HomeMy WebLinkAboutVILLAGE COOPERATIVE FORT COLLINS - PDP - PDP160036 - CORRESPONDENCE - (4)Contact: Eric Olson, 970-221-6704, eolson(aUcgov.com Topic: General Comment Number: 1 Comment Originated: 11/11/2016 11/11/2016: Irrigation plans are required no later than at the time of building permit. The irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of the Land Use Code. Direct questions concerning irrigation requirements to Eric Olson, at 221-6704 or eolson@fcgov.com Department: Water -Wastewater Engineering Contact: Shane Boyle, 970-221-6339, sboyle(@fcqov.com Topic: Construction Drawings Comment Number: 1 Comment Originated: 11/15/2016 11/15/2016: Please check the remaining cover over the existing sanitary sewer main at Pond B and indicate on the Utility Plans. Comment Number: 2 Comment Originated: 11/15/2016 11/15/2016: Please see minor comments in redlines. Department: Zoning Contact: Marcus Glasgow, 970-416.2338, mglasgowRfcgov.com Topic: General Comment Number: 1 Comment Originated: 11/09/2016 11/09/2016: What is the height of the building? Buildings over 40 ft in height will need to submit a shadow analysis. Comment Number: 2 Comment Originated: 11/09/2016 11/09/2016: How will the grills for the PTAC units be screened? Comment Number: 3 Comment Originated: 11/09/2016 11/09/2016: Need to include shrub details on final landscape plan. Comment Number: 4 Comment Originated: 11/09/2016 11/09/2016: The number of Parking Spaces provided does not meet the minimum requirements. A modification will be required to approve proposed parking. Comment Number: 2 Comment Originated: 11/16/2016 11/16/2016: Please make changes to the Owners & Lienholders signature blocks as marked. See redlines. Comment Number: 3 Comment Originated: 11/16/2016 11/16/2016: Please make changes to the vicinity map as marked. See redlines. Comment Number: 4 Comment Originated: 11/16/2016 11/16/2016: Please make changes to the Basis Of Bearings statement as marked. See redlines. Comment Number: 5 Comment Originated: 11/16/2016 11 /16/2016: Please make changes on sheet 2 as marked. If changes are not made or you disagree with comments, please provide written response of why corrections were not made. Please provide any responses on redlined sheets and/or in response letter. Topic: Site Plan Comment Number: 6 Comment Originated: 11/16/2016 11 /16/2016: Some of the easement descriptions shown are incorrect. If they are going to stay on the plan, they should match what is shown on the Subdivision Plat. Comment Number: 7 Comment Originated: 11/16/2016 11/16/2016: Please revise the legal description to match the corrected legal description on the Subdivision Plat. Department: Traffic Operation Contact: Nicole Hahn, 970-221.6820, nhahn(a)fcgov.com Topic: General Comment Number: 2 Comment Originated: 11/14/2016 11/14/2016: The comment in the previous round of revisions asked for a sidewalk connection on the east side of Stanford north of the project. The comment response indicated that this connection will be made, however it was not shown on the site plan. We are making mention of the connection to make sure its still in the plan. Comment Number: 3 Comment Originated: 11/14/2016: The submitted traffic study explored the traffic generated by this development. The information has been reviewed and the following conclusions have been accepted. The development will require a right turn lane from WB Horsetooth to NB Stanford. A singular vehicular access off of Stanford is appropriate. Topic: Traffic Impact Study Comment Number: 1 11/14/2016 Comment Originated: 11/14/2016 11/14/2016: Traffic operations is supportive of the design alternative that includes mainline Horsetooth travel lanes, bike lanes, and right turn lane. Department: Water Conservation and lack of naturalistic shaping of these areas. Department: Technical Services Contact: Jeff County, 970-221.6588, icounty(a)fc4ov.com Topic: Building Elevations Comment Number: 9 Comment Originated: 11/16/2016 11/16/2016: There is text that needs to be masked. Mask all text in hatched areas. See redlines. Topic: Construction Drawings Comment Number: 11 Comment Originated: 11/16/2016 11/16/2016: Please revise the sub -title to match the corrected sub -title on the Subdivision Plat. Comment Number: 12 Comment Originated: 11/16/2016 11/16/2016: The benchmark shown does not match our records. Comment Number: 13 Comment Originated: 11/16/2016 11/16/2016: Please revise the Basis Of Bearings to match the revised Basis Of Bearings on the Subdivision Plat. Comment Number: 14 Comment Originated: 11/16/2016 