An Administrative (Type 1) Public Hearing has been scheduled for Monday,
September 10, 2007 at 4:30 p.m. in Conference Room A, 281 N. College Ave. If
your project development plan is approved at this public hearing you will be required
to submit Final Plans (revised per this comment letter) and the applicable Final Plan
fees. Please be sure to return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6750.
Sincerely,
k ocV�
Shelby Sommer
Associate City Planner
Page 3
[8/15/07] The plat in plan view has mislabeled the lots and blocks... should be tract
C, lot 5 and 6, block 2 not lots 1 and 2 block 1, Tract A. With that said, my comment
takes the back seat to Shelby Sommer and Tech Services. It is they who will
determine the appropriate title of the property. Thanks.
Number: 4 Created: 8/15/2007
[8/15/07] Should Tract A also be dedicated as a private irrigation easement as well?
I'm not sure that the drainage and utility easement is giving somebody the easement
that they really need.
Number: 5 Created: 8/15/2007
[8/15/07] Corrections required to the statement of ownership and subdivision, see
redlines.
Number: 6 Created: 8/15/2007
[8/15/07] The tract table has the lots and the tract incorrectly labeled if the project
title stays the same.
Number: 15
[8/22/07] From Technical Services:
1. Boundary closes.
2. Change Title.
3. Remove Block One
4. Who owns and maintains Tract A?
Created: 8/22/2007
Department: PFA Issue Contact: Carie Dann
Topic: Fire
Number: 12 Created: 8/22/2007
[8/22/07] PFA has no comments or concerns at this time.
Department: Traffic Operations Issue Contact: Ward Stanford
Topic: Traffic
Number: 11 Created: 8/21 /2007
[8/21/07] If re -grading of 2 lots is it, no Traffic issues.
Department: Stormwater-Water-Wastewater Issue Contact: Basil Hamdan
Topic: Stormwater
Number: 14 Created: 8/22/2007
[8/22/07] Please label the revision in the bubbled area as well as in the revision
block with a number, such as revision 1, then describe it and date it in the revision
block.
Department: Zoning
Topic: ZONING
Number: 10
Issue Contact: Jenny Nuckols
Created: 8/21 /2007
Page 2
(01[92!
City of Fort Collins
Mark Foster
7251 W 20th St #C-200
Greeley, CO 80634
STAFF PROJECT REVIEW
Date: 08/24/2007
Staff has reviewed your submittal for MAPLE HILL THIRD REPLAT PDP - TYPE I
(FORMERLY BLOCK 2 LOTS 5 & 6 AND TRACT C REPLAT), and we offer the
following comments:
ISSUES:
Department: Advance Planning
Topic: General
Number: 8
[8/20/07] No comment.
Department: Current Planning
Topic: General
Number: 13
[8/22/07] No issues.
Issue Contact: Pete Wray
Created: 8/20/2007
Issue Contact: Dana Leavitt
Created: 8/22/2007
Department: Current Planning Issue Contact: Shelby Sommer
Topic: General
Number: 1 Created: 8/7/2007
[8/7/07] The following departments have no concerns with this proposal: Park
Planning, Environmental Planning, Comcast, Xcel Energy, GIS, ELCO Water
District, Boxelder Sanitation District, Post Office, and Building Department.
Number: 9 Created: 8/21 /2007
[8/21/07] The project title should be revised to "Maple Hill Third Replat" being a
replat of Lots 5 and 6, Block 2 and Tract C.
Topic: Plat
Number: 2 Created: 8/8/2007
[8/8/07] County Assessor: The current owner of record for Tract C is Maple Hill
Master's Association. They will also need to sign the final plat. Thank you. For
questions please contact Megan Harrity at 498-7065.
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number: 7 Created: 8/17/2007
[8/17/07] The utility plan revisions are ready for mylars.
Topic: Plat
Number: 3
Created: 8/15/2007