that will also make
access to this site difficult. In addition, there will be short term construction easements required
that will essentially close our business. Combined, this will create a distinct long term
commercial hardship for our business.
With the cooperation of other adjacent property owners, the City of Fort Collins Engineering
Department and the Colorado Department of Transportation, we have proposed access
consolidation and frontage road closures to significantly improve local traffic flow and safety.
In summary, this redevelopment proposal is intended to provide improved traffic safety at this
intersection and maintain a viable business in the City of Fort Collins. We are incorporating
significant landscaping and unique project items to develop and maintain a facility that genuinely
supports the significant community improvements in the area. This will be a lasting commercial
development that the City of Fort Collins and Sinclair Oil Corporation can be proud of.
The new facility will include an attractive, open, interior sales area for typical convenience store
and automotive items and a 350 to 400 square foot "quick service restaurant" (QSR). This
facility will provide similar offerings that match current industry trends to satisfy customer
needs. The present Sinclair facility on site provides limited convenience items. Historically,
in other Sinclair Oil Corporation stores we have offered many types of these convenience items
ranging from candy and chips to prepackaged sandwiches, hot dogs, microwave foods and
regional fast food products.
We are proposing to offer a nationally franchised food chain product to maintain a higher quality
that current customers demand. The QSR will be similar in operation to the "SUBWAY"