11/16/2016: Some of the sheet titles in the sheet index do not match the sheet titles on the noted sheets. See redlines. Comment Number: 15 Comment Originated: 11/16/2016 11/16/2016: All benchmark statements must match on all sheets. Comment Number: 16 Comment Originated: 11/16/2016 11/16/2016: All Basis Of Bearings statements must match on all sheets. Comment Number: 17 Comment Originated: 11/16/2016 11116/2016: Some of the easement descriptions shown are incorrect. If they are going to stay on the plan, they should match what is shown on the Subdivision Plat. Comment Number: 18 Comment Originated: 11/16/2016 11 /16/2016: There is text that needs to be masked. Mask all text in hatched areas. See redlines. Comment Number: 19 Comment Originated: 11/16/2016 11/16/2016: There are line over text issues. See redlines. Topic: Landscape Plans Comment Number: 8 Comment Originated: 11/16/2016 11/16/2016: There are line over text issues. See redlines. Topic: Lighting Plan Comment Number: 10 11/16/2016: No comments. Topic: Plat Comment Originated: 11/16/2016 Comment Number: 1 Comment Originated: 11/16/2016 11/16/2016: Please make changes to the sub -title as marked. See redlines. please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com Contact: Shane Boyle, 970-221-6339, sboyle(cDfcgov.com Topic: Construction Drawings Comment Number: 2 Comment Originated: 11/15/2016 11/15/2016: 10' minimum separation is required between the outlet structure of Pond B and the existing sanitary sewer. Comment Number: 3 Comment Originated: 11/15/2016 11/15/2016: There are several areas shown in the plans that don't appear to be constructible as shown. These include areas of both detention ponds and the proposed inlet on Horsetooth near Stanford. Please review the redlines and revise design as appropriate. Comment Number: 4 Comment Originated: 11/15/2016 11/15/2016: Please see redlines for additional minor comments. Topic: Drainage Report Comment Number: 5 Comment Originated: 11/15/2016 11/15/2016. More detail will be needed on how the combination water quality in the chambers/Pond A works together. Comment Number: 6 Comment Originated: 11/15/2016 11/15/2016: The report references zero freeboard in Pond B. At a minimum, 1' of freeboard is required to the finished grade of the building. Please address this in the report and/or revise the design if necessary. Comment Number: 7 Comment Originated: 11/15/2016 11/15/2016: Since the streets are existing, the site is required to capture and treat/detain all portions of the street where it is feasible. In this case, it appears the development plan is doing so. Therefore, the drainage calculations can be completed without incorporating the portions of the street that are not able to be captured by the site drainage design. Doing so should result in the ability to increase the release rate from the detention ponds. Comment Number: 8 Comment Originated: 11/15/2016 11/15/2016: The report and plan shows Basin C1 being captured and conveyed to the sanitary sewer. Stormwater is not allowed to be discharged into the sanitary sewer. A system that captures this runoff and conveys it to an appropriate stormwater outfall will be required. Topic: Landscape Plans Comment Number: 9 Comment Originated: 11/15/2016 11/15/2016: Landscaping is shown on top of and in close proximity to the proposed storm sewer at the northwest corner of the site. Even though this pipe is private, a minimum landscape separation of 6' is required. Comment Number: 10 Comment Originated: 11/15/2016 11/15/2016: As shown, the Landscape Plan does not meet the Detention Pond Landscape Guidelines. Technically, neither does the grading, but it is recognized that there is a significant grade issue on this site that makes grading difficult. In light of that, additional and robust landscaping (i.e. screening) will be needed around the detention ponds to mitigate the slopes turning its back onto Horsetooth. Topic: Landscape Plans Comment Number: 8 Comment Originated: 11/15/2016 11/15/2016: Sheets LS3 and LS4 contain no information but have charts for shrubs. I assume this means further detail about the landscape plan will be supplied for the second round of review. Topic: Site Plan Comment Number: 1 Comment Originated: 11/14/2016 11/14/2016: The scale indicated on the site plan is incorrect. The plan is scaled at 1" = 30'. Please upate the scale to reflect this. Comment Number: 2 Comment Originated: 11/14/2016 11114/2016: How far is the surface parking lot setback from the property to the north? The label for that dimension does not appear