Loading...
HomeMy WebLinkAboutGRIT ATHLETICS FACILITY - PDP - PDP160024 - REPORTS - RECOMMENDATION/REPORT W/ATTACHMENTSGRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 10 E. Staff finds that the Request for Modification of Standard complies with applicable criteria under Section 2.8.2(H) in that: • The granting of the Modification would not be detrimental to the public good; • The plan as submitted will promote the general purpose of the standard for which the modification is requested equally well or better than would a plan which complies with the standard for which a modification is requested. F. This is because the architectural design of the building meets the overall intent of the standard in that the primary and secondary roofs remain pitched and not flat. The building is not box -like and there will be no rooftop mechanical equipment. The building's location is not highly visible from the 1-25 / E. Mulberry Street elevated interchange. There is no predominant architectural style within the IBP. RECOMMENDATION: Staff recommends: 1. Approval of the Request for Modification of Standard. 2. Approval of the GRIT Athletics #PDP160024. Attachments: 1. Applicant's Statement of Planning Objectives 2. Aerial Map 3. Site Plan 4. Landscape Plan 5. Architectural Elevations 6. Material Sample Board GRIT Athletics Facility, #PDP160024. Administrative Hearing, November 7, 2016 Page 9 3. State Highway 392 (Carpenter Road) and 1-25. Of these three, only the IBP is developed. Realistically, this particular standard will become most effective when applied to the two vacant centers. In addition, one of the fundamental purposes of requiring pitched roofs is to improve the aesthetics of commercial development as viewed from overhead from the elevated interchanges. Staff finds that the implementation of this standard is not critical to meeting the aesthetic objectives. There will no rooftop mechanical equipment and that the location of the building is such that it is not highly visible from the elevated interchange. • Finally, staff finds that the primary clerestory roof, accented by the off -setting secondary roof, represents a commercial architectural style that is attractive despite being shallower in pitch. Staff, therefore, finds that the Request for Modification to Section 3.9.5.(A) is justified based on the criteria of Section 2.8.2(H)(1): • The granting of the Modification would not be detrimental to the public good; • The plan as submitted will promote the general purpose of the standard for which the modification is requested equally well or better than would a plan which complies with the standard for which a modification is requested. 5. Findings of Fact/Conclusion: In evaluating the request for GRIT Athletics P.D.P., Staff makes the following findings of fact: A. The P.D.P. is in compliance with the Northern Colorado 1-25 Corridor Plan — Regional Communities (2001) and the 1-25 Subarea Plan (2003). B. The P.D.P. complies with the applicable land use and development standards of Article Four, Section 4.21 General Commercial zone district. C. The P.D.P. complies with the applicable Article Three General Development Standards with one exception. D. A Request for Modification of Standard to Section 3.9.5(A)(1)(a,b,c) Commercial Building Design Standards has been submitted and evaluated by Staff. GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 8 (1)(a) be pitched with a minimum slope of at least 5:12, (1)(b) incorporate the 5:12 pitch by use of a modified Mansard roof, covering a sufficient area of the roof so as to create the appearance that the Mansard roof covers the entire structure, and (1)(c) incorporate at least one (1) of the following elements into the design for each fifty (50) lineal feet of roof: 1. Projecting gables/dormers, 2. Hips, 3. Horizontal or vertical breaks, 4. Three (3) or more roof planes. The building features a primary clerestory roof and a secondary roof both of which are pitched at a 1:12 ratio. And, the building does not include any of the four features required under Section 3.9.5 (A)(1)(c). The applicant has submitted a Request for Modification to this standard. The applicant contends that given the size of the building, the two off -setting clerestory roofs sufficiently mitigate the mass and bulk of the building in a manner that meets the overall intent of the standard. The building, as designed, is not a simple box. Rather, the primary purpose of the main roof is to allow natural day -lighting into the interior space. In addition, the rectangular -shaped building is oriented with the short side facing the street so the full effect of the two pitched roofs will be highly visible. Finally, the applicant contends that the vacant site is an infill condition between two existing buildings, both of which have flat roofs, and that this