HomeMy WebLinkAboutTIMBERLINE CHURCH EXPANSION - MAJOR AMENDMENT - 1-97B - CORRESPONDENCE -[6/20/07] Since no building permit is associated with Phase I improvements please
add a note to the phasing plans stating that fees for Phase I improvements will need
to be paid prior to issuance of a DCP for Phase I. Fees for the future Phase II
improvements can be associated with a building permit of a DCP for Phase II.
Please provide a breakdown for the increase in impervious area associated with
Phase I and those associated with Phase II improvements, in order to subdivide the
stormwater fees into two separate amounts, one for each phase.
Topic: Utility Plans
Number: 78 Created: 6/20/2007
[6/20/07] Please add a boulder to the riprap detail for the outfall into the Foothills
Channel to hide the pipe outfall.
Plans look OK for mylars. submittal at final.
Comment from Current Planning:
Please add the following note to the Site Plan:
Parking lot lighting, along the perimeter of the project, shall be
sensitive to and in compatibility with the abutting neighborhoods.
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6750.
Sincer/ely,
Ted Shepard
Chief Planner
Page 2
BHA Design
Whitney Duvall
1608 Oakridge Dr
Fort Collins, CO 80525
STAFF PROJECT REVIEW
Date: 06/27/2007
Staff has reviewed your submittal for TIMBERLINE CHURCH EXPANSION MAJOR
AMENDMENT, and we offer the following comments:
ISSUES:
Department: Engineering Issue Contact: Marc Virata
Topic: General
Number: 75 Created: 5/24/2007
[6/21/07] Carried over for reference.
[5/24/07] At the time of final submittal after public hearing, a Transportation
Development Review Fee of $1,000 is required. A Development Construction
Permit (DCP) will be required prior to any work pertaining to this major amendment.
Number: 81 Created: 6/21 /2007
[6/21/07] With the final submittal, we'll discuss permitting process via the DCP and
whether an amendment to the original development agreement and/or a new
development agreement is required.
Topic: Site Plan
Number: 76 Created: 5/24/2007
[6/21/07] Technical Services has indicated that there are still areas of concern. See
attached redlines.
[5/24/07] Technical Services has redlined areas on the site plan that may be of
concern for scanability purposes. Please see the attached redlines.
Department: PFA Issue Contact: Carle Dann
Topic: Fire
Number: 77 Created: 6/19/2007
[6/19/07] PFA has no additional comments or concerns at this time.
Department: Stormwater-Water-Wastewaterlssue Contact: Basil Harridan
Topic: Erosion Control Plans
Number: 79 Created: 6/20/2007
[6/20/07] The erosion control security estimate is calculated for Phase I. Please
clarify in the estimate calculations sheet that the figure calculated is for Phase I
improvements only. A separate Phase II security escrow calculation should also be
provided.
Topic: Stormwater Fees
Number: 80
Created: 6/20/2007