Topic: General
Comment Number: 1 Comment Originated: 03/07/2017
03/07/2017: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Department: Water -Wastewater Engineering
Contact: Dan Mogen, 970-224-6192, dmogen@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 03/14/2017
03/14/2017: Please note that the 8" water main in Mathews exists up to the
valve shown in the plans. 4" main exists north of this valve (8" south). There is
not ability to tap the 8" further north without extending the 8" main.
Comment Number: 2
Comment Originated: 03/14/2017
03/14/2017: The existing sanitary service will need to be located and
abandoned at the main.
Comment Number: 3 Comment Originated:
03/14/2017: The proposed sanitary service location is not currently acceptable.
Please coordinate with Engineering and Water Utilities to determine an
acceptable alignment. Water Utilities will need to have the service either
located within an easement or worked out with Engineering to allow the service
to run along Oak to the existing main.
Comment Number: 4 Comment Originated:
03/14/2017: Please see redlines.
Department: Zoning
Contact: Ryan Boehle, 970416-2401, rboehle@fcgov.com
Topic: General
Comment Number: 1
03/14/2017
03/14/2017
Comment Originated: 03/14/2017
03/14/2017: How will the trash removal be handled. It is unclear where the trash
enclosure will be located, and also define the trash enclosure area on the site
plan.
Comment Number: 2 Comment Originated: 03/14/2017
03/14/2017: Please provide the total number of bicycle parking spaces
provided.
Comment Number: 4 Comment Originated: 03/17/2017
03/17/2017: There are line over text issues. See redlines.
Topic: Construction Drawings
Comment Number: 5 Comment Originated:
03/17/2017: Please revise the sub -title as marked. See redlines.
Comment Number: 6 Comment Originated:
03/17/2017: The City has moved to the NAVD88 vertical datum, and as of
January 1, 2015, all projects are required to be on NAVD88 datum. Please
provide the following information for the Benchmark Statement in the EXACT
format shown below.
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION
ELEVATION:
BENCHMARK # w/ DESCRIPTION
ELEVATION:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL
DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29
UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE,
THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED
= NAVD88 - X.XX'.
03/17/2017
03/17/2017
Topic: Landscape Plans
Comment Number: 2 Comment Originated: 03/17/2017
03/17/2017: Please remove "Conceptual Review" from the title on sheet
LP501. See redlines.
Topic: Site Plan
Comment Number: 1 Comment Originated: 03/17/2017
03/17/2017: Some of the sheet titles in the sheet index do not match the sheet
titles on the noted sheets. See redlines.
Department: Traffic Operation
Contact: Nicole Hahn, 970-221-6820, nhahn@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 03/14/2017
03/14/2017: Please revise driveway depth to better define parking and backing
movements.
Comment Number: 2 Comment Originated: 03/14/2017
03/14/2017: Please provide signing and striping plans including the additional
on street parking with the final submittal.
Department: Water Conservation
table. You should include the parking spaces you are proposing to provide
off -site in addition to the shared vehicle for the site.
Comment Number: 2
Comment Originated: 03/10/2017
03/10/2017: The summary of the building floor area should also include the
floor area requirements of the NCB zone district. As part of this table, please
include the following:
Lot size
Overall building floor area
Overall floor area ratio
Building floor area in the rear half of the lot (from Oak St.)
Maximum floor area allowed in rear half of the lot per NCB standards (33% of
rear half)
Comment Number: 3 Comment Originated: 03/10/2017
03/10/2017: The line work makes it difficult to tell how far back the building is
set from the right-of-way. Please more clearly delineate the sidewalk, property
boundary, and building envelope on the site plan.
Department: Stormwater Engineering
Contact: Dan Mogen, 970-224-6192, dmogen@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 03/14/2017
03/14/2017: Are there any offsite flows that need to be accounted for?
Comment Number: 3 Comment Originated: 03/14/2017
03/14/2017: Please see redlined utility plans and drainage report (provided in
pdf format).
Contact: Jesse Schlam, 970-218-2932, jschlam@fcqov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 03/06/2017
03/06/2017: No Comment from Erosion Control. Based upon the submitted
materials it has been determined that this site; disturbs less than 10,000 sq. ft.,
is not in a sensitive area, and is not in a larger development under construction.
