HomeMy WebLinkAboutALTA VISTA (903 BUCKINGHAM ST.) WTF - PDP - PDP160028 - REPORTS - RECOMMENDATION/REPORT W/ATTACHMENTS (5)Staff Report —Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 7
RECOMMENDATION:
Staff recommends approval of Alta Vista, PDP160028.
ATTACHMENTS:
1. Zoning & Site Vicinity Map
2. Alta Vista Planning Document Set (including site plan, elevations, and photo
simulations)
Staff Report —Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 6
F. Section 3.8.13(C)(8) — Color
All wireless telecommunications facilities shall be painted to match as
closely as possible the surrounding built environment. The proposed color
of the tower is green, which will appear similar to the nearby grain silos
employed by New Belgium brewing.
G. Section 3.8.13(C)(15) — Stealth Technology
All wireless facilities must employ stealth technology to mitigate the visual
impact of the tower. In this case, the applicant chose to build a structure
that mimics a grain silo used at one of the nearby breweries.
4. Compliance with Article 4 of the Land Use Code — Division 4.28 Industrial
M
The project complies with all applicable Article 4 standards as follows:
A. Section 4.28(B)(1)(a) — Permitted Uses
The proposed use, wireless telecommunications facility, is permitted in the
I zone district and is consistent with the district's intent to accommodate
uses that are complementary and support work places such as
manufacturing, warehousing, and distributing.
5. Findings of Fact/Conclusion:
In evaluating the request for Alta Vista Wireless Telecommunications Facility
Project Development Plan, Staff makes the following findings of fact:
A. The Project Development Plan/Final Plan complies with process located in
Division 2.2 — Common Development Review Procedures for
Development Applications of Article 2 — Administration.
B. The Project Development Plan/Final Plan complies with relevant
standards of Article 3 — General Development Standards.
C. The Project Development Plan/Final Plan complies with relevant
standards located in Division 4.28, Industrial (1) of Article 4 — Districts.
Staff Report — Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 5
fiberglass material. The silo will be a green color to match closely the
colors of other nearby silos.
At 68' tall, this tower will be the tallest structure on the Colorado Iron and
Metal Site and adjacent properties. Other silos in the vicinity are 40-50'
tall. The proposed tower, however, will be 12 — 32' feet shorter than the
Platte River Power Authority transmission lines nearby. The transmission
lines along Lemay Ave. and the north side of New Belgium's property
range from 80 — 100' tall. To mitigate for the tower's height, the proposed
tower will have a significant setback from the right-of-way. The tower will
be over 500' from the closest right-of-way. Since the tower is so far on the
interior of the site, the visual impact of the tower will be minimized.
C. Section 3.8.13(C)(3) — Wireless Telecommunications Equipment
Wireless telecommunications equipment shall be the same color as the
tower, be mounted as flush as possible, and not exceed the height of the
structure it is mounted to by 15'. Ground equipment must also be
screened in a manner compatible with the building's design, color, and
material. All of the antennae for this tower will be housed inside the
fiberglass silo so they will be completely screened and will not exceed the
height of the tower. The ground equipment will be screened by a wood
fence.
D. Section 3.8.13(C)(4) — Landscaping
In certain instances, ground equipment must be screened through
landscaping if no other screening method is employed. For this tower, the
site plan shows a wood fence that will provide screening for the ground
equipment. As such, this proposal is exempt from this standard.
E. Section 3.8.13(C)(5) — Fencing
When fences are used for screening, the fence must be built of wood,
masonry, stucco, or other acceptable, opaque materials. The fence may
not exceed 6 in height'. The proposed fence will be built from wood and
will not be taller than 6'
Staff Report — Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 4
2. Compliance with Article 2 of the Land Use Code — Administration
The project complies with all applicable Administrative procedures as follows:
A. Section 2.2.11(D)(9) — Post Denial Re -submittal Delay
Projects denied by a hearing officer may not be re -submitted for a period
of 6 months from the final decision unless the Director determines that the
new plan includes substantial changes in land use, residential density,
and/or non-residential intensity. The new tower is 12' shorter than
previously proposed, the tower no longer has a cap to enhance
compatibility, and the tower will use a different color to better blend into
the surrounding area. The Director determined these changes constituted
a substantial change in non-residential intensity and was eligible for re -
submittal.