on the site plan. Please update this label so staff can ensure compliance with the 5' minimum setback from a property line. Comment Number: 3 Comment Originated: 11/14/2016 11/14/2016: 88 parking spaces is required for this development. The proposed site plan only shows 75 parking spaces, which is 13 spaces short. Staff did not find a modification request as part of this round of review. Please submit a modification request as part of your next round of review. Comment Number: 4 Comment Originated: 11/14/2016 11/14/2016: The site is also 56 bicycle parking spaces short of meeting the minimum bicycle parking requirement. Please also submit a modification request to this standard. Comment Number: 5 Comment Originated: 11/15/2016 11/15/2016: The two tandem spaces in the NW corner of the parking structure cannot be counted towards your minimum parking requirement. This results in a total of 73 parking spaces. Comment Number: 6 Comment Originated: 11/15/2016 11/15/2016: Please label the location of the trash and recycling enclosures on the site plan. Comment Number: 7 Comment Originated: 11/15/2016 11/15/2016: How wide is the drive aisle for the structured parking? Please show this dimension and label it clearly. Department: Stormwater Engineering Contact: Jesse Schlam, 970-218-2932, ischlama()fcgov.com Topic: Erosion Control Comment Number: 1 Comment Originated: 11/01/2016 11/01/2016: The site disturbs more than 10,000 sq. ft., therefore Erosion and Sediment Control Materials need to be submitted for FDP. The erosion control requirements are in the Stormwater Design Criteria under the Amendments of Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials Submitted do not meet requirements. Please submit; an Erosion Control Plan, an Erosion Control Report, and an Escrow / Security Calculation. If you need clarification concerning the erosion control section, or if there are any questions EMERGENCY ACCESS ONLY" rather than "Fire Lane Only." Comment Number: 2 Comment Originated: 11/15/2016 11/15/2016: ALTERNATIVE MEANS AND MEASURES The fire marshal has accepted the proposed measures for meeting the intent of the fire code via alternative means as per email from Chris Goring dated 09/01/2016. The email needs to be submitted in letter form, via email to the fire marshal. His contact information is as follows: Bob Poncelow Poudre Fire Authority Division Chief Community Safety and Service Office 970-416-2871 bponcelow@poudre-fire.org Comment Number: 3 Comment Originated. 11/15/2016 11/15/2016: LABELING The 1:20 scale printed on the Site Plan is incorrect. It appears to be a 1:30 scale. Department: Planning Services Contact: Clay Frickey, 970-224-6045, cfrickey(a)fcgov.com Topic: Building Elevations Comment Number: 9 Comment Originated: 11/15/2016 11/15/2016: Please provide material samples of the brick veneer and the stone veneer. Comment Number: 10 Comment Originated 11/15/2016: Please indicate the height of the building in different locations of the building. Some of the sections of the building will be over 50' in height when taking into account the grade change and the height of the roof. Comment Number: 11 Comment Originated 11/15/2016: Perspective #4 is not labeled on sheet A7.2. Please add this label. Comment Number: 12 Comment Originated: 11/15/2016: Generally speaking, the architecture presented is appropriate for the area and properly articulated. Consider carrying the brick through the entire first floor elevation along Horsetooth Rd. This elevation will have the most visibility by the public and should have the highest quality materials and architectural treatment. Comment Number: 13 Comment Originated: 11/15/2016: Since the building is over 40' in height, you must submit a shadow analysis. Staff will need to see diagrams of the shadow the building casts on adjacent properties at the summer and winter solstices in addition to the spring and fall equinox. 