Loading...
HomeMy WebLinkAboutMAPLE HILL, PHASE ONE - PDP - 29-00A - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTexceeds this value 1.0 is used in its place. Gutter (or channel) travel times were determined by utilizing Figure 3-3 for the flow velocity within the conveyance element. The travel time was then determined by dividing the gutter flow length by the velocity. This procedure for computing time of concentration allows for overland flow as well as travel time for runoff collected in streets, gutters, channels, or ditches. After the peak runoff was calculated, attenuated runoff was calculated. This was done by combining all contributing areas upstream of a given design point. The time of concentration for the design point was taken as the greatest time of all the contributing subbasins. 3.2 Drainage Plan Development The proposed drainage plan consists of a combination of overland flow and gutter flow. The runoff will sheet flow across landscaped yards and common areas, then concentrate at proposed streets. Gutter flow in streets will be collected at low points via curb inlets or area inlets and then conveyed via a storm sewer system or drainage pans to the detention ponds. Subbasins were delineated based on the proposed grading. Final grading and basin delineation is shown on the Rational Drainage Plan Sheet, which can be found in the back of this report. The site has been graded to accommodate two (2) detention ponds, however, they have been hydraulically linked to function as one detention pond. Most of the site runoff will be directed through this pond prior to discharge to the Larimer/Weld No.8 Ditch (No.8). The development has been restricted to a 10 cfs release rate, except at the northeast corner of the site where the Lind Farm property will discharge into the ditch through a series of swales and storm sewer pipe. Basin A encompasses the western portion of the site. Basin B encompasses the middle/right portion of the site. This includes the proposed multi- family area and the neighborhood park. Basin C encompasses the southwest part of the site. Basin D encompasses the northeast portion of the site. Basin E encompasses the southeast portion of the site. Runoff from each of the basins will be collected by a storm sewer system and directed to the proposed detention pond. TST, Inc. 7 November 18, 2002 0953-003 10 Developed Conditions Plan 3.1 Deslan Criteria The drainage system presented in this report has been developed in accordance with the criteria established by the City of Fort Collins Storm Drainage Design Criteria and Construction Standards Manual (SDDC) dated May 1984 and revised in January 1997. Where applicable, design guidelines and information were also obtained from the Denver Regional Council of Government Urban Storm Drainage Criteria Manual (USDCM). Developed condition hydrology was evaluated based on the 2-year and 100-year storm frequencies as dictated by Table 3-1 of the SDDC manual. Because of the limited size of the subbasins on the site, the Rational Method was selected to calculate runoff. However, the detention pond was analyzed and designed using UDSWM, which will be discussed in Section 3.2.5. The Rational Method utilizes the SDDC manual equation: Q = CCAA where Q is the flow in cfs, C is the runoff coefficient, Cf is the storm frequency coefficient, I is the rainfall intensity in inches per hour, and A is the total area of the basin in acres. The runoff coefficient, C, was calculated from Table 3-3 of the SDDC manual based on the proposed developed condition land use. A composite runoff coefficient was calculated for each sub -basin based on the percentage of impervious surface (C = 0.95) and pervious surface (C = 0.25). Cf was taken from Table 3-4 of the SDDC manual and was determined