Therefore, no submittal of erosion control material is needed at this time.
However, the site still must be swept and maintained to prevent dirt, saw
cuttings, concrete wash, trash & debris, landscape materials and other
pollutants from entering the storm sewer at all times or erosion and sediment
control measures will be required of the site. If you need; clarification concerning
the erosion control section, or if at any time the site does in fact disturb greater
than 10,000 sq. ft., or if there are any questions, please contact Jesse Schlam
970-218-2932 or email @ jschlam@fcgov.com
Department: Technical Services
Contact: Jeff County, 970-221-65889 icounty@fcgov.com
Topic: Building Elevations
Comment Number: 3 Comment Originated: 03/17/2017
03/17/2017: There is text that needs to be masked. Mask all text in hatched
areas. See redlines.
more logical to have the box located somewhere else on the structure. Knox
Box size and location(s) to be determined by time of final CO.
Comment Number: 5
Comment Originated: 03/11/2017
03/11/2017: PERIMETER ACCESS
Fire access is required to within 150' of all exterior portions of any building as
measured by an approved route around the perimeter. This requirement has
been met provided that perimeter fencing allows for quick access. A plan to
allow fire access through the steel, perimeter fence is required. One option is to
provide gate keys inside the required Knox Box.
Comment Number: 6 Comment Originated: 03/11/2017
03/11/2017: SPV SYSTEMS
Multi -Family products are considered commercial use occupancies.
Commercial rooftop solar arrays require a separate plan review and permit
from the Poudre Fire Authority. Refer to IFC 605.11.1 through 605.11.3 for
Marking, DC Location, Access and Pathway details.
Department: Planning Services
Contact: Clay Frickey, 970-224-6045, cfrickey@fcclov.com
Topic: Building Elevations
Comment Number: 4 Comment Originated: 03/10/2017
03/10/2017: Where are the front doors? The elevations do not show a clearly
defined front entrance. Please provide more detail on this element of the
building.
Comment Number: 5 Comment Originated: 03/10/2017
03/10/2017: In looking at Terreal's terracotta panels, it looks like there are
multiple textures available. Which texture are you proposing to use on the
building?
Comment Number: 6
Comment Originated: 03/10/2017
03/10/2017: On a more general level, the building reads more like a
commercial building than a residential building. Staff is concerned about the
scale of elements of the building and how this makes the building appear
commercial (fenestration, store front appearance along Oak, large sliding doors
on the south side). Staff would like to meet to iron out these details after your
work session with Landmark Preservation Commission. LPC will likely give you
more specific direction on how the building can better fit in with the context of
the neighborhood. Based on this direction, staff would like to work with you on
how to best integrate this feedback into the building design.
Topic: General
Comment Number: 7
Comment Originated: 03/13/2017
03/13/2017: Thank you for your modification requests. I did not see a
modification request to the parking standard. While you did get a parking
modification from P&Z for the previous iteration of your project, you will need to
re -apply for the parking modification now that your building program has
changed.
Topic: Site Plan
Comment Number: 1 Comment Originated: 03/10/2017
03/10/2017: Clarify the amount of parking you will be providing in the parking
Comment Number: 6 Comment Originated: 03/15/2017
03/15/2017: Please contact Tyler Siegmund at Light & Power Engineering if
you have any questions at 970.416.2772. Please reference our policies,
construction practices, development charge processes, and use our fee
estimator at hftp://www.fcgov.com/utilities/business/builders-and-developers
Department: Outside Agencies
Contact: Clay Frickey, 970-224-6045, cfrickey@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 03/16/2017
03/16/2017: Comment from Comcast - Comcast needs a 5' utility easement on
the west side of the building and along the south side of the property. Current
Comcast facility is in the alley.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, ilynxwiler@poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 03/11/2017
03/11/2017: UST STORAGE TANKS
The removal of Underground Storage Tanks (UST) require a separate plan
review and permit from the Poudre Fire Authority. Please contact Assistant Fire
Marshal, Ron Gonzalez at 970-416-2864 with any questions.
Comment Number: 2 Comment Originated: 03/11/2017
03/11/2017: GROUP R SPRINKLER SYSTEMS -LOCAL AMENDMENT
This Multi -Family building may be allowed to install an NFPA 13-R sprinkler
system with approval of the Building Department. Code language provided
below.
