HomeMy WebLinkAboutWILMARC MEDICAL - PDP - PDP160033 - CORRESPONDENCE -Department: Water -Wastewater Engineering Contact: Wes Lamarque, 970-416-2418, wlamarauenafcaov.com Topic: General Comment Number: 1 Comment Originated: 11/02/2016 11/02/2016: Please provide water usage calculations to verify the 1 1/2 inch water service and meter are adequate. Comment Number: 2 Comment Originated: 11/02/2016 11/02/2016: The fire hydrant at the north end of the building acts as a long dead end and may present poor water quality issues. Discussion needs to take place to explore if there is a better location or option for an additional hydrant. Department: Zoning Contact: Noah Beals, 970-416-2313, nbeals fcgov.com Topic: General Comment Number: 1 Comment Originated: 11/01/2016 11/01/2016: The signature block for Planning on the site plan needs to match the signature block on the plat. Comment Number: 2 Comment Originated: 11/01/2016 11/01/2016: Please provide and overall site plan on one sheet. Comment Number: 3 Comment Originated: 11/01/2016 11/01/2016: The landscape sheets and lighting plan sheets need to be included on the sheet index of the site plan, where the signature block is. Comment Number: 4 Comment Originated: 11/01/2016 11/01/2016: Need to include a management plan to establish the seed mix areas Comment Number: 5 Comment Originated: 11/01/2016 11/0112016: A full tree stocking is required on the west and south landscaped areas of the building. Comment Number: 6 Comment Originated: 11/01/2016 11/01/2016: The planting beds need to include more details. Comment Number: 7 Comment Originated: 11/01/2016 11/01/2016: The sidewalk connection to precision could be moved to the west. Contact: Pete Wray, 970-221-6754, owrav fcaov.com Topic: General Comment Number: 8 Comment Originated: 11/02/2016 11/02/2016: A neighborhood meeting is scheduled for November 17, 2016 for this project. The delay for holding this meeting was approved by Planning previously. Page 12 of 12 Comment Number: 9 Comment Originated: 11/04/2016 11/04/2016: All reception numbers for documents recorded by separate document, must be added prior to producing mylars. Comment Number: 10 Comment Originated: 11/04/2016 11/04/2016: Is the remainder of Lot 2, Harmony Technology Park, Second Filing going to be a D,U&AE? Please show the limits of the new D,U&AE on this plat. Comment Number: 11 Comment Originated: 11/04/2016 11/04/2016: All easements must be labeled & locatable. If the easements east of the property are not relevant to the plat, please remove. See redlines. Comment Number: 12 Comment Originated: 11/04/2016 11/04/2016: There is text that needs to be rotated 180°. See redlines. Topic: Site Plan Comment Number: 13 Comment Originated: 11/04/2016 11/04/2016: Please revise the legal description as marked. See redlines. Comment Number: 14 Comment Originated: 11/04/2016 11 /04/2016: Please change the title block on all sheets as marked. See redlines. Comment Number: 15 Comment Originated: 11/04/2016 11/04/2016: Some of the easement descriptions shown are incorrect. If they are going to stay on the plan, they should match what is shown on the Subdivision Plat. Comment Number: 16 Comment Originated: 11/04/2016 11/04/2016: There are match line issues. See redlines. Comment Number: 17 Comment Originated: 11/04/2016 11/04/2016: There is text that needs to be rotated 180°. See redlines. Department: Traffic Operation Contact: Nicole Hahn, 970-221-6820, nhahn fcaov.com Topic: General Comment Number: 1 Comment Originated: 11/01/2016 11/01/2016: There appears to bean off site pedestrian path adjacent to the property, connecting into that path be beneficial to the project site pedestrian traffic. Comment Number: 2 Comment Originated: 11/04/2016 11/04/2016: The conclusions in the traffic study indicate that a signal is warranted at Harmony and Technology Parkway. We will need a signal warrant study and professional recommendation to accompany the study if the study is suggesting that this development will trigger the need for the signal at this time. If this is not what the study is suggesting than the traffic study conclusions can be reviewed and revised. We are available to meet and discuss this further upon request. Department: Water Conservation Contact: Eric Olson, 970-221-6704, eolson(Mcaov.com Topic: General Comment Number: 1 Comment Originated: 10/31/2016 10/31/2016: Irrigation plans are required no later than at the time of building permit. The irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of the Land Use Code. Direct questions concerning irrigation requirements to Eric Olson, at 221-6704 or