HomeMy WebLinkAboutKMART PLAZA - PDP/FDP - 38-97 - SUBMITTAL DOCUMENTS - ROUND 1 - CORRESPONDENCE-CONCEPTUAL REVIEW24. Staff encourages the incorporation of outdoor use areas for customers and pedestrians by
providing plazas, patios, other amenities.
25. Staff recommends that there be elements of architectural unity among the three new
buildings. The existing building forms are non-descript and lack distinctive features.
Please be aware that national, corporate, formula, prototypical architecture will be
discouraged. With this proposal, there is an excellent opportunity to enhance the overall
appearance of not only the center but the streetscape as well. Staff looks forward to
working with the applicant and design team to accomplish our mutual objectives.
buildings. Each building will pay its own fee at the time of building permit issuance. For
an estimate of the fee, please contact Matt Baker, Engineering Department, 221-6605.
16. On the westerly building along Lemay, the west parking lot will need a back -out space or
another outlet for circulation. Otherwise, a customer entering the lot, and finding the lot
full, will have to back out all the way to the access drive.
17. On the same parking lot, the parking spaces are not 100 feet back from Drake. There
should be no disruption of traffic flow on Drake, or at the DrakeJaccess drive intersection,
due to the proximity of these spaces to Drake.
18. The site is located in the Spring Creek Drainage Basin. The storm drainage fee in this
basin is $2,175 per acre of new development. The Storm Drainage Utility will have to
research what amount of fees ha-!e been paid to date for the K-Mart Plaza.
19. At the time of submittal, a Drainage Report, Grading and Drainage Plan, and Erosion
Control Plan must be included. These documents must meet the requirements of the
Utility. It is recommended that the consulting engineer have a pre -submittal meeting if
there are any questions regarding the scope and content of the submittal documents.
20. Since the new buildings are replacing hard surface, the primary concern is the
characteristics of the new drainage patterns. All storm flows must be routed to the
appropriate outlets. There are storm sewers onsite and one on College Avenue. These
sewers have not been analyzed and may be undersized. If used, then the system must be
analyzed for capacity and introduction of additional storm flows.
Storm flows must not be routed west to the pond by the C.S.U. Vet Hospital as
this pond is over capacity. The direction of the new storm flows and the volumes
must be documented. Please investigate opportunities to address water quality,
such as disconnection from the impervious surface, and by providing best
management practice. For further information, please contact Glen Schlueter,
221-6589.
21. A11 new trash enc'.osures must be constructed oast of b,iildir_g materials that match principal
building. Enclosures should be placed on concrete and feature a swinging gate.
Enclosures should be sized so that there is ample room for recycling containers.
22. During construction, measures should be taken to reduce the problems associated with
fugitive dust. Larimer County Health Department is the agency that enforces air quality
regulations for new construction.
23. Staff applauds the placement of the buildings adjacent to the public streets and placing
parking to the sides and rears of the buildings. This will enhance the streetscapes of both
arterials. Pedestrian connections to the public walks will be important. Placing building
entrances so that they face the arterials is encouraged.
sodium to match public street lighting and for energy conservation attributes. For further
information regarding handicap accessibility, the U.B.C. and energy conservation, please
contact Sharon Getz, Plans Examiner, 221-6760.
13. The Poudre Fire Authority will require that any uncontained interior floor space that
exceeds 5,000 square feet will need to be equipped with an automatic fire extinguishing
system or separated by one -hour rated fire walls. For further information, please contact
Roger Frasco, Assistant Fire Marshal, 221-6570.
14. The Transportation Department has three comments based on vehicles, transit, and
bikes/peds:
A. Vehicles
A traffic impact analysis was done for the City's capital improvement project. This
study should be updated to reflect the new buildings and their anticipated trip
generation and the level of service at the impacted intersections. Also, the internal
private road network that connects K-Mart Plaza to University Mall (King
Soopers and McDonald's) should be analyzed.
