3. Other Variance Requests
a. Reduction of slope of Willox
• This variance request is still under consideration.
b. Crest in Mason
• This variance has been approved by the Engineering Department.
4. Street Lighting along Mason.
• Resolved prior to meeting.
5. Changing duplex unit lots to 3-unit multi -family.
Current Planning
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov. com/currentplanning
• Increased density is acceptable to Current Planning in the Service Commercial Zone District, which
does not have any density limitations.
• Tri-plex units must have fire sprinklers. This alleviates PFA's concerns regarding road width.
• Additional parking will need to be accounted for with the increased density. A Modification of Standard
is needed to meet parking stall width requirements.
6. Designing storm sewer to act as equalization pipe for ponds.
• This will be discussed off-line with Stormwater.
7. GWET Easement
• GWET needs to be routed the Utility Plans and Subdivision Plat prior to hearing, there will need to be a
signature block added for GWET to both plans at final compliance.
arof
t`Coll
Union Place Utility Coordination Meeting Notes
June 3, 2009
2:30pm
Attendees -
Current Planning
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov. com/currentplanning
Emma McArdle
Planner — City
Ext 6206
Christina Vincent
URA — City
Ext 2294
Len Hilderbrand
XCEL
225-7848
Don Kapperman
Comcast
567-0245
Bill Johnson
Qwest
377-6401
Roger Buffington
Water/Wastewater — City
Ext 6854
Steve Olt
Current Planning — City
Ext 6341
Sheri Lan enbur er
Engineering — City
Ext 6573
Michele While
Nolte Associates
419-1338
Rob Ross
Merten Inc — Applicant
720-304-0011
Donna Merten
Merten Inc —Applicant
720-304-0011
Justin Fields
Light & Power — City
Ext 6150
Wes Lamar ue
Stormwater — City
Ext 2418
Andrew Carney
Engineering - City
Ext 6501
Discussion Items:
15' Utility Easement along Willox Ln. — What, if any, can be vacated?
• Xcel will accept no less than an 8' utility easement outside of the ROW.
• Comcast needs pocket easements to fulfill their needs.
• Qwest has existing service buried in ROW, future needs can be met with pocket easements.
• City Utilities will be accommodated within the ROW, no additional Utility Easement is necessary.
• City Engineering is willing to consider reducing the ROW dedication required to help alleviate the utility
easement requirements and site constraints. The applicant will need to ask for a variance decreasing
the ROW dedication from 42' to 36' from center line of Willox Lane and reduce the utility easement
outside the ROW to 8'. This variance will move the ROW line from the back of the sidewalk to the front
of the sidewalk.
• Back up plan: Acquire an easement on the north side of Willox for 15-20' in order to vacate the south
end. This requires letters of intent from all property owners on the north side of Willox.
2. What kind of landscaping can be done over the Utility Easement and in the Willox ROW?
The applicant has proposed the use of pervious pavers within the City's ROW, which requires a
variance from Engineering. Engineering has been in contact with the applicant regarding the
requirements they needs to consider the use of permeable pavers as opposed to grass or pavement.