eolson@fcgov.com Page 11 of 12 Comment Number: 24 Comment Originated: 11/04/2016 11/04/2016: Some of the easement descriptions shown are incorrect. If they are going to stay on the plan, they should match what is shown on the Subdivision Plat. Comment Number: 25 Comment Originated: 11/04/2016 11/04/2016: Is the right of way line shown along Precision Drive the original right of way line, or the new line after the 2' of right of way is dedicated? See redlines. Comment Number: 26 Comment Originated: 11/04/2016 11/04/2016: There are line over text issues. See redlines. Comment Number: 27 Comment Originated: 11/04/2016 11/04/2016: There is text that needs to be rotated 1800. See redlines. Comment Number: 28 Comment Originated: 11/04/2016 11/04/2016: There is text that needs to be masked. Mask all text in hatched areas. See redlines. Topic: Landscape Plans Comment Number: 18 Comment Originated: 11/04/2016 11/04/2016: Please revise the legal description as marked. See redlines. Comment Number: 19 Comment Originated: 11/04/2016 11/04/2016: Please change the title block on all sheets as marked. See redlines. Comment Number: 20 Comment Originated: 11/04/2016 11/04/2016: There are match line issues. See redlines. Topic: Lighting Plan Comment Number: 22 Comment Originated: 11/04/2016 11/04/2016: Please change the title block on all sheets as marked. See redlines. Topic: Plat Comment Number: 2 Comment Originated: 11/04/2016 11/04/2016: Please add the missing note "There shall be no private.... of the City Code.". Comment Number: 3 Comment Originated: 11/04/2016 11/04/2016: Please add new title commitment information if available. You could be potentially liable for any documents recorded since this date. Comment Number: 4 Comment Originated: 11/04/2016 11/04/2016: Please add bearings & distances as marked. See redlines. Comment Number: 5 Comment Originated: 11/04/2016 11/04/2016: Please clarify if the 10' Drainage, Utility & Access Easement is on or off site, and why a separate document is needed. See redlines. Comment Number: 6 Comment Originated: 11/04/2016 11/04/2016: Is the arrow (marked) in the right location for the Utility & Drainage Easement. See redlines. Comment Number: 7 Comment Originated: 11/04/2016 11/04/2016: Please label the Point Of Beginning. Comment Number: 8 Comment Originated: 11/04/2016 11/04/2016: A detail of the southwest corner of the property would be helpful. See redlines. Page 10 of 12 Comment Number: 1 Comment Originated: 10/25/2016 10/25/2016: Current Erosion Control Materials Submitted do not meet requirements. Please submit; an Erosion Control Plan (Based upon redlines), an Erosion Control Report (Based upon comments), and an Escrow / Security Calculation (Recalculated based upon redlines and comments). Also, based upon the area of disturbance State permits for stormwater will be required since the site is over an acre. If you need clarification concerning the erosion control section, or if there are any questions please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com Contact: Wes Lamarque, 970-416-2418, wlamargue(a)fcgov.com Topic: General Comment Number: 2 Comment Originated: 11/02/2016 11/02/2016: Please discuss how each regional pond taking flows for the site is able to detain the flows and that the impervious area and acreage is equal to or less than what was planned. Comment Number: 3 Comment Originated: 11/04/2016 11/04/2016: The storm sewer taking flows from the inlet in Technology Parkway is required to be in a 20-ft wide drainage easement. discussion needs to take place if this alignment is the best option for future maintenance. Comment Number: 4 Comment Originated: 11/04/2016 11/04/2016: Stormwater is ready for a hearing. Additional comments will follow during final compliance. Department: Technical Services Contact: Jeff County, 970-221-6588, icounty(&fcgov.com Topic: Building Elevations Comment Number: 21 Comment Originated: 11/04/2016 11/04/2016: Please change the title block on all sheets as marked. See redlines. Topic: Construction Drawings Comment Number: 23 Comment Originated: 11/04/2016 11/04/2016: Please provide the following information for the Benchmark Statement in the EXACT format shown below. PROJECT DATUM: NAVD88 BENCHMARK # w/ DESCRIPTION ELEVATION: BENCHMARK # w/ DESCRIPTION ELEVATION: PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR VERTICAL DATUMS. IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - X.XX'. Page 9 of 12 Comment Number: 6 Comment Originated: 11/02/2016 11/02/2016: GENERAL Further PFA comments may arise at Building Permit Stage Department: Planning Services Contact: Pete Wray, 