11/15/2016 11/15/2016 11/15/2016 11/15/2016 Comment Number: 14 Comment Originated: 11/15/2016 11/15/2016: Please provide color, perspective renderings of the building. This will help staff to evaluate the articulation of the building in conjunction with the quality of the porch facing Horsetooth. Staff wants to ensure the building is not 11/16/2016: Please contact Luke Unruh at Utility - Light & Power Engineering if you have any questions at 970.416-2724. Please reference our free fee estimator at http://www.fcgov.com/utilities/business/builders-and-developers Comment Number: 4 Comment Originated: 11/16/2016 11/16/2016: Are single or three phase electric facilities anticipated for the site? Please note L&P single phase transformers are limited to 7 parallel runs of no larger than 350kcmil cables. Three phase transformers are limited to no more than 12 parallel runs of no larger than 500kcmil cables. Comment Number: 5 Comment Originated: 11/16/2016 11/16/2016: Contact Light and Power Engineering if help is needed to coordinate a transformer location, please show the locations on the utility plans. Transformer must be within 10' of an asphalt/concrete surface. Pay close attention to the transformer clearances in the Electric Service Standards, Comment Number: 6 Comment Originated: 11/16/2016 11/16/2016: You may reference Light & Power's Electric Service Standards at http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar ds_FINAL_17June2016.pdf Comment Number: 7 Comment Originated: 11/16/2016 11/16/2016: Electric Capacity Fee, Building Site charges, and any necessary system modification charges will apply at owners expense. Department: Outside Agencies Contact: Clay Frickey, 970-224-6045, cfrickey(afcgov.com Topic: General Comment Number: 1 Comment Originated: 11/15/2016 11/15/2016: Comment from Comcast: "Comcast Cable has no issue with the plat map. Comcast will need a right of entry agreement to service this development. Comcast will need to coordinate with the developer on how to have the units pre -wired with conduit from the demark point to a media panel in the unit. Comcast will be planning on building this with a fiber to the unit design and will work with the developer on demarcation points. Please call Don Kapperman with questions." Department: PFA Contact: Jim Lynxwiler, 970-416-2869, ilynxwiler(a)poudre-fire.orq Topic: General Comment Number: 1 Comment Originated: 11/15/2016 11/15/2016: FIRE LANE SIGNAGE > Horizontal Control Plan: Please add one No Parking - Fire Lane sign to the south side of the island immediately across from the main entryway. Add another sign to the west of this island, on the other side of the main entry drive aisle. > EAE signage on the southeast connection to Horsetooth Road should read, Environmental Planning and Planning Services appreciates cooperation in helping design and build a healthy community from a public health and environmental health perspective. Thank you. Department: Forestry Contact: Molly Roche, mroche(ofcgov.com Topic: Landscape Plans Comment Number: 1 Comment Originated: 11/17/2016 11/17/2016: Royal Red Maple and Red Oak are not on the City of Fort Collins Street Tree List. Northern Red Oak does not reliably survive or thrive in Fort Collins soils. Please incorporate tree species that are approved on the Street Tree List. Also, on private property, replacing the Northern Red Oaks with a more adaptable species is recommended. Comment Number: 2 Comment Originated: 11/17/2016 11/17/2016: It appears that there are three trees that are too close to gas lines —from the entry off of Horsetooth Rd, 2 to the east and 1 to the west. Street trees need to be 4 feet from gas lines — please explore locating those trees in back of the walk. For further guidance, visit the utility separation specifications in the Land Use Code. Comment Number: 3 Comment Originated: 11/17/2016 11/17/2016: Please show locations of street lights and adjust tree spacing according to street tree separation requirements if necessary. Comment Number: 4 Comment Originated: 11/17/2016 11/17/2016: If there are any existing trees on the site, please contact the City Forester for proper tree inventory and mitigation information. Comment Number: 5 Comment Originated: 11/17/2016 11/17/2016: Will there be trees located at the east end of the project in the water retention area? Department: Light And Power Contact: Luke Unruh, 9704162724, lunruhanfcgov.com Topic: General Comment Number: 1 Comment Originated: 11/16/2016 11/16/2016: Light and Power has three phase facilities readily accessible on the southwest comer of the proposed development. Comment Number: 2 Comment Originated: 11/16/2016 11/16/2016: Streetlights will be placed along public streets. A 40 feet separation on both sides of the light is required between canopy trees and streetlights. A 15 feet separation on both sides of the light is required between ornamental trees and streetlights. Comment Number: 3 Comment Originated: 11/16/2016 11/16/2016: We'll need a formal variance request to the 3 foot of cover from finished grade for the storm utility crossings and the widening for the bikelane/turn lane. Comment Number: 6 Comment Originated: 11/16/2016 11/16/2016: Based on Traffic Operations