to be 1.0 for the 2-year storm and 1.25 for the 100-year storm. The appropriate rainfall intensity was interpolated from the rainfall intensity duration table in Figure 3-1 of the SDDC manual dated 1999. To obtain the rainfall intensity, the time of concentration had to be determined. The following equation was utilized to determine the time of concentration: tc = ti + tt where tc is the time of concentration in minutes, Q is the initial or overland flow time in minutes, and tt is the travel time in the gutter in minutes. The initial or overland flow time was calculated with the SDDC manual equation: t. = [1.87(1.1 - CCf)Lo.$)/(S)0.33 where L is the length of overland flow in feet (limited to a maximum of 500 feet), S is the average basin slope in percent, C is the composite runoff coefficient, and Cf is the storm frequency coefficient. The formula limits the product of CCf to 1.0 and when the product TST, Inc. 8 November 18, 2002 11 0953-003 F::'l 0 fZ W CK ,I 1 I C I ill t I I !} �► I �I I � ���II \ �\\1 11 11`i IIII \\\\\ } I I HYDROLOGY TABLE DESIGN BASIN AREA (ACRES) COMPOSITE'C' QZ (CFS) Q {oo (CFS) POINT Al A2 44.5 66.3 0.20 0.20 6.78 7.83 30.50 36.54 AZ A2 Al AND A2 110.80 0.20 13.08 60.74 NN o ASIA r / \\\\\\\\ I -Al \\ .5ac 'ZI It zil r Il+ll/ i�/I� 1j1j IIII I111 II}} IIII I ! 1 I / / /V t/ Al \� A2 GILLESPIE PROPERTY SCALE IN FEET CR 52 0 Ix m W N E mE mUgm N O �aa^mm NLL�LL 5 sawWa+MO pn onn AG se eY sew 8f01111 Mp1111 �I a.yert for cnewt. ►arm, .y " .�„ > - Al c ed by 2 7oQ rtarm f r :r flown Al 1 `n q {�.T; • 6 s ' JT .r I 1 2 ,Fbc Of . 6, to GIs J i. \ 1 �1f 11tt i'l llt l4l5l ,+lt t'tl\jt i 1 1 ,r % r / i� L �4a.°m�Yj`" _ ` x }7 r .♦ - , � � '�`�•• !�� t r'iil�l l�jh, ,:i itltl lL l' J, r ! !' ar; '�i'��5d'4-trk,5?� � ._� s ♦ `'�+ _ __ i p '• I ' I J , '1 ill+ I , ' r / J- T iF �.. r ♦ ♦ - r ^ r -\ � !II '1!i 1 `!'rl Ililll I•!•; , �''•r ! / ''_P'-r1�Y,�ihw.�i�tL -�'^ ♦♦` i � (' p !1 /I; rrJ tlllt. q4 IIIrI i;�:ti// � � / r It /.k�ri �++aa4 �" ���tli �`•'G�+.�"1 �`� \ J �,, !^ • I{ ,. 1= !, !I! !! �, 1t II {,'.'il!, / t ♦('�t� 11 /�E.....:1---♦ �•. — COUNTY i 1 � � •• + ."f%,%lli r'riir j/ 11„'q, t 1,�+11lllel � 1: / ! /> v �x�rr ... _._. �`'-o .., .," ~-``��-� �''..••r;/'f'Jel Ir / il.l ait y,Sll I I ! r ! ''�r r/ ri'• ?,t.,`•r �•- I q° •. , � j-`-�::�`1. ♦ l l��� �/ j/t % r //'J! tl�l a, yt�+ 111•+t J Jl•.' r° w». a 11, .0 ! -, , I!!•! „/r/l rl1: i,i/!/ /'jJ t �p(('•-.1\t 1! ,/r;//!; 7/,/, 11! 1� t J ! 1'. / d> l y/c i r Yt ll)•r!,,..- QI `: ,1/1 /1 /!'J ItJItIR!e1 / /.-! faaJ qJt , a!ffi 1 .♦•. _•_ o � 'xlt�l I1' !r,J/J/!�/f /, f 4 !f i111 �1!@I ! 11>:)�f ,'Y � ^J�at�3�.,,t♦'� �`-._-...♦ i� \ JU% • Ai .' .{7 yy!' r !i 1!! / ,I 1711!I/ 1,11 t ( l �9 1 1 xr �/,� j t I r•^el �T�I�SVi�i!t!•�/1���!!J!!�'•f lJrr �,i�l �tlt�ll�i1'� J!r /} �„? S+•'�j ,/�i , \,,,_ �._... - __--__-__-__ ` fi i ? +It 1! rl !rr !t!r rtrl11! r/ !� l,�r� ,r >�0,,f v`-♦. I f h. 1 t ill ' J; lil .bl i/ �- � � � • _ �,.1�/il�ll ���jrll��i`A 1; �I %/!�,!% t 1' I1 / t /l i !f '1'p �vaY/� �•$�yIJ ` •v t Y*♦ >`1 //1�l1 !, r111r ' !! 1 ( / / !'.i�l r �t� rJ �'YY t' ...\ ....-`• 102 t J I L70 6S tl \ `'� �. '�'��/;�, Il! i i • / r i / fr lr 1 !1 ! 77 69 p , i t mot'\rii /!f . !, / Y ! w t i t q/ i ! '/ {{d+t't• ! / i9'/ � w 1l a! 1.'�\.` /r�ll�l rl/11 Jflf lii 11;1 / 1+ , /"� IIYT 'J' _ s�„`J ( �'```♦ r- � � I '._S \i i' j'ii 101 J i r 1� 1! r 1 f I; V 1 i J f J 1 r/ 1/' 1r ,. .'F / ,, 8.^.,��'•'.• . ll;l,J,ll ! 1 t r 4 �•� r 7 'rs� _t jO�`-_1�'♦ N 63 1 � ' j ? ; fl � it j ;1 1 -s �• . l w t `• (, / 1 f 1 > f 1 1 ! 1 f , / f 1 1 ! ! ! / ! w / il.-a".!¢. 1 /' t. _• i7. ♦�♦ Il•001 1 If l 1�1W ¢, f•tt t�'h.. I .'�/{, 1i 1�1/:!/lJ ltq fl//1 I•� I{ firl '!t`.F�'`: >�\_ „yt./p q' �it �`Ci �i�t"�.}1. ``�,1ti,rl I ij�: r/'1 7 (f� y 1 ! f i t i ! i l , !