HomeMy WebLinkAboutELEVATIONS CREDIT UNION - FDP - FDP160042 - CORRESPONDENCE -Comment Number: 9 Comment Originated: 11/21/2016
11/21/2016: John is okay with the South College Avenue right of way as it is
shown, or as shown on sheet 2. See redlines.
Topic: Site Plan
Comment Number: 10 Comment Originated: 11/21/2016
11/21/2016: There are spelling issues. See redlines.
Comment Number: 11 Comment Originated: 11/21/2016
11/21/2016: There are cut off text issues. See redlines.
Comment Number: 12 Comment Originated: 11/21/2016
11/21/2016: There is text that needs to be rotated 1800. See redlines.
Department: Traffic Operation
Contact: Nicole Hahn, 970-221-6820, nhahn@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 11 /22/2016
11 /22/2016: The drive on the N. side of the site needs a no not enter where the
one way section starts. A one way sign is also needed behind the diagonal
parking on the N. side to direct traffic through the site. - See redlines
Comment Number: 2 Comment Originated: 11/22/2016
11 /22/2016: Truncated domes on Arthur Drive should be installed to direct
pedestrian traffic directly across the drive to the receiving dome instead of
directing traffic into the road. See redlines.
Department: Water -Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamargue@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 11/21/2016
11/21/2016: There is a conflict with the water service and a couple of trees.
Please revise
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 11/16/2016
11/16/2016: Please add the additional notes include in the response letter
concerning the light fixture on the northwest side of the property on the lighting
plan sheet.
11/21/2016: There is text that needs to be masked. Mask all text in hatched
areas. See redlines.
Comment Number: 22 Comment Originated: 11/21/2016
11/21/2016: There is text that needs to be rotated 1800. See redlines.
Comment Number: 23 Comment Originated: 11/21/2016
11/21/2016: There are cutoff text issues. See redlines.
Comment Number: 24 Comment Originated: 11/21/2016
11/21/2016: There are spelling issues. See redlines.
Topic: Landscape Plans
Comment Number: 13 Comment Originated: 11/21/2016
11/21/2016: There are line over text issues. See redlines.
Comment Number: 14 Comment Originated: 11/21/2016
11/21/2016: There are spelling issues. See redlines.
Topic: Lighting Plan
Comment Number: 16 Comment Originated: 11/21/2016
11/21/2016: No comments.
Topic: Plat
Comment Number: 1 Comment Originated:
11/21/2016
11/21/2016: Please provide current acceptable monument records for the
aliquot corners shown. These should be emailed directly to Jeff at
jcounty@fcgov.com
Comment Number: 2 Comment Originated:
11/21/2016
11/21/2016: Please make note of the bridge construction that has caused
benchmark C322's elevation to change, and list the current elevation per the
City's updated data.
Comment Number: 3 Comment Originated:
11/21/2016
11/21/2016: Please show record bearings & distances as marked. See
redlines.
Comment Number: 4 Comment Originated:
11/21/2016
11/21/2016: All easements must be labeled & locatable. See redlines.
Comment Number: 5 Comment Originated: 11/21/2016
11/21/2016: Please address the set monuments as marked. See redlines.
Comment Number: 6 Comment Originated: 11/21/2016
11/21/2016: Property owner information is not necessary and maybe removed
if you choose.
Comment Number: 7 Comment Originated: 11/21/2016
11/21/2016: If you use the south line of Lots 8 & 12 as the Basis Of Bearings,
you don't need to show the section line. If you use the section line, you need to
tie it to the subdivision boundary.
Comment Number: 8 Comment Originated: 11/21/2016
11/21/2016: Please add dedication information for all street rights of way. See
redlines.
Comment Number: 1 Comment Originated: 11/01/2016
11/01/2016: Please correct details included in the returned plan set.
Contact:
Mark Taylor, 970-416-2494, mtavlor@fcgov.com
Topic:
Floodplain
Comment Number: 2 Comment Originated:
11/09/2016
11 /09/2016: In the previous review, on the Plat, I asked that the word
'approximate' be removed from the description of the FEMA 100-year
floodplain boundary. That comment was not addressed.
Contact:
Wes Lamarque, 970-416-2418, wlamargue@fc oc ov.com
Topic:
General
Comment Number: 3 Comment Originated:
11/21/2016
11/21/2016: Please provide 10 feet of separation from storm sewers and all
trees.
Comment Number: 4 Comment Originated:
11/21/2016
11/21/2016: Some text in the drainage report needs to be updated from an
earlier iteration of the drainage design. Some data within the text is missing as
well. See flow rate references which are mostly labeled as 0 cfs.