Please be aware that after March 28, 1997 (anticipated adoption of the New Land Use Code) the
typical traffic impact study must be upgraded and include more information for all modes of
transit. This new upgraded analysis will be referred to as a Transportation Impact Study. For
further information regarding the scope of the updated traffic study and the new Transportation
Impact Study, please contact Fred Jones, 221-6820.
B. Transit
The site plan should indicate the location of the transit stops on College and
Drake. Sidewalk connections to these transit stops are encouraged. The transit
stop on Drake is west of the access drive and will need a concrete pad.
Landscaping should be coordinated to avoid conflicts. For further information
regarding transit issues, please contact Gaylene Rossiter, 221-6620.
C. Bikes and Pedestrians
Bike racks should be permanently mounted on concrete and located near building
entries in well -illuminated areas. Sidewalks should connect building entries to the
public sidewalks. Please investigate providing an internal sidewalk that connects
K-Mart to the public walks on College and Drake. Sidewalks should be well -
illuminated with parking lot light fixtures or with decorative bollard -lighting at a
pedestrian scale.
15. For retail uses, the Street Oversizing Fee is $19,443 per acre of newly developed land
area. This will include the building envelope and the parking assigned to the new
5. All buildings will be served by the City of Fort Collins Water and Wastewater Utility. An
eight inch diameter water main on the west side of K-Mart is available as is a six inch
diameter water main that runs north -south in the K-Mart parking lot. There is also a 12
inch diameter water main in Drake.
6 Sanitary sewer is available in a main that runs from the southwest corner of the K-Mart
building and runs under the westerly building on Drake. This main can be relocated
subject to proper grades. There is also a sanitary sewer main west of Denny's restaurant.
If there is a restaurant proposed as a tenant in any of the three new buildings, then a
grease interceptor will be required. For further information, please contact Roger
Buffington, 21-6681.
7. The existing zoning is H-B, Highway Business. The anticipated new zoning is C,
Commercial. Both zones allow retail. Under the new zoning, the request would be
processed as Project Development Plan subject to an Administrative Review. The P.D.P.
is followed by a Final Plan. The Director may allow both plans to be consolidated if
appropriate. The replat will follow along with the P.D.P. and Final Plan and be reviewed
in accordance with the same process.
8. Drive-thru's are discouraged. If a drive-thru component is included, then the P.D.P. and
Final Plans must be considered by the Planning and Zoning Board.
9. The balance of the K-Mart Plaza would need to be amended to account for the loss of
parking, the change (if any) to parking lot access and circulation, and the relocated recycle
trailer. This amendment would be processed as an Administrative Change similar to what
was done to verify the new curb cut locations and landscape changes as a result of the
City's capital project along Drake and College. The fee for an Administrative Change is
$168. Please be aware that under the new Land Use Code, this process will be referred to
as a "Minor Amendment."
10. If new lot lines are created, then we will need a Replat to accompany the Project
Development Plan. The Replat must dedicate any new utility easements required to serve
the new buildings and vacate old easements that are no longer needed. New buildings
must not encroach onto existing or newly platted easements. The architect should
coordinate with the land surveyor so that the newly created lots do not place the K-Mart
building out of compliance with the setback requirements of the Uniform Building Code.
This setback for unlimited -sized buildings is 60 feet.
11. There must be a handicap accessible sidewalk connecting the public sidewalk to the entry
and required exits of the new buildings. This sidewalk must meet slope requirements of
the A.D.A.
12. The City has adopted a new Model Energy Code (1996). In particular, there are new
requirements for exterior building -mounted security lights and indoor lighting. Outdoor
parking lot lighting is not subject to the energy code but is encouraged to be high pressure
iAIr _ft
CONCEPTUAL REVIEW STAFF COMMENTS
City of Fort Collins
MEETING DATE: February 24, 1997
ITEM: K-Mart Plaza New Retail Buildings and Replat
APPLICANT: Evans White, Southwest Productions c/o Tom Oldenburg,
Galloway, Romero, and Associates, 5350 DTC Parkway,
Englewood, CO. 80111.
