HomeMy WebLinkAboutEVERGREEN PARK REPLAT (NO. 1), BLOCK 5, LOTS 1 & 2 - PDP/FDP - 24-96A - CORRESPONDENCE - (6)If you have any questions regarding these comments, please do not hesitate to
call me at 221-6750.
Best egards,
Leanne A. Harter
xc: Mark McCullum
Stormwater Utility
Ron Gonzales/Poudre Fire Authority
file/Project Planner
Commur Planning and Environmental c --vices
Current Planning
City of Fort Collins
Brian Shear
Shear Engineering Corporation
4836 South College Avenue, Suite 12
Fort Collins, Colorado 80525
RE: Lots 1-2, Block 5,
Replat of Evergreen Park
Dear Brian:
August 11, 1998
Representatives from the Engineering Department, Poudre Fire Authority and
Current Planning Department met last Friday to discuss the above -referenced
project. There are substantial concerns related to fire access through the site,
and the comments listed below reflect necessary changes to comply with Code
requirements. In addition, there are comments related to off -site grading and
defining the LOD line that must be addressed with the submittal of revisions.
1. A turn -around for fire vehicles will not be permitted in the detention area as
proposed on the plans. Tum-arounds must be placed in a location wherein
unobstructed access is allowed at all times, and the proposed location shown
on the plans does not guarantee this type of access may be maintained.
2. The fire access lane on the south of the building on Lot 2 must be a minimum
width of 20' and signed as a fire lane with no parking allowed. If these
requirements cannot be met, the building must be fire sprinklered.
3. The curb return for this access road must be clearly signed as one-way.
4. A 13'6" clearance must be maintained along the south of the fire lane. This
clearance must remain unobstructed, without the slope as shown on the
plans. With the submittal of revisions, please submit a cross section of the
south property line of Lot 2 that demonstrates the clearance for fire
emergency vehicles and location of landscaping elements.
5. With the submittal of revisions, please provide a letter of intent from adjoining
property owners wherein off -site grading will occur.
6. The Limits of Development line and 100' buffer must be shown on all plans,
including the utility plans.