_hef 1. /J 1 `♦ Milo ¢ l�•�t eta y,L;,rr?it, r; r , t , � 1a'r�t , , ; w'lY�l O � I ! }t gN!rtt t1/t •1�i9' )L !r• / r J / 1 I t I / 1 1 / / t 1 :Fs. -, Itt tr� -. _, t ,y e {! Sr H �'' �la:Li'�+1�'!•.:-v{, �, i;das r3 .. ._ 1 1 t ` r,� ', l�i..�=YT�r..• ".:, i , �at'�ir.. �.ri.�. �c'�.s+:'iwt:s �„ ' ..;n {� � r 11 � 1•} L�,'. �,tis`f� it}li'/ ilitt +,1 t�` f � ! � , f 1 Fy�a�.. i-/ ' /{, t . ` 107 � � �l r, ll!!i `Ifi L'l•1U�1.t\III+'ll still rl trt 1t♦l ♦3, k. rt� l S !'�rvz y/ Q 7.96 63 O �♦ 1 p , ' ! f t t 1 t I } t l' I 1 r I / i � ! +J l T. .y- ! / a'�' , w pt V r8171 i yaf f I I '•mt ,. 1 I I t , J ! f ..- \,��r- x.v^ � . 1 -- � ' t N I Rf 6Y1 r, I�t � f •q 1 1 / tr !. ., \: ^1 'r � 1 t ram• ., O .l O� a 'I rrJ l,'• Ir, !'111 '. �.� 'I�lr l;. fil; 71(//J` t!)t it l;I+- i =! I 1 t 1 / t �,^ , ♦ , :�O"'• r :. rJ r: it ir'; it/l1J rl!r,rl �'ltl ll'il li'Itq � y { r e t I 1 ! rL.x� +.. 1 �s5,.'� � I tJ 1\ LU(1i ;�//lll lrl��l1 `1!!I• l,rli �l+�(il�!.r11 1 , ' it � j tt f �K'�' C t;.� V\l \ 1"""t"��`0�... �.,, .i_ I ',I,-. 1� (. Ii /, /!/: ,•/: !ll ', 1f l t lr:c t<! I J ! t`a tt ,- i'.�'. �t .r,ws�L r •fr ,,,/ ! rr ;t{, 1c flt 1 t l t4><•£ t p�•�t 4�.1.+s1.:;. I { r � t p 3 la` � 1 tr/1: �11 Illl!7f 1; 1!J,!ttf i ' \•`!lit C•�� ��,\1/7/ !!/!!! li., rJ, J I/! ! 1" w•\nviJ �;ro 7 • .. 103 !� ; �r!!1 ri� rl It 11.00 63 Q , IL 11t1};tL1 + i J ! !! ,� J , f!r r! % 1 % !) f ,-h, '" to 1` \\ `\v ,�♦ i c _�1�!- ems' - w -.fl;Il1111414i�l,/J%/!i!!!l},t!!: I! I 1 1 r:I! / 'I OS ' p i t Of ;fY'tR \. • t \ ♦ l 7 �� , ti f,l. `�t11,S, {I ',: qi !,/� }'11I1 I r i Ir 'Iaz/ r... T•y 66 ♦�♦♦t\',, t, t'lI t ! 4 �li Iq,l1 11 t',VN yt�il;tif ��i�j �i±�l 11 ,1 lgli='1' �Ir. F♦`.,\1 ' �) `�` l t !'., �ly.l li-JyFla •,11,111ti1 i/.71J 1`V+S.v� 72t��. ,�['., i•.1�\`\\.�,I 1t I�'.+! , `� 171Jr it /1\, ,1 t; ,�\4 ♦`\�•.L,ti \\\ttl, ll lit 11 , .,+ 1_r. �,. R °n F W dc Lj O N W CD M wrYS" 1 OF 1 FIGURE I VICINITY MAP Scc% 1 " = 2000' r� 100 Introduction 1.1 Scope and Purpose This report presents the results of a Final Drainage Evaluation for Maple Hill. In accordance with the requirements of the Fort Collins Storm Drainage Design Criteria and Construction Standards Manual (SDDC), the purpose of this report is to present a storm drainage plan that identifies peak runoff conditions and provides a means by which to safely collect and convey runoff across the site. This report will evaluate hydrologic conditions for the proposed development to determine the location and magnitude of the storm runoff, and will use that information for hydraulic analysis of the proposed streets and conveyance facilities. 1.2 Project Location and Description Maple Hill is a proposed 451 single family, 76 duplex dwelling unit and 25 building (8-plex), 200 multi -family dwelling unit development located in the Northwest Quarter of Section 32, Township 8 North, Range 68 West of the 6"' P.M., City of Fort Collins, State of Colorado. The site is bounded on the west by County Road 11, the south by existing agricultural land, the east by the Larimer/Weld No. 8 Irrigation Ditch (No. 8) and the north by County Road 52. A vicinity map illustrating the project location is provided in Figure 1. This project is located entirely within the Cooper Slough/Boxelder Drainage Basin. A master drainage study currently does not exist for this portion of the basin. However, the existing topography indicates that the proposed site drains to the No. 8 ditch and conveyed south. TST, Inc. 1 November 18, 2002 0953-003 TABLE OF CONTENTS 1.0 Introduction Page 1.1 Scope and Purpose...................................................................................................1 1.2 Project Location and Description...............................................................................1 2.0 Historic