HomeMy WebLinkAboutMULBERRY / LEMAY CROSSINGS PUD, LOT 2, FILING 2 - FINAL PUD - 36-96E - CORRESPONDENCE - REVISIONS (7)Mr. Ted Sheppard
October 10, 2000
Page 6
The canopy on this building was shown to overhang into the easement. It has been
adjusted so as not to overhang into the UE.
Please contact me should you need additional information as we move toward the
scheduling of the Planning and Zoning hearing in November.
Sincerely,
CLC ASSOCIATES NC.
Kurt D. Prinslow
Vice President
KDP:cst
Enclosures
cc: Mark Goldberg, Goldberg Property Associates, Inc. (with attachments)
Lucia Liley, March and Liley (without attachments)
Mr. Ted Sheppard
October 10, 2000
Page 5
Stormwater
1. Please resubmit the Floodplain Use Permits to the City Floodpalin Department with
the correction elevations.
Refer to the attached revised Floodplain Use Permit for Lot 2, Building "C". All other
finish floor elevations are consistent with permit.
2. The Cost Estimate must contain an item for the re-seeding/mulching of the total
disturbed area.
Refer to the attached revised Cost Estimate.
1. The Cost Estimate must contain an item for the re -seeding / mulching of the total
disturbed area.
The revised Cost Estimate has been included with this submittal.
2. This one has gone to hell in a hand basket ( City Manager, Rodeo Detentionpond,
Roundabout, etc. ) I give up.
The overlot grading has occurred on the site and currently the infra -structure is
under construction. The Owner and General Contractor have contacted Bob Zakely
regarding inspections on the Erosion Control measures. Mr. Zakely has inspected
the site and the Contractor is making the corrections and completing the work.
New Century Energies
1. In general, PSCo gas mains will be 4 feet back of walk in the 9 foot UE.
No comment
2. Water meter pit for Retail C cannot be in this location. There will be a 4" gas line in
the 9 foot UE, and there is no room for the pit.
The water meter pit has been moved.
2. The Retail C building appearts to overhang into the 9 foot UE. If this the case, it is
not acceptable.
Mr. Ted Sheppard
October 10, 2000
Page 4
The required fire hydrant spacing is met and a letter from ELCO will be forthcoming.
4. Corrosives, flammable liquids, reactive, or toxic materials (as defined in the Uniform
Fire Code) if used, stored, orhandled on -site must have Hazardous Materials Impact
Analysis (HMIA) completed and supplied to the Planning Department and the Fire
Department.
The required permits for hazardous materials used on -site will be secured.
5. Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every new
building equipped with a required fire sprinkler system or fire alarm system.
"Knox Box" will be included on all buildings.
6. This proposed building shall be fire sprinklered. This applies to Buildings C, D, E,
and F.
The sprinkling of Buildings C, D, E, and F will be addressed in the Building Permit
plans.
7. These proposed building exceed 5000 square feet for type V construction and must
be fire contained or fire sprinklered. This applies to Buildings I and J.
The type of construction of these buildings will be addressed in the Building Permit
plans.
Engineering
Plat
• You are not re -platting with this project?
Will either need replat or provide the easements by separate document that
are needed for the water and sewer mains, storrmwater facilities, and for all
the other utilities to access and serve the site and buildings (i.e. PSCo,
Cable, US West, Light and Power). One solution is to provide all the area
outside of the building envelopes as a utility easement.
Please refer to the attached Mulberry and Lemay Crossings, Filing 2 Final
Plat.
Mr. Ted Sheppard
October 10, 2000
Page 3
The Site Plan has been modified so that the building envelopes and dimensions are
more distinct; bike racks have been added by Buildings D and J; and the side walk
note has been revised.
7. The following comments apply to the architectural sheets 4-7:
Comment "A." The signage has been added to the elevations and the note
regarding signage has been added.
Comment "B." The typical eyebrow canopy has been added along with the
requested note.
Comment "C" The arched faux window detail has been added to the facades
redlined on sheets 4 & 5.
Comment "D" The gooseneck light fixture has been added to the elevations
redlined on sheets 4, 5, and 6.
Comment "E" Additional typical heights have been added to all architectural
elevations.
8. Please reduce the height of the handicap parking sign.
This has been corrected.
Poudre Fire Authority
1. A fire lane is required, this fire lane shall be visible by painting and signage, and
maintained unobstructed.
The fire lane has been labeled as an "Emergency Access Easement" and this has
been shown on the enclosed Final Plat.
2. Address numerals shall be visible from the street fronting the property, and posted
with a minimum of 6-inch numerals on a contrasting background.
The address numerals will meet this requirement.
3. Fire hydrants are required with a maximum spacing of 600 feet along an approved
roadway. Each hydrant must be capable of delivering 1500 gallons of water per
minute at a residual pressure of 20 psi. Note : A letter from ELCO Water District is
required to verify fire flow of hydrants.
Mr. Ted Sheppard
October 10, 2000
Page 2
Enclosed you will find the following plan sets:
5 Folded copies Final Planned Unit Development (cover sheet, site
plan, and site details)
1 Unfolded copy Final Utility Plan
1 Copy Final Drainage Report and Drainage Plans
1 Folded copy Landscape Plan and Details
2 Folded sets Architectural Elevations
6 Folded sets Final Plat
In addition to these revised plans, we are offering written comments to the various
reviewing agencies:
Current Planning
Please refer to the attached comment sheet from Engineering.....
These comments will be addressed later in this correspondence.
2. Please refer to the attached comment sheet and "redlined" Drainage Report from
Stormwater....
These comments will be addressed later in this correspondence.
3. Please refer to the attached comment sheet and those from New Century Energies
( PSCo )....
These comments will be addressed later in this correspondence.
4. Please refer to the attached comment sheet from Poudre Fire Authority....
These comments will be addressed later in this correspondence.
5. Please make the following revisions to sheet 1 of 11.
The Cover Sheet to the Final P.U.D. Site Plan has been revised to incorporate a
total building square footage in the site data table, the starting date has been
revised, and the Multi -family to the north has been noted as existing.
6. Please make the following revisions to sheet 2 of 11:
CLC
Associates, Inc.
8480 E. Orchard Rd.
suite 2000
Englewood, CO 80111
303/770.5600
303/770.2349 FAX
Planning
Engineering
Architecture
Landscape Architecture
Land Surveying
October 10, 2000
Mr. Ted Sheppard
Current Planning
City of Fort Collins
281 North College Avenue
Fort Collins, CO 80522-0580
RE: Mulberry and Lemay Crossings, Filing 2, Lot 2
Final Planed Unit Development (PUD) Re -Submittal
Dear Mr. Sheppard:
Accompanying this cover letter are the five (5) sets of the revised submittal plans of the
Mulberry and Lemay Crossings Lot 2 Final PUD; two(2) sets of Architectural Elevations;
one (1) set of the revised On -Site Utility Plans; There are also three (3) copies of the
Landscape Plan and one (1) Final Drainage Report and Drainage Plans. All of these
documents are dated October 3, 2000. These revisions to the Final P.U.D. Submittal and
Utility Plan are based on the written comments and accompanying "red -lines" we received
on the following dates:
Department/Agency Received
Utility - Storm water August 3, 2000
Engineering August 3, 2000
New Century Energies - PSCo August 3, 2000
Poudre Fire Authority August 3, 2000
These "redline" sets / plan sheets are being returned for use by the respective departments:
Stormwater Final Utility Plan ( 3/10/00 )
Planning Architectural Elevations sheets 4,5,6,and 7