970-221-6754, pwrav(o)fcgov.com Topic: Building Elevations Comment Number: 6 Comment Originated: 11/02/2016 11/02/2016: Need to show details of building materials on plans such as type of brick and color so full spectrum of finishes can be reviewed. Topic: General Comment Number: 7 Comment Originated: 11/04/2016 11/04/2016: A neighborhood meeting is scheduled for November 17, 2016 for this project. The delay for holding this meeting was approved by Planning previously. Comment Number: 10 Comment Originated: 11/04/2016 11/04/2016: Need revised plans relating to comments 1,2,4,9 for hearing. if this warrants another formal round of review let us know. or a PDF round. Topic: Landscape Plans Comment Number: 4 Comment Originated: 11/02/2016 11/02/2016: Add full landscape plan on LP003, adjust sheets accordingly. Comment Number: 5 Comment Originated: 11/02/2016 11/0212016: LP101/LP102- Need more detail on landscape planting for building foundations and perimeter near parking and trash enclosure areas for more full tree and shrub design. Topic: Plat Comment Number: 9 Comment Originated: 11/0412016 11/04/2016: Need correct plat for hearing to include lot 1 and or 2. Topic: Site Plan Comment Number: 1 Comment Originated: 11/02/2016 11/02/2016: LS001- Add notes and table from LS002 to this cover sheet. Comment Number: 2 Comment Originated: 11/02/2016 11/02/2016: LS002- Add a full rendering of site plan on this sheet to include both parcels. Comment Number: 3 Comment Originated: 11/02/2016 11/02/2016: LS101/LS102- Clarify timing and responsibility for developing connecting trail as identified on ODP. If not part of this PDP, show sidewalk connection to east property line for future trail link. Comment Number: 8 Comment Originated: 11/04/2016 11/04/2016: Tech Pkwy frontage, move 5' sidewalk to abut ROW and property line. Department: Stormwater Engineering Contact: Jesse Schlam, 970-218-2932, ischlam(&fcgov.com Topic: Erosion Control Page 8 of 12 Comment Number: 2 Comment Originated: 10/27/2016 10/31/2016: FIRE AERIAL ACCESS Aerial Fire Apparatus access is required for structures over 30ft in height which is measured to the top of parapet walls. From the provided plan elevations, a large proportion of the building appears to be over 30ft in height thereby triggering Aerial Apparatus standards. Code language provided below: WHERE REQUIRED: > IFC D105.1: Where the vertical distance between the grade plane and the highest roof surface exceeds 30 feet, approved aerial fire apparatus access roads shall be provided. For purposes of this section, the highest roof surface shall be determined by measurement to the eave of a pitched roof, the intersection of the roof to the exterior wall, or the top of parapet walls, whichever is greater. WIDTH: > IFC D105.2; FCLUC 3.6.2(B)2006; and Local Amendments: Aerial fire apparatus access roads shall have a minimum unobstructed width of 30 feet, exclusive of shoulders, in the immediate vicinity of the building or portion thereof. PROXIMITY TO BUILDING: > IFC D105.3: At least one of the required access routes meeting this condition shall be located within a minimum of 15 feet and a maximum of 30 feet from the building, and shall be positioned parallel to one entire side of the building. The side of the building on which the aerial fire apparatus access road is positioned shall be approved by the fire code official. Comment Number: 3 Comment Originated: 10/31/2016 10/31/2016: WATER SUPPLY Hydrant spacing and flow must meet minimum requirements based on type of occupancy. A hydrant is required at 600' intervals along Technology Parkway which would indicate the addition of another hydrant being installed in conjunction with this project. Code language provided below. > IFC 507.5 and PFA Policy: COMMERCIAL REQUIREMENTS: Hydrants to provide 1,500 gpm at 20 psi residual pressure, spaced not further than 300 feet to the building, on 600-foot centers thereafter. Comment Number: 4 Comment Originated: 11/02/2016 11/02/2016: FIRE LANE SIGNS The limits of the fire lane shall be fully defined. Fire lane sign locations should be indicated on future plan sets. The fire lane sign detail (diagram 1418) currently shown on the plan is an outdated version. Please update with current detail. Code language provided below. > IFC D103.6: Where required by the fire code official, fire apparatus access roads shall be marked with permanent NO PARKING - FIRE LANE signs complying with Figure D103.6. Signs shall have a minimum dimension of 12 inches wide by 18 inches high and have red letters on a white reflective background. Signs shall be posted on one or both sides of the