juxtaposition allows the proposed building to stand out in a positive manner. Staff has evaluated the Request for Modification and makes the following findings: • The IBP was mostly developed in Larimer County. There is no cohesive or unified architectural theme that establishes a distinctive character. The site is an infill parcel and is flanked by two flat -roofed buildings. At 7,545 square feet, the building is considerably smaller than the Otter Box Distribution Warehouse at 81,579 square feet. • The City's 1-25 Sub -area Plan intentionally steers highway -oriented and commercial development into three activity centers. The planning objective is to create a degree of open space among the centers to minimize the appearance of sprawl development. The three activity centers are: 1. State Highway 14 (East Mulberry Street) and 1-25 2. East Prospect Road and 1-25 GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 7 side of the rectangular building). This entrance is as close to the street as possible given its orientation and it is highlighted by a projecting canopy. The street -facing elevation features two full -height windows which help orient the entrance to the street. M. Section 3.5.3(C)(1) — Relationship of Buildings to Streets, Walkways and Parking — Orientation to a Connecting Walkway: This standard requires that commercial buildings align with any established building/sidewalk relationship and be located no more than 15 feet from the right- of-way of the adjoining street (Southeast Frontage Road). The only established building / sidewalk relationship is the existing mini -frontage road that was constructed at the time the two adjoining sites developed in the County. In response, the proposed building is brought as close to the mini -frontage as possible while still allowing for emergency access and parking lot access along the southwest side of the building. As mitigation, the connecting walkway is as far to the northeast as possible so there is no conflict with traffic entering or exiting the parking lot. N. Section 3.5.3(D)(E) — Commercial Architecture. - These standards require that the building features a sufficient level of architectural details that break up the mass, articulate the facades and are not duplicative of a standardized prototype design. In response, the building includes a distinctive base of split -face block and the building field is a combination of split -face block and insulated metal panels. Two accent bands are provided which consist of a different color split -face block. The main roof is a clerestory with a bank of windows facing southwest. The secondary roof over the office is pitched in the opposite direction than the main roof which adds interest. The roof material is standing seam metal. Both roofs include overhangs with supporting brackets O. Section 3.6.4 — Transportation Impact Study: A Transportation Impact Study was not required for this P.D.P. The applicant will be required to obtain the necessary access control permits from CDOT Region IV as the State has jurisdiction over the S.E. Frontage Road. P. Section 3.9.5(A) (1)(a, b, c) — Development Standards for the 1-25 Corridor — Commercial Building Design Standards - Request for Modification: This standard requires that in the 1-25 Overlay Zone, for commercial buildings, the roofs on principal structures with a building footprint of less than 10,000 square feet, must: GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 6 F. Section 3.2.2(C)(5) — Walkways: There is a connecting walkway that links the front door of the building to the public sidewalk along the Southeast Frontage Road. G. Section 3.2.2(J) — Setbacks: The Southeast Frontage Road is classified as a Local Street. The vehicular use area is separated from this street by ten feet which complies with the required minimum of ten feet. H. Section 3.2.2(K)(2) — Non-residential Parking Requirements: The facility requires a minimum of no less than 16 and an allowable maximum of no more than 34 spaces. The P.D.P. provides 19 spaces in compliance with the standard. I. Section 3.2.4 — Site Lighting: All pole and building -mounted lighting will feature sharp cut-off and fully -shielded luminaries. J. Section 3.2.5 — Trash and Recycling Enclosure: The trash and recycling enclosure will feature exterior masonry materials that match the building and a solid gate. K. Section 3.4.1(E)(I) — Establishment of Buffer Zones, Design and Aesthetics: The proposed project is located within 500 feet of Boxelder Creek and associated wetlands, which are considered significant natural features and part of a wildlife movement corridor. An Ecological Characterization Study was completed in July 2016 to document the context of the site and any potential impacts of the project. Due to the property's urban location and high human disturbance level, there