Comment Number: 5 Comment Originated:
11/21/2016
11/21/2016: Please label the inspection ports on the utility plan.
Comment Number: 6 Comment Originated:
11/22/2016
11/22/2016: Please see other minor redlines in the plan set.
Department: Technical Services
Contact: Jeff County, 970-221-6588, 4county@fcgov.com
Topic: Building Elevations
Comment Number: 15 Comment Originated: 11/21/2016
11/21/2016: There are line over text issues. See redlines.
Topic: Construction Drawings
Comment Number: 17 Comment Originated:
11/21/2016
11/21/2016: Please make note of the bridge construction that has caused
benchmark C322's elevation to change, and list the current elevation per the
City's updated data.
Comment Number: 18 Comment Originated:
11/21/2016
11/21/2016: The Subdivision Plat Basis Of Bearings may change. Please
make sure this matches the Subdivision Plat.
Comment Number: 19 Comment Originated:
11/21/2016
11/21/2016: There are line over text issues. See redlines.
Comment Number: 20 Comment Originated:
11/21/2016
11/21/2016: There are text over text issues. See redlines.
Comment Number: 21 Comment Originated: 11/21/2016
have questions. (970) 221-6700. You may reference Light & Power's Electric
Service Standards at
hftp://www.fcgov.com/utilities/img/site specific/uploads/ElectricServiceStandar
ds_FINAL_17June2016.pdf
You may reference our policies, development charge processes, and use our
fee estimator at
hftp://www.fcgov.com/utilities/business/builders-and-developers.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, llynxwiler@poudre-fire.org
Topic: General
Comment Number: 1
Comment Originated: 11/17/2016
11/17/2016: FIRE CONTAINMENT VS. AUTOMATIC FIRE SPRINKLER
SYSTEM
Local amendment to the International Fire Code (903.2.1.8) Occupancy Group
B, states that an automatic sprinkler system shall be provided for fire areas
containing Group B occupancies when the fire area exceeds 5000 square feet
(or be otherwise fire separated). The current plans indicate the building is
projected to be 5,000 +/-. Should the building exceed 5,000 sq. ft., fire
containment or an automatic fire sprinkler system will be mandatory.
Comment Number: 2
Comment Originated: 11/22/2016
11/22/2016: SCALE ERROR
The Site Plan (Sheet S1) is printed at 1 "=10', however the scale is shown at
1 "=20'.
Department: Planning Services
Contact: Clay Frickey, 970-224-60459 cfrickey@fcqov.com
Topic: General
Comment Number: 2 Comment Originated: 11/22/2016
11/22/2016: The sidewalk shown on Spring Court is scaling out to 5'-6% not 6'
as indicated. Please update all drawings to show a 6' sidewalk along Spring
Court.
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 11/22/2016
11/22/2016: The tree mitigation schedule shows the need for 18 mitigation
trees but only 17 mitigation trees are shown on the landscape plan. Please
upsize at least one of the evergreen trees to meet the mitigation requirement.
Topic: Site Plan
Comment Number: 3 Comment Originated: 11/22/2016
11/22/2016: Please add a note to the site plan about gaining approval for the
alternative compliance to the parking requirement outlined in 3.2.2(K) of the
Land Use Code.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, Ischlam@fcgov.com
Topic: Erosion Control
separate document? If so, please indicate this on the plans.
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-4164290, sblochowiak@fcgov.com
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 11/22/2016
11/22/2016: Landscape plans look good. Refer to Current Planning comments
regarding tree upsizing and mitigation etc.
Main concern: that upsized trees will not be planted rather replaced by hired
contractor with lesser caliper.
Comment Number: 2 Comment Originated: 11/22/2016
11/22/2016: Add note to Landscape Plans and/or Construction documents that
: no substitutions shall be approved for lower caliper mitigation trees.
Something getting to the effect that the upsized trees called for on plans need to
be planted.
Department: Forestry
Contact: Molly Roche, mroche@fcgov.com
Topic: Landscape Plans
Comment Number: 8
11 /23/2016:
Please add the bolded Permit note box on page I
Department: Light And Power
Contact: Coy Althoff, CAlthoff@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 11/23/2016
Comment Originated: 11/18/2016
11/18/2016: Single phase power is serving the existing facility. 3-phase power
is not currently available to this property without significant system modifications
such as boring a 4" underground conduit and pulling new primary cable to the
site.
Comment Number: 2 Comment Originated: 11/18/2016
11/18/2016: Any changes to the existing electric capacity and or location will
initiate electric development and system modification charges. Please
coordinate power requirements with Light & Power Engineering at
970-221-6700.