fire apparatus road as required by Section D103.6.1 or D103.6.2. Comment Number: 5 Comment Originated: 11/02/2016 11/02/2016: FDC > IFC 912.2: Fire Department Connections shall be installed in accordance with NFPA standards. Fire department connections shall be located on the street side of buildings, fully visible and recognizable from the street or nearest point of fire department vehicle access. The location of the FDC shall be approved by the fire department. Page 7 of 12 Topic: General Comment Number: 1 Comment Originated: 11/01/2016 11/01/2016: Light & Power will has electric facilities running along both Technology Pkwy and Precision Dr. that can be utilized to serve this proposed building. Comment Number: 2 Comment Originated: 11/01/2016 11/01/2016: Development charges, electric Capacity Fee, Building Site charges and any system modification charges necessary will apply to this development. Comment Number: 3 Comment Originated: 11/01/2016 11/01/2016: As your project begins to move forward please contact Light and Power Engineering to coordinate the streetlight, transformer and electric meter locations, please show the locations on the utility plans. Comment Number: 4 Comment Originated: 11/01/2016 11/01/2016: Please provide a one line diagram and a C-1 form to Light and Power Engineering. The C-1 form can be found at: http://zeus.fcgov.com/utils-procedures/files/EngWiki/WikiPdfs/C/C-1 Form.pdf Comment Number: 5 Comment Originated: 11/01/2016 11/01/2016: You may contact FCU Light & Power, project engineering if you have questions. (970) 221-6700. You may reference Light & Power's Electric Service Standards at http://www.fcgov. com/utilities/img/site_specific/uploads/ElectricServiceStandards_F INAL_17June2016.pdf You may reference our policies, development charge processes, and use our fee estimator at http://www.fcgov.com/utilities/business/builders-and-developers. Department: PFA Contact: Jim Lynxwiler, 970-416-2869, ilynxwilerApoudre-fire.org Topic: General Comment Number: 1 Comment Originated: 10/27/2016 10/31/2016: 2015 IFC CODE ADOPTION The Poudre Fire Authority and the City of Fort Collins are in the process of adopting the 2015 International Fire Code. Building plan reviews shall be subject to the adopted version of the fire code in place at the time of plan review submittal and permit application. Page 6 of 12 Comment Number: 1 Comment Originated: 11/02/2016 11 /02/2016: Building Permit Pre -Submittal Meeting: Pre -Submittal meetings are required to assist the designer/builder by assuring, early on in the design, that the new commercial or multi -family projects are on track to complying with all of the adopted City codes and Standards listed below. The proposed project should be in the early to mid -design stage for this meeting to be effective and is typically scheduled after the Current Planning conceptual review meeting. Applicants of new commercial or multi -family projects are advised to call 416-2341 to schedule a pre -submittal meeting. Applicants should be prepared to present site plans, floor plans, and elevations and be able to discuss code issues of occupancy, square footage and type of construction being proposed. Construction shall comply with the following adopted codes as amended: 2012 International Building Code (IBC) 2012 International Residential Code (IRC) 2012 International Energy Conservation Code (IECC) 2012 International Mechanical Code (IMC) 2012 International Fuel Gas Code (IFGC) 2012 International Plumbing Code (IPC) as amended by the State of Colorado 2014 National Electrical Code (NEC) as amended by the State of Colorado Fort Collins has amendments to most of the codes listed above. See the fcgov.com web page to view them. Accessibility: State Law CRS 9-5 & [CC/ANSI A117.1-2009. Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF. Frost Depth: 30 inches. Wind Load: 100- MPH 3 Second Gust Exposure B. Seismic Design: Category B. Climate Zone: Zone 5 Energy Code Use 1. Single Family; Duplex; Townhomes: 2012 IRC Chapter 11 or 2012 IECC. 2. Multi -family and Condominiums 3 stories max: 2012 IECC residential chapter. 3. Commercial and Multi -family 4 stories and taller: 2012 IECC commercial chapter. Wilmarc — project specific concerns: 1. Fire -sprinkler systems or fire -containment is required for buildings over 5000 sq.ft. 2. Upgraded insulation is required for buildings using electric heat or cooling. 3. Low -flow Watersense plumbing fixtures (toilet, faucets, shower heads) are required. 