Conditions..........................................................................................................3 3.0 Developed Conditions Plan rtl 3.1 Design Criteria ...........................................................................................................6 3.2 Drainage Plan Development......................................................................................7 3.2.1 Street Capacity 14 3.2.2 ........................................................................................:... Inlet Design..................................................................................................14 3.2.3 Storm Sewer Design....................................................................................19 3.2.4 Swale Design ................ :................................................................. ............. 19 3.2.5 Riprap Design 3.2.6 ..............................................................................................19 Detention Pond Design................................................................................ 24 3.3 Erosion/Sediment Control Plan................................................................................25 Figures Figure1 - Vicinity Map................................................................................................................2 Figure 2 - Historic Drainage Map................................................................................................4 Figure 3 — Lind Property Historic Drainage Map.........................................................................5 Tables Table 1 — Hydrologic Calculations Worksheet........................................................................8-11 Table 2 — Summary of Attenuated Runoff ....... :—'.... .............. ............... .. ... ............. ....-- .... 12-13 Table 3 — Summary of Street Capacity Analysis..................................................................15-16 Table 4 — Summary of, Inlet Analysis and Design.................................................................17-18 Table 5 — Summary of Storm Sewer Design........................................................................20-22 Table 6 — Summary of Riprap Design.......................................................................................23 Technical Appendices Appendix A — Rational Method Analysis Appendix B — UDSW M Model and Detention Pond Analysis Appendix C — Street Capacity and Inlet Analysis Design Appendix D — Storm Sewer and Riprap Design Appendix E — Swale Design Appendix F — Erosion Control Sheets RationalDrainage Plan..............................................................................................Sheet 1 of 1 UDSWMDrainage Plan.............................................................................................Sheet 1 of 1 November 18, 2002 Mr. Basil Hamden City of Fort Collins Storm Water Division P.O. Box 580 Fort Collins, CO 80522 Re: Maple Hill Project No. 0953-003 Dear Mr. Hamden: t We are pleased to present you with this Final Drainage Report for Maple Hill. This report was prepared based on Urban Storm Drainage Criteria and City of Fort Collins criteria. We believe it satisfies all criteria for a final report. This report also includes I discussion of erosion and sediment control measures that will be utilized during and after construction. We look forward to your review and comment and will gladly answer any questions you may have. Sincerely, IINC. NSULTING ENGINEERS t arsono SD/sjk Enclosures TST, INC. Consulting Engineers 748 Whalers Way - Building D Fart Collins, CO 80525 (970)226-0557 Metro (303) 595-9103 Fax (970) 226-0204 Email info@tstinc.com www.tstinc.com FINAL DRAINAGE REPORT FOR MAPLE HILL Submitted to: CITY OF FORT COLLINS November 18, 2002