Comment Number: 3 Comment Originated: 11/18/2016
11/18/2016: Contact Light & Power engineering to coordinate the transformer
and electric meter locations, please show the locations on the utility plans.
Comment Number: 4
Comment Originated: 11/18/2016
11/18/2016: Please provide a one line diagram and a C-1 form to Light and
Power Engineering. The C-1 form can be found at:
http://zeus.fcgov.com/utils-procedures/files/EngWikiMikiPdfs/C/C-1 Form.pdf
Comment Number: 5 Comment Originated: 11/18/2016
11/18/2016: You may contact FCU Light & Power, project engineering if you
Comment Number: 5 Comment Originated: 11/22/2016
11/22/2016: Please show all easements on the Utility Plan correctly. 9' UE
along Spring Court and Arthur Drive as well as 15' UE along College Avenue.
Please see redlines. The drainage easement width varies. The ROW
dedication limits also need to be reflected correctly.
Comment Number: 6 Comment Originated: 11/22/2016
11/22/2016: Concrete will be needed behind the walk on both driveways on
Spring Court and Arthur Drive.
Comment Number: 7
Comment Originated: 11/22/2016
11/22/2016: It appears the window awning structures sit within the utility
easements. Please revise the building to remove these from the easements.
Comment Number: S
Comment Originated: 11/22/2016
11/22/2016: More details are needed for the decretive grates along the
College Avenue sidewalks. How will these grates sit along the sidewalk. The
grate frames and any anchors need to be independent of the sidewalk and can't
be anchored in the sidewalk. How will the drain work? A cutoff wall or
waterproofing is needed.
Comment Number: 9 Comment Originated: 11/22/2016
11/22/2016: Modifications to the rain garden are needed. A 2' grading setback
behind the walk is needed. See LCUASS detail 1602.
Comment Number: 10
Comment Originated: 11/22/2016
11/22/2016: Please verify the sidewalk along Spring Court will all fit within
existing ROW. It appears that the 6' walk won't fit. If more ROW is needed,
please adjust the plat to include these areas.
Comment Number: 11 Comment Originated: 11/22/2016
11/22/2016: Provide existing grades along Spring Court for the street cross
sections sheet.
Comment Number: 12 Comment Originated: 11/22/2016
11/22/2016: Label the Z-cut detail as Private and On -Site Only
Comment Number: 13 Comment Originated: 11/22/2016
11/22/2016: Please update the sidewalk chase with to the modified detail with
flares behind the walk. This detail was also used on the Slab Property project.
Comment Number: 14 Comment Originated: 11/22/2016
11 /22/2016: Modifications to the liner along the rain garden are needed. How
will the 30" Mil Liner be attached? The sidewalk and subgrade within the ROW
can't be used. A cutoff wall will most likely be needed between the rain garden
and the public ROW.
Comment Number: 15
Comment Originated: 11/22/2016
11/22/2016: The Developer should consider a design change to the retaining
wall along Spring Court. As proposed, the footers within the easement would be
an encroachment that will need to be documented in the Development
Agreement. The agreement would acknowledge potential damage to the wall
and complete responsibility would be on the Developer, not the utility provider.
Comment Number: 16
Comment Originated: 11/22/2016
11/22/2016: The Demolition Plan calls for a waterline easement to be vacated
to the north of the property. Show this vacation on the Plat. Will this be done by
Fort Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
kgov. com/developmentreview
November 28, 2016
Cara Scohy
CS DESIGN, INC.
2519 S SHIELDS ST #129
Fort Collins, CO 80526
RE: Elevations Credit Union, FDP160042, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Clay Frickey, at 970-224-6045 or cfrickey@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Marc Ragasa, 970.221.66037 mragasa@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 11/22/2016
11/22/2016: A variance request will be needed for the parking setback on
College Avenue. Setbacks for an arterial roadway with an ADT between
100-750 is 75'
Comment Number: 2 Comment Originated:
11/22/2016: A variance request will be needed for the street cross section of
Arthur Drive and Spring Court. Standards require detached walks with
parkways.
Comment Number: 3 Comment Originated:
11 /22/2016: The limits of sidewalk and asphalt removal at the corner of Spring
Court and Arthur Drive will need to be modified. The new sidewalk in this
location will need to be 6' wide. The cuts will need to be combined. All street
cuts need to be perpendicular to the curb. Add the sidewalk cut to the nearest
joint note to the Utility Plan.
Comment Number: 4
11/22/2016
11/22/2016
Comment Originated: 11/22/2016
11/22/2016: The portion of walk behind the driveway will need to be in an
"Access" Easement, not pedestrian easement.