3. Compliance with Article 3 of the Land Use Code — General Development
Standards:
The project complies with all applicable General Development Standards as
follows:
A. Section 3.8.13(C)(1) — Setbacks
For wireless towers, the setback of the facility from the property line shall
be 1 foot for every foot of height unless it can be demonstrated the
structure will collapse rather than topple. The proposed tower is designed
to collapse rather than topple, which exempts the tower from this
standard.
B. Section 3.8.13(C)(2) — Wireless Telecommunications Facilities
Wireless telecommunications facilities should be consistent with the
architectural character of the surrounding environment. If the wireless
telecommunications facility is an accessory use, the facility should be
constructed out of materials equal to or better than the materials of the
principal use. Since this facility will be located on the Colorado Iron and
Metal site, this will be considered an accessory use. Colorado Iron and
Metal is housed in a tan colored building constructed out of metal. The
building features a synthetic stone wainscot with a subtly pitched, metal
roof. The proposed wireless tower will be a 68' tall silo built out of a
Staff Report — Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 3
Staff Report — Alta Vista — PDP160028
Administrative Hearing 01-05-2017
Page 2
• The Project Development Plan/Final Plan complies with relevant standards
located in Division 4.28, Industrial (1) of Article 4 — Districts.
COMMENTS:
1. Background
The property was annexed into the City as part of the Northeast Consolidated
Annexation in June, 1974. The land sat vacant until 1998 when Vanworks built a
warehouse on the site. In 2008, Colorado Iron and Metal moved their operation to 903
Buckingham. Colorado Iron and Metal filed for a replat in 2012 to obtain the parcel to
the west. A hearing officer approved this replat in 2012. Following the replat, Colorado
Iron and Metal submitted the Colorado Iron and Metal Second Filing to expand their
operation onto the newly acquired parcel. Colorado Iron and Metal Second Filing was
approved in 2013 with the final documents recorded with the City on August 5, 2013.
Since recording their final documents, Colorado Iron and Metal has yet to install any of
the necessary public infrastructure to obtain vesting for their development.
Earlier in 2016, the applicant brought forward a Project Development Plan, PDP160004,
for a wireless tower at this site. This applicant proposed an 80' tower disguised as a
grain silo with a round cap to be painted white. The hearing officer denied this project
citing the height and design of the tower.
The surrounding zoning and land uses are as follows:
Direction
Zone District
Existing Land Uses
North
Industrial I
Brewery, institutional
South
Industrial (1)
Brewery, storage, light industrial
East
Industrial (1)
Warehouse, vacant
West
Industrial (1), Low Density Residential
(RL)
Vacant, single-family detached residential
A zoning and site vicinity map is presented on the following page.
City of
Fit Collins
ITEM NO 1
MEETING DATE
STAFF
Jan. 5, 2017
Clay Frickey
ADMINISTRATIVE HEARING OFFICER
PROJECT: Alta Vista, PDP160028
APPLICANT: Caleb Crossland
4450 Arapahoe Ave.
Suite 100
Boulder, CO 80303
OWNERS: Colorado Iron and Metal, Inc.
903 Buckingham St.
Fort Collins, CO 80524
PROJECT DESCRIPTION:
This is a request for a Project Development Plan to build a telecommunications tower
housed within a 2,000 sq. ft. wireless facility. This facility will provide critical wireless
coverage to the surrounding area. This is a developing industrial and residential area
where coverage is reaching its capacity limits and there is a growing need for advanced
quality voice and data services. This tower and facility will be used for structural
support of up to three wireless providers. Each provider will install antennas and on -
the -ground base station equipment. The site is located in the Industrial (1) zone district.
RECOMMENDATION: Staff recommends approval of Alta Vista, PDP160028.
EXECUTIVE SUMMARY:
Staff finds the proposed Alta Vista Project Development Plan complies with the
applicable requirements of the City of Fort Collins Land Use Code (LUC), more
specifically:
• The Project Development Plan/Final Plan complies with the process located in
Division 2.2 — Common Development Review Procedures for Development
Applications of Article 2 — Administration.
• The Project Development Plan/Final Plan complies with relevant standards of
Article 3 — General Development Standards.
Planning Services 281 N College Ave — PO Box 580 — Fort Collins, CO 80522-0580