> IFC 903.3.1.2: New multi -family buildings shall be provided with NFPA13 (full
protection) fire suppression systems.
Exception 1: M-F units with six (6) or fewer dwelling units per building will be
allowed to install 13-R fire suppression systems provided the units are
separated by one -hour construction (walls & floors).
Comment Number: 3
Comment Originated: 03/11/2017
03/11/2017: FDC
> IFC 912.2: Fire Department Connections shall be installed in accordance with
NFPA standards. Fire department connections shall be located on the street
side of buildings, fully visible and recognizable from the street or nearest point
of fire department vehicle access. The location of the FDC shall be approved by
the fire department.
Comment Number: 4 Comment Originated: 03/11/2017
03/11/2017: KEY BOXES REQUIRED
> IFC 506.1 and Poudre Fire Authority Bureau Policy 88-20: Poudre Fire
Authority requires at least one key box ("Knox Box") to be mounted in an
approved, exterior location (or locations) on every new or existing building
equipped with a required fire sprinkler or fire alarm system. The box shall be
positioned 3 to 7 feet above finished floor and within 10 feet of the front door, or
closest door to the fire alarm panel. Exception can be made by the PFA if it is
ranges in age from the 1880s to the 1930s.
Comment Number: 5
Comment Originated: 03/14/2017
03/14/2017: "(4) Visual and pedestrian connections between the site and
neighborhood focal points, such as a park, school or church, shall be preserved
and enhanced, to the maximum extent feasible."
The general visual and pedestrian connections between the site and the park
and Carnegie Library building are not a current concern for historic preservation
staff.
Department: Light And Power
Contact: Tyler Siegmund, 970-416-2772, tsiecimund@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 03/15/2017
03/15/2017: Light and Power has electric facilities along the south side of Oak
St that can be utilized to provide power to the site. Modifications may be
needed, Light and Power may have to intercept exiting primary lines and cut in
a vault along the Oak St frontage. Is 3phase or single phase power
anticipated?
Comment Number: 2
Comment Originated: 03/15/2017
03/15/2017: Electric capacity fees, development fees, building site charges
and any system modification charges necessary to feed the site will apply to this
development. Please contact me or visit the following website for an estimate
of charges and fees:
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investmen
t-development-fees
Comment Number: 3 Comment Originated: 03/15/2017
03/15/2017: A commercial service information form (C-1 form) and a one line
diagram for the commercial meter will need to be completed and submitted to
Light & Power Engineering. A link to the C-1 form is below:
http://www.fcgov.com/utilities/business/builders-and-developers/development-
forms-guidelines-regulations
Comment Number: 4
Comment Originated: 03/15/2017
03/15/2017: Transformer location will need to be coordinated with Light &
Power. Typically, transformers are placed on the property. Transformer must
be placed within 10 ft of a drivable surface for installation and maintenance
purposes. The transformer must also have a front clearance of 10 ft and
side/rear clearance of 3 ft minimum.
Comment Number: 5
Comment Originated: 03/15/2017
03/15/2017: Electric meter locations will need to be coordinated with Light and
Power Engineering. Please show meter location on the utility plan and site
plan. Each residential unit will need to be individually metered. If you wish to
gang the meters on one side of the building please place on the opposite side
of the gas meters. The owner is responsible to provide and maintain the
electrical service from the transformer to the meter bank.
Street and Olive Street would reflect two corner anchors with zero lotlines that
frame the streetscape of the block with 16-feet setbacks in the middle, creating
a larger siteline pattern that would carry through to the north upon the
construction of the new MAVD building approved at 221 Mountain Avenue. The
height and width of the three-story building is generally consistent with the range
of buildings in the area of adjacency, which consist of one-story, two-story, and
three-story buildings that are from 38 feet to 83 feet wide. The applicant
suggests that the PV panels should be difficult to see from a pedestrian
viewpoint facing the building's facade on Oak Street.
Generally speaking, the height, setback, and width of the proposed new building
seem to avoid negatively impacting the exterior integrity and significance of
individually designated and eligible buildings along Oak Street and Mathews
Street based on scale, in part because those buildings are not immediately
abutting the proposed new construction.