LAND USE DATA: Request to add three separate retail buildings in the parking lot of
K-Mart Plaza. One building would be along College Avenue and
two would be along Drake Road. Total new retail area would be
19,400 square feet. Existing number of parking spaces in the
shopping center would be reduced from 702 to 593.
COMMENTS:
The site will be served by City of Fort Collins Light and Power Utility. For the two
buildings on Drake, electricity can be supplied from an existing oval vault west of the
Texaco/Jiffy Lube. These two buildings could be supplied from one new transformer. A
bore would be needed so the new access drive is not cut. For the building on College,
power would come from an existing transformer located at the northwest corner of the
existing building containing World Savings. Power would have to bore under the new
access drive to avoid cutting. All modifications to the existing system, including
directional boring, are costs that would be borne by the developer. Boring is expected to
be about $18 to $20 per foot.
2. The electrical contractor should contact Light and Power to complete the Commercial
One ("C-1 ") form to determine entrance capacity.
3. The location of the electrical transformer(s) must be closely coordinated with landscape
architect and site planner. The transformers must not be located between the buildings
and the public streets. They must be within ten feet of hard surface on one side for
emergency change -out by a boom truck. They may be screened with solid material subject
to clearance specifications, or by landscaping. For further information regarding electrical
power, please contact Bruce Vogel, 221-6700.
4. Normal electrical charges will apply. Light and Power Staff, however, will have to
research what fees have already been paid by the original development of K-Mart Plaza.
Fees are based on linear front footage along public streets and the amount of land area
devoted to new development.
COMMUNM PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O.Box580 Fort Collins,C080522-0580 (970)221-6750
PLANNING DEPARTMENT
Community Planning and Environmental Services
Current Planning
City of Fort Collins
Mr. Tom Oldenburg
Galloway, Romero, and Associates
5350 DTC Parkway
Englewood, CO 80111
Dear Tom:
February 25, 1997
For your information, attached is a copy of the Staffs comments concerning the
Request to add three separate retail buildings in the parking lot of K-Mart Plaza
presented before the Conceptual Review Team on February 24, 1997.
The comments are offered informally by Staff to assist you in preparing the detailed
components of the project application. Modifications and additions to these comments
may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in the
review process, please feel free to call me at 221-6750.
Sincerely,
1..
Ted Shepard
City Planner
TS/vrm
cc: Eric Bracke, Streets Department
Stormwater Department
Project Planner
File
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6750
FAX (970) 221-6378 • TDD (970) 224-6002
20. OK
21. OK
22. OK
23. STOREFRONTS IN DIVIDED TENANT SPACE BUILDINGS THAT FACE
THE STREET ARE EXTREMLY HARD TO LEASE AND RENTAL RATES
ARE VERY LOW WHEN YOU ARE NOT ALLOWED TO PARK ON THE
STREET THAT YOU ARE FACING. WE ARE PROPOSING
ARCHITECTURAL SOLUTIONS TO THE PROBLEM OF PLACING THE
BACK OF THE BUILDINGS CLOSE TO THE STREET. PLEASE REFER TO
THE ARCHITECTURAL ELEVATIONS.
24. OK
25. UNITY IS PROPOSED BETWEEN THE PROPOSED BUILDING AND THE
EXISTING ADJACENT BUILDING.
Thomas Oldenburg
Architect / Planner
Southwestern Production Corp.
December 19, 1997
Mr. Ted Shepard
City Planner
Community Planning and Environmental Services
City of Fort Collins
Dear Ted,
Please find our response to your concept review letter for the proposed
addition of 6500 S.F. of retail building and site remodeling at the Kmart Plaza. Kmart
plaza is located on the Northwest comer of College and Drake.
RESPONSE TO CONCEPT REVIEW LETTER
1. OK
2. OK
3. OK
4. OK
5. OK
6. OK
7. OK
8. OK
9. OK
10. NO NEW LOT LINES
11. OK
12. OK
13. OK
14. A. WAIVER LETTER
B. OK
C. BIKE RACKS WILL BE PROVIDED
15. OK
16. NO LONGER APPLICABLE
17. NO LONGER APPLICABLE
18. OK
19. OK