4. Low VOC interior finishes. City of Fort Collins Building Services Plan Review 416-2341 Department: Light And Power Contact: Coy Althoff, , CAlthoff(&fcgov.com Page 5 of 12 Comment Number: 4 Comment Originated: 11/04/2016 11/04/2016: If there are any existing trees within the property lines, please contact the City Forester for an onsite meeting to obtain tree inventory and mitigation information for landscape plans. Existing significant trees should be retained to the extent reasonably feasible. Comment Number: 5 Comment Originated: 11/04/2016 11/04/2016: Explore adding additional appropriate ornamental and conifer trees where feasible in planting beds and in wider lawn areas along Precision Drive and Technology Parkway. Comment Number: 6 Comment Originated: 11/04/2016 11/04/2016: Species selection Greenspire Lindens typically do not survive or thrive well in parking lot islands and peninsulas. Please evaluate changing Lindens in these locations for better adapted shade trees. The City Forester suggests Kentucky Coffeetree would be a good canopy tree for these locations. Caddo Maples are still being evaluated for their range of adaptability in Fort Collins. Typically locations to consider for their use do not include overly exposed or dry locations. Forestry requests that an alternative canopy shade tree on the Street Tree List be placed where Caddo Maples are shown in parkways as street trees. Caddo Maples presently placed in lawn areas off parkways on private property are okay. Comment Number: 7 Comment Originated: 11/04/2016 11/04/2016: Minimum Species Diversity Please check quantities of species used for compliance with the Land Use Code — minimum species diversity. Please list percentages of each tree species under the Plant Schedule. Comment Number: 8 Comment Originated: 11/04/2016 11/04/2016: Please list all trees as balled and burlapped. Department: Internal Services Contact: Russell Hovland, 970-416-2341, rhovland(d)Jcgov.com Topic: Building Insp Plan Review Page 4 of 12 Contact: Sheri Langenberger, 970-221-6573, slangenberger(aMcgov.com Topic: General Comment Number: 1 Comment Originated: 11/02/2016: the project owes an additional $1,173.26 for TDRF PDP fees. acreage being platted was not used in the submitted calculations. Department: Environmental Planning Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak(a)fcgov.com Topic: General Comment Number: 1 11/02/2016 The total Comment Originated: 11/02/2016 11/02/2016: Memo ECS received. Environmental Planning concurs with consultant no natural habitat buffer zone extending onto property. Thank you. Topic: Landscape Plans Comment Number: 2 Comment Originated: 11/02/2016 11/02/2016: Include scientific names for seed to be applied in bioswale. Seeding rate and specifications for proper installation needed as well. If the proposed project is approved, highly recommend ensuring a qualified, experienced contractor installs the bioswale. Topic: Lighting Plan Comment Number: 3 Comment Originated: 11/02/2016 11/02/2016: More detail needed on lighting plan and manufacture cut -sheets. Clarify on plans which bulbs will be selected i.e. 2500K, 3000K etc. Staff requests 3000K or below especially for any LED lights due to resident complaints and recommended specifications by the International Dark Skies Association and the American Medical Association. Department: Forestry Contact: Tim Buchanan, 970-221-6361, tbuchanan(a)fcgov.com Topic: Landscape Plans Comment Number: 1 Comment Originated: 11/04/2016 11/04/2016: There are currently only 2 species of street trees on the plan. Please increase street tree diversity by using around 4 different species. Suggestions of trees can be found on the Street Tree List. Comment Number: 2 Comment Originated: 11/04/2016 11/04/2016: Please display any locations of street lights and stop signs and provide code required separation figures. Comment Number: 3 Comment Originated: 11/04/2016 11/04/2016: The first tree on Precision Drive from Technology Parkway appears to be too close to the corner and may cause visibility issues. Please evaluate not including this tree for improvement of intersection visibility. Page 3 of 12 Comment Number: 7 Comment Originated: 11/04/2016 11/04/2016: The indication on Sheet 4 Note 3 is the installation of residential local street approach 1606a for the two driveways. These driveways should instead be designed and referenced with LCUASS detail 707.1 or 707.2. The radii for the driveways should be 15 feet in accordance with LCUASS Table 8-2. Comment Number: 8 Comment Originated: 11/04/2016 11/04/2016: We'll want to take a closer look at the driveways and whether they direct drainage across the sidewalk. No more than 750 square feet of sheet flow drainage area is allowed