Comment Number: 3 Comment Originated: 03/14/2017
03/14/2017: "(2) New structures shall be designed to be in character with such
existing historic structures. Horizontal elements, such as cornices, windows,
moldings and sign bands, shall be aligned with those of such existing historic
structures to strengthen the visual ties among buildings. Window patterns of
such existing structures (size, height, number) shall be repeated in new
construction, and the pattern of the primary building entrance facing the street
shall be maintained to the maximum extent feasible."
Staff feels that the Old Town commercial building typology is not specifically
called for at this site because it lacks immediate proximity to similar buildings
and also does not reflect a predominant historic pattern in the area of
adjacency. The applicant has chosen the typology based on the logic that the
more immediate surroundings lack a clear pattern of character and typology, i.e.
the proposed historic area of adjacency is a varying mix of types and styles.
Additionally, the building would sit in a transition area between the Downtown
District and the Neighborhood Conservation - Medium Density (NCM) District,
so the applicant has an interesting design challenge regarding this section of
the code.
Comment Number: 4 Comment Originated: 03/14/2017
03/14/2017: "(3) The dominant building material of such existing historic
structures adjacent to or in the immediate vicinity of the proposed structure shall
be used as the primary material for new construction. Variety in materials can
be appropriate, but shall maintain the existing distribution of materials in the
same block."
Staff feels that the dominant building material choice of terracotta panels is a
sensitive modern construction material that would visually harmonize with the
existing, varying pattern of brick and stone masonry in the area of adjacency.
However, the panels will differ from the appearance of the traditional building
materials in the area based on the modular installation, the larger -format size of
the panels, the pattern of installation and the lack of mortar -replaced by
suspension on a frame. The overall effect of building style, material choice, and
construction methodology is thus indirectly referential and one of contrast and
differentiation, representing a modern addition to an area of adjacency that
Topic: Landscape Plans
Comment Number: 1
Comment Originated: 03/17/2017
03/17/2017:
Please provide for two upsized mitigation trees to meet the requirement.
Canopy shade trees: 3"
Ornamental: 2.5"
Evergreen trees: 8' height
Comment Number: 2
Comment Originated: 03/17/2017
03/17/2017:
Show irrigated turf in the parkway on Mathews and Oak Street. Also, clearly
show the location of the sidewalk along Mathews and Oak as well as the
parkway.
Comment Number: 3 Comment Originated: 03/17/2017
03/17/2017:
Forestry suggests the applicant to consider a new cultivar of oak to be planted
where the Fastigiate English Oak are currently proposed. This new oak is the
cultivar `Skinny Genes', which is a White Oak x English Oak hybrid with a very
narrow crown spread.
Is it feasible that this cultivar of oak could also be sited along Oak Street?
Department: Historic Preservation
Contact: Maren Bzdek, 970-221-6206, mbzdek@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 03/14/2017
03/14/2017: Land Use Code (LUC) Section 3.4.7, Historic and Cultural
Resources contains the applicable standards for new buildings, where
designated or eligible historic landmarks or historic districts are part of the
development site or surrounding neighborhood context. At its March 15, 2017
preliminary review of the project, the Landmark Preservation Commission will
discuss the appropriate area of adjacency upon which compliance with this
section of the code will be based.
Comment Number: 2 Comment Originated: 03/14/2017
03/14/2017: LUC 3.4.7(F)(1) requires that "To the maximum extent feasible,
the height, setback and width of new structures shall be similar to: (a) those of
existing historic structures on any block face on which the new structure is
located and on any portion of a block face across a local or collector street from
the block face on which the new structure is located.... Notwithstanding the
foregoing, this requirement shall not apply if, in the judgment of the decision
maker, such historic structures would not be negatively impacted with respect to
their historic exterior integrity and significance by reason of the new structure
being constructed at a dissimilar height, setback and width. Where building
setbacks cannot be maintained, elements such as walls, columns, hedges or
other screens shall be used to define the edge of the site and maintain
alignment. Taller structures or portions of structures shall be located interior to
the site."
