SPRING CREEK FARMS — Project Phasing
The Spring Creek Farms project in Fort Collins, Colorado will be developed in three (3) phases as follows:
AREA Phase
LMN Phase I ( Single Family)
MMN Phase II A & B ( Multi -Family)
E Phase III (Employment)
NOTES:
1. Future sub phasing to be determined at the time of Preliminary Development
Plan(s) for the entire site.
2. Please reference the attached Spring Creek Farms Phasing Plan for further clarification.