is limited wildlife use on the site and its ecological value is low. The proposed project would not degrade the off -site ecological features. Any visual impacts of the project on the aesthetics of the Boxelder Creek corridor would be mitigated by a row of large, dense shrubs planted at the southeastern boundary of the site, per LUC section 3.4.1(1). L. Section 3.5.3(C)(1) — Relationship of Buildings to Streets, Walkways and Parking — Orientation to a Connecting Walkway: The street elevation is to the northwest (the short side of the rectangular building) but the entrance to the building is located along the southwest elevation (the long GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 5 detached sidewalk, with street trees, that helps link the establishments on both sides and the IBP as a whole. The proposed activity, wrestling, will be indoors but with the four overhead garage -type doors on the southwest side, such activity will be visible on days when the doors are open, weather permitting. Although this type of activity is not pedestrian -oriented as envisioned by the standard, it is activity nonetheless that is unique and interesting and not typically found in a business park. 4. Compliance with Applicable Article Three General Development Standards: A. Section 3.2.1 — Landscaping and Tree Protection: There are three existing street trees along the S.E. Frontage Road that will be preserved. Additional trees and shrubs will be provided around all four sides of the site. B. Section 3.2.1(E)(4)(a)(b) — Parking Lot Perimeter Landscaping: The parking lot along the southwest edge faces the Honda Motorcycle Dealership. This edge is treated with a combination of various shrubs. C. Section 3.2.1(E)(5) — Parking Lot Interior Landscaping: The parking includes three landscape islands along the southwest edge with one tree per island. There are two landscape islands along the southwest edge of the building as well. The parking lot complies with the standard that 6% of the area be landscaped which is the minimum required for parking lots with less than 100 spaces. D. Section 3.2.2(B) — Access, Circulation and Parking: The parking and circulation system consists of an existing, shared, private driveway that splits the northeast property line with the adjoining development (Otter Box Distribution Warehouse). This driveway connects to an existing private drive that serves the two lots like a mini -frontage road which then leads to the parking lot. With the site being only 1.19 acres and having only 19 parking stalls, the access, circulation and parking system is safe, convenient and sufficient to serve the proposed use. E. Section 3.2.2(C)(4) — Bicycle Parking: Four bike parking spaces are required and one is required to be enclosed. The P.D.P. provides four space and one is enclosed in compliance with the standard. GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 4 "The Commercial Corridors classification is intended to provide for a wide range of community and regional retail uses, as well as offices, business and personal services. The majority of Commercial Corridor areas, near the 1-25/Mulberry Street interchange, are fully developed, whereas areas near the 1-25/Prospect Road interchange are, for the most part, undeveloped. While this classification is typically the location for highway business and auto -related uses, it also presents opportunities over time to transform existing developed areas into mixed -use (including residential), multi -modal centers, concurring with the overall community vision for Fort Collins." According to the 1-25 Corridor Plan Land Use Map, the subject parcel was properly zoned into the C-G, General Commercial zone district. Most of the development standards related to the Sub -area plan are already addressed in the Article Three General Development Standards and the Article Four zone district standards. For those remaining standards that intended to cover the entire sub -area, Section 3.9 was established to implement the vision of the plan. The P.D.P. will be evaluated by these standards, as found applicable, in a subsequent section of this staff report. 