2/13/04 N
#29-OOC/D
Maple Hill First & Second Replats
Type I (L U C) 1 inch : 1000 feet
3. Compliance with General Development Standards:
The First Replat complies with the following applicable General Development
Standards:
A. Section 3.3.1(B) — Plat Standards — General Provisions - Lots
The First Replat creates two additional lots that have the proper lot size for the
zone district. Both lots front on public streets. Side lot lines are at substantial
right angles to street lines. Alley access is provided at the rear of the lots.
The Replat does not impact the layout of roads, driveways, utilities, drainage
facilities and other services within the larger project. The public streets remain
interconnected to the abutting subdivision to the north (Lind Farm) and street
stubs are provided to the south (Poudre School District).
B. Section 3.3.1(C) — Public Sites, Reservations and Dedications
The First Replat continues to dedicate rights -of -way for public streets, drainage
easements and utility easements as needed to serve the area being platted.
4. Findings of Fact:
In evaluating the request for Maple Hill First Replat, Staff makes the following
findings of fact:
E. The First Replat continues to comply with the Mountain Vista Subarea
Plan.
F. The First Replat continues to comply with the Gillespie Farm Amended
Overall Development Plan.
G. The First Replat continues to satisfy the applicable development
standards of the L-M-N zone district.
H. The First Replat continues to satisfy the applicable General Development
Standards of Article Three.
RECOMMENDATION:
Staff recommends approval of Maple Hill First Replat, #29-OOC.
2. Compliance with L-M-N Standards:
A. Density
The P.D.P. is required to contain no less than five dwelling units per net acre and
no more than eight dwelling units per gross acre of residential land. On a net
acreage basis, the average density is 4.64 d.u.'s/acre. On a gross acreage
basis, the average density is 3.85 d.u.'s/acre. The P.D.P. complies with not
exceeding the maximum allowable density of the L-M-N zone, but falls short of
meeting the required minimum.
The P.D.P. is Phase One of the larger Gillespie Farm O.D.P. The future phases
are shown as future tracts on the P.D.P. According to the approved O.D.P.,
these parcels are approved for multi -family (16.90 acres) and a neighborhood
center (1.00 acre). It is expected, therefore, that with development of the future
multi -family parcel, the residential density for the entire Maple Hill project will
meet or exceed the required minimum of 5.00 d.u. on a net acreage basis.
The phasing of density is allowed under Section 2.3.2(H)(8), which states
"Any standards relating to housing density and mix of uses will be applied
over the entire overall development plan, not on each individual project
development plan review."
The First Replat would add two lots. (The Second Replat would add two lots as
well.) Combined, the four additional lots would positively contribute to achieving
the required minimum density within Phase One. At the upper end of the range,
there are no issues related to exceeding the maximum allowable density.
B. Mix of Housing
A minimum of three housing types is required for any project
containing 45 acres or more. A single housing type shall not
constitute more than 90% of the total number of dwelling units.
The two new lots each contain less than 6,000 square feet. (The two new lots for
the Second Replat also contain less than 6,000 square feet.) Combined, the four
additional lots represent 68% of the total. This housing type represents the
largest percentage within the project and remains significantly below the
maximum allowable of 90%.
C. Neighborhood Center, Parks, Streets and Blocks
The addition of the new lots does not impact the project's compliance with
provision of a neighborhood center, proximity to a park, and a network of streets
and blocks.
COMMENTS:
Background:
The surrounding zoning and land uses are as follows:
N: L-M-N; Vacant (Lind Property -Under Development by Centex Homes)
S: L-M-N; Vacant (Poudre School District Future School Site)
E: L-M-N; Vacant (Irrigated Agriculture)
W: R; Existing Single Family Detached in Unincorporated Larimer County
The Maple Hill project is part of a larger 320-acre parcel that was annexed in
1978. Also in 1978, on the Maple Hill parcel, the Nineteenth Green Subdivision
was approved consisting of 58 single family lots on 28.9 acres. Although this
subdivision was approved and recorded, it expired due to lack of activity in the
mid-1980's.
The parcel is located within the Mountain Vista Area Plan adopted by City
Council in March of 1999. The 160-acre Gillespie Farm Overall Development
Plan was approved in February of 2001 and amended in October of 2002.
The original Maple Hill subdivision was approved on September 9, 2003. This
approved project represents the first and largest phase of a residential
subdivision that is located on 136.89 acres at the southeast corner of County
Road 11 (soon to re -named Turnberry Road) and Richards Lake Road.
The approved plan includes 449 single family detached dwelling units and 78
duplex dwelling units for a total of 527 dwelling units. The project sets aside 7.16
acres for a neighborhood park that will be developed by the City of Fort Collins at
some point in the future. An off-street bicycle/pedestrian path will be provided.
Future phases include multi -family on 16.90 acres and a neighborhood center on
1.00 acre. The site is bounded by the Poudre School District property on the
south, the Number Eight Outlet Ditch on the east, and the Lind Farm (Centex
Homes) on the north. County Road 11 (soon to be re -named Turnberry Road)
forms the western boundary. The property is zoned L-M-N, Low Density Mixed -
Use Residential.
ITEM NO. -L
MEETING DATE 3'a+" �y
iiA STAFF_ %`EO cSJfdrP RR ,O
Citv of Fort Collins HEARING OFFICER
STAFF REPORT
PROJECT: Maple Hill, First Replat, #29-OOC
APPLICANT: Mr. Mike Sollenberger and Mr. Tom Dougherty
Gillespie Farm Development Company
3937 Harbor Walk Lane
Fort Collins, CO 80525
OWNER: Nineteenth Green Partnership
6373 South Grape Court
Littleton, CO 80121
PROJECT DESCRIPTION:
This is a request to replat Block 26 of Maple Hill by adding an alley and two lots.
The site is located within the Maple Hill Subdivision. The block is surrounded by
Bar Harbor Drive, Sunbury Lane, Clearfield Way and Summerpark Lane. Maple
Hill is a 137 acre residential neighborhood located at the northeast corner of
Country Club Road (extended) and County Road 11. The parcel is zoned L-M-N.
EXECUTIVE SUMMARY:
A. The First Replat continues to comply with the Mountain Vista Subarea
Plan.
B. The First Replat continues to comply with the Gillespie Farm Amended
Overall Development Plan.
C. The First Replat continues to satisfy the applicable development
standards of the L-M-N zone district.
D. The First Replat continues to satisfy the applicable General Development
Standards of Article Three.
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 (970) 221-6750