acceptance of the TIS, and its trip generation, I'm comfortable with the premise that the new driveway onto Stanford Road is not a high volume driveway and its access spacing along Stanford Road is acceptable. Comment Number: 7 Comment Originated: 11/16/2016 11/16/2016: The emergency access off of Horsetooth requires the specifying of a driveover curb for the access drive. Plastic delineator/bollards would need to be specified behind the right-of-way with further onsite design of the emergency access to meet PFA requirements. Comment Number: 8 Comment Originated: 11/16/2016 11/16/2016: Please have the City's full plat language for the certificate of dedication, maintenance and repair guarantee, etc. Department: Environmental Planning Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak(a)fcQov.com Topic: Landscape Plans Comment Number: 1 Comment Originated: 11/16/2016 11/16/2016: Proposed shade tree species include approximately 36% Quercus spp. including bur oak and red oak varieties. Please re -allocate and diversify by lowering amount of oak species and increasing other species perhaps: Hackberry (C. occidentalis) or Catalpa (C. speciosa) in accordance with species diversity standards outlines in LUC 3.2.1(D). Long-term the City of Fort Collins has a desire not to rely too heavily on specific species for urban tree canopy cover in case of drastic reductions in the future due to disease or pest species, for example the reductions anticipated in the next 3-5 years due to emerald ash tree borer (approximately 25% of City urban tree canopy is composed of green ash trees). Comment Number: 2 Comment Originated: 11/16/2016 11/16/2016: Thank you for including the note and specifics on the native seed mix that includes grasses and forbs (wildflowers). Additional installation and maintenance standard notes need to be added to Landscape Notes. City Staff can provide those. In addition, please note that City of Fort Collins Natural Areas Department has notified seed companies to begin creating these specific requested mixes for 2017, thus, there should be no difficulty in availability or need for substitutions in lieu of mixes included on approved plans. Thank you. Topic: Lighting Plan Comment Number: 3 Comment Originated: 11/16/2016 11/16/2016: 3000K or less LED fixtures are called out on plans. Please ensure these notes make it to approved plans and/or construction drawings and that substitutions are not made. The request for LED luminaires with corrected color temperature of 3000K or less is due to City resident complaints and recommendations by both the American Medical Association and International Dark Skies Association for reducing the amounts of blue light in the night sky. Fort Collins Community Development and Neighborhood Services 281 North College Avenue PO Box 580 Fort Collins, CO 80522 970.221.6750 970.224.6134 - fax fcgov. com/developmentreview November 18, 2016 Cathy Mathis TB Group 444 Mountain Ave Berthoud, CO 80513 RE: Village Cooperative Fort Collins, PDP160036, Round Number 1 Please see the following summary of comments from City staff and outside reviewing agencies for your submittal of the above referenced project. If you have questions about any comments, you may contact the individual commenter or direct your questions through the Project Planner, Clay Frickey, at 970-224-6045 or cfrickey@fcgov.com. Comment Summary: Department: Engineering Development Review Contact: Marc Virata, 970.221.6567, mvirataa)fcgov.com Topic: General Comment Number: 1 Comment Originated: 11/16/2016 11/16/2016-. Discussion with Transportation staff on the Horsetooth Road frontage improvements has general support on further exploration of the pork chop design to create the bike lane with the right turn lane avoiding the box structure. Further design implementation should be explored. Comment Number: 2 Comment Originated: 11/16/2016 11/16/2016: Discussion with Transportation staff finds general support on not necessarily requiring additional right-of-way dedication for the detached sidewalk system along Horsetooth Road, provided that access easement is in place. The right turn lane/pork chop would need to be fully in right-of-way. Comment Number: 3 Comment Originated: 11/16/2016 11/16/2016: The parameters for the sight distance easement shown on the plat would need further information. Comment Number: 4 Comment Originated: 11/16/2016 11/16/2016: Are the plans reflective of the "existing condition" today with the right turn lane constructed by Alberta Development? Comment Number: 5 Comment Originated: 11/16/2016