The applicants have identified the following areas that address 3.4.7(F)(1). The
proposed setback pattern on the west side of Mathews Street between Oak
Contact: Stephanie Blochowiak, 970-416-4290,
Topic: Landscape Plans
Comment Number: 1
sblochowiak@fcgov.com
Comment Originated: 03/13/2017
03/13/2017: Update the songbird nesting note on landscape plans to: "NO
TREES SHALL BE REMOVED DURING THE SONGBIRD NESTING SEASON
(FEBRUARY 1 TO JULY 31) WITHOUT FIRST HAVING A PROFESSIONAL
ECOLOGIST OR WILDLIFE BIOLOGIST COMPLETE A NESTING SURVEY
TO IDENTIFY ANY ACTIVE NESTS EXISTING ON THE PROJECT SITE. THE
SURVEY SHALL BE SENT TO THE CITY ENVIRONMENTAL PLANNER. IF
ACTIVE NESTS ARE FOUND, THE CITY WILL COORDINATE WITH
RELEVANT STATE AND FEDERAL REPRESENTATIVES TO DETERMINE
WHETHER ADDITIONAL RESTRICTIONS ON TREE REMOVAL AND
CONSTRUCTION APPLY"
Comment Number: 2 Comment Originated: 03/13/2017
03/13/2017: Thank you for adding Water Quality Planter. What will the "Bio-Mix
12 inch Min" consist of? Please provide specs by Final Plan.
Comment Number: 3
Comment Originated: 03/13/2017
03/13/2017: Vine fence is a great idea and nice, unique amenity. Please
change plant choice, however, as English Ivy (Europe native) is invasive in many
States. There are other vine choices better suited for the Front Range climate
and that are native to North America (versus Europe or Asia). For example:
"Kintzley's Ghost honeysuckle" Lonicera reticulate; "Passion flower" Passiflora
incarnata; "Coral honeysuckle" Lonicera sempervirens; "American bittersweet"
Celastrus scandens; "Common hop" Humulus lupulus. Many native pollinators
do not have the enzymes necessary to digest non-native plant parts.
Topic: Lighting Plan
Comment Number: 4 Comment Originated: 03/13/2017
03/13/2017: What will the lighting for the proposed project be like? Especially
for LED light fixtures, cooler color (blue) temperatures are harsher at night and
cause more disruption to circadian (biological) rhythms for both humans and
wildlife. Warmer color temperature (warm white, 3000K or less) for any LED
light fixtures in addition to fixtures with dimming capabilities are preferred. Site
light sources shall be fully shielded and down -directional to minimize up -light,
light spillage and glare [see LUC 3.2.4(D)(3)].
Several departments within the City of Fort Collins have been working together
to address this issue; they are referred to as the City's Night Sky team. Results
of the team's work can currently be viewed on the City's Public Records website
in Resolution 2016-074, a summary of City of Fort Collins City Council Intent
and General Policy Regarding Night Sky Objectives. For further information
regarding health effects please see:
http://darksky.org/ama-report-affirms-h u man-health-impacts-from-leds/
Comment Number: 5 Comment Originated: 03/13/2017
03/13/2017: By final plan please have more details for outdoor lighting fixtures
to be ordered and installed including catalog cut sheets.
Department: Forestry
Contact: Molly Roche, mroche@fcgov.com
Fort of
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov. com/developmentreview
March 22, 2017
722 W MOUNTAIN AVE
Fort Collins, CO 805212506
RE: Living Oaks, PDP170009, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Clay Frickey, at 970-224-6045 or cfrickey@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Marc Ragasa, 970.221.6603, mragasa@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 03/15/2017
03/15/2017: A response to the variance request dated February 17, 2017 to
reduce the width of the driveway was sent on March 6th. Engineering has
denied the request based on the items listed in the letter. Please modify the site
plan to accommodate a larger driveway. Also, as proposed the gate would
need to be set back so that a vehicle has adequate room to idle outside of the
public right of way while the gate is opening.
Comment Number: 2
Comment Originated: 03/15/2017
03/15/2017: The sanitary sewer service and the storm service connecting to
the inlet is not allowed in the public ROW as shown. These services will need to
be in a Utility Easement. Based on the variance request dated 10/19/2016 to
remove the required 9' utility easements behind the ROW, it was indicated that
pocket easements would be provided behind the ROW if necessary. Please
work with Engineering and Water Utilities to determine an alternative design for
this issue. There is a major encroachment option, but there is an application
(and fee) for this revocable permit and it doesn't guarantee approval. All options
must be explored and exhausted before an major encroachment is considered.
Department: Environmental Planning