3. Compliance with the C-G, General Commercial Zone District: A. Section 4.21(B)(2) - Land Use: A Limited Indoor Recreational Facility that is less than 5,000 square feet is a permitted use in the C-G zone subject to Administrative Review. Although the building would be a total of 7,545 square feet, 4,784 would be devoted to indoor recreation. The balance would be divided between office and equipment storage. A. Section 4.21(E)(2) - Site Design: This standard requires that: "Pedestrian -oriented outside spaces be placed next to activity areas that generate the users (such as street corners, shops, stores, offices, day care and dwellings). Because liveliness created by the presence of people is the main key to the attractiveness of such space, to the maximum extent feasible, the development shall link outdoor space to and make them visible from streets and sidewalks. Sculpture, kiosks or shelters are encouraged in prominently placed outdoor spaces. " The site is relatively small compared to the balance of the IBP. It is not located on a corner and the use is not a shop, store, office, daycare or dwelling. As such, there is no pedestrian -oriented outdoor space. Instead, the P.D.P. provides for a continuous GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 3 COMMENTS: 1. Background: The surrounding zoning and land uses are as follows: N: C-G Otter Box Warehouse and Distribution Facility S: C-G Honda Motorcycle Dealership E: C-G Boxelder Creek Open Space W: C-G Air Care Colorado Emissions Testing Facility The site is Lot 13 of the Interchange Business Park which was approved and developed in Larimer County. The entire business park was annexed in 2005. Within this park, the following have been approved in the City of Fort Collins: • Otter Box Warehouse Distribution Facility Expansion • Air Care Colorado Emissions Testing Facility • Maverik Convenience Store and Fuel Sales 2. Northern Colorado 1-25 Corridor Plan — Regional Communities (2001), and 1-25 Sub -area Plan (2003): In 2001, the City of Fort Collins adopted the Northern Colorado 1-25 Corridor Plan in conjunction with Larimer County, Weld County, Town of Berthoud, Town of Timnath, Town of Johnstown, Town of Windsor, City of Loveland and the Colorado Department of Transportation. This joint planning effort encompassed an area roughly one mile on either side 1-25 for a distance of 32 miles for a total of over 60 square miles. The basic thrust of this Plan was for the jurisdictions to collaborate on a unified vision for the Corridor particularly with regard to maintaining physical separation, retaining individual characteristics and identities, and addressing the built and natural environment. After adoption of the regional plan in 2001, the City of Fort Collins followed up with its own 1-25 Sub -area Plan in 2003 which covers the area along 1-25 between Larimer County Roads 52 (Richards Lake Road) and 32 (Carpenter Road and Colorado State Highway 392). The most significant difference between the two plans is the Subarea plan deals with land uses in a more detailed manner than the regional plan because the regional plan is based on existing land use plans of the participating jurisdictions. The Fort Collins Sub -area plan builds upon the earlier effort but is more site specific. One of the primary findings of the Sub -area plan is that the Interchange Business Park, at the southeast quadrant of 1-25 and State Highway 14, is designated as an Activity Center/Commercial Corridor. The Plan states: GRIT Athletics Facility, #PDP160024, Administrative Hearing, November 7, 2016 Page 2 C. The P.D.P. complies with the applicable Article Three General Development Standards with one exception. D. A Request for Modification of Standard to Section 3.9.5(A)(1)(a,b,c), Commercial Building Design Standards, has been submitted and evaluated. Staff finds that the Modification complies with the applicable criteria of Section 2.82(H)(1). Vicinity Map 1 inch =1,000 feet GRIT Athletics Facility City of Fit Collins PROJECT: GRIT ATHLETICS FACILITY #PDP160024 APPLICANTS: RSW Holdings LLC c/o TB Group 444 Mountain Avenue Berthoud, CO 80513 OWNERS: RSW Holdings LLC 2120 Milestone Drive Fort Collins, CO 80515 PROJECT DESCRIPTION: ITEM NO 1 MEETING DATE November 7, 2016 STAFF Ted Shepard HEARING OFFICER This is a request for a P.D.P. for a one-story, 7,545 square foot building on a vacant lot located at 846 S.E. Frontage Road. The parcel is also identified as Lot 13 of the Amended Plat of Lots 13 and 14, Interchange Business Park (IPB). The facility will be used as a non-profit wrestling facility. Of the total building, approximately 4,784 square feet will be devoted to limited indoor recreation, 1,694 square feet will be used as office space, and 1,067 square feet will be for equipment storage. There will be 19 parking spaces. The site is 1.19 acres and located in the General Commercial (CG) zone district. The P.D.P. includes a Request for Modification to Section 3.9.5(A) — Commercial Building Design Standards in the 1-25 Sub -area. RECOMMENDATION: Approval of the Request for Modification and the P.D.P. EXECUTIVE SUMMARY: A. The P.D.P. is in compliance with the Northern Colorado 1-25 Corridor Plan — Regional Communities (2001) and the 1-25 Subarea Plan (2003). B. The P.D.P. complies with the applicable land use and development standards of Article Four, Section 4.21 General Commercial zone district. Planning Services 281 N College Ave — PO Box 580 — Fort Collins, CO 80522-0580 fcgov.com/developmentreview/ 970.221.6750