across the sidewalk from behind a driveway. Comment Number: 9 Comment Originated: 11/04/2016 11/04/2016: While not technically required, I'm wondering with the additional 1 foot behind the sidewalk for Technology Parkway, whether the applicant would consider either detaching the sidewalk one foot further east for a wider parkway, (or providing a 6 foot sidewalk that then abuts the right-of-way line.) The trees within the parkway have increased viability with the additional width, and the area behind the back of walk that's right-of-way can't be utilized otherwise. Comment Number: 10 Comment Originated: 11/04/2016 11/04/2016: We'll want verification as to whether MAVD/Harmony Technology Park LLC will remain the owner of the property throughout the entitlement of the project, or whether WilMarc Medical LLC will seek to acquire title to the property prior to the final plan approval. This will have implications on both the development agreement as well as site plan/plat signatures. While information on the plans is a little unclear as to whether work is occurring offsite of the development plan boundary, vs. being built by the master developer as part of the infrastructure plan set, the fact that all work appears to be in land currently owned by MAVD/Harmony Technology Park LLC, no letters of intent for offsite easements appears to be needed. Comment Number: 11 Comment Originated: 11/04/2016 11/04/2016: I'm wondering why the project would not provide some sort of connection to the abutting trail that abuts the regional pond. It would seem like an amenity that the end users would look to access, but there's no corresponding pathway to do so. Comment Number: 12 Comment Originated: 11/04/2016 11/04/2016: The plat calls out an emergency access easement for the main drive aisle internal to the project, however this does not appear to be labelled on the plans. Comment Number: 13 Comment Originated: 11/04/2016 11/04/2016: What is the two parallel lines that cross into the utility easement behind Technology Parkway right-of-way? Is this a drainage pan? Just looking to ensure this isn't a potential conflict in the utility easement. Comment Number: 14 Comment Originated: 11/04/2016 11/04/2016: Comment #1 from Sheri Langenberger references the need for additional fee pertaining to the platting of Lot 2 and its acreage not being included in the associated fee. If the reason to plat Lot 2 was motivated by needing to have Lots 1 & 2 as part of the land purchase from the overall land owner, this should be discussed further. The City wouldn't require that Lot 2 be platted at this time and if removed from the plat, the additional fee would not be required. Since the plat is presented at public hearing, verification on whether Lot 2 will be included or not is a pre -hearing item. Comment Number: 15 Comment Originated: 11/04/2016 11/04/2016: In addition to the question of the platting/fees of Lot 2, the other pre -hearing item is the showing of the sidewalk along Technology Parkway extending further north to cover the common area, and the sidewalk shown abutting the right-of-way (if the applicant is amenable to this). Page 2 of 12 Fort Collins November 04, 201 Shelley La Mastra Russell Mills Studios 141 S. College Ave, Suite 104 Fort Collins, CO 80524 RE: WilMarc Medical, PDP160033, Round Number 1 Community Development and Neighborhood Services 281 North College Avenue PO Box 580 Fort Collins. CO 80522 970,221.6750 970.224 6134 -fax fcgov. com/developmentreview Please see the following summary of comments from City staff and outside reviewing agencies for your submittal of the above referenced project. If you have questions about any comments, you may contact the individual commenter or direct your questions through the Project Planner, Pete Wray, at 970-221-6754 or pwray@fcgov.com. Comment Summary: Department: Engineering Development Review Contact: Marc Virata, 970-221-6567, mvirata(cDfcgov.com Topic: General Comment Number: 2 Comment Originated: 11/04/2016 11/04/2016: The civil plans are a little difficult to discern between proposed improvements, existing improvements, existing conditions, etc. Can different lineweights/linetypes be utilized to provide more distinction? Comment Number: 3 Comment Originated: 11/04/2016 11/04/2016: Please show the sidewalk along Technology Parkway extending 20 feet further north to complete the portion in front of the drainage/access/utility easement. Comment Number: 4 Comment Originated: 11/04/2016 11/04/2016: What is the intent of the plat creating Lot 2, but no associated development plan shown on the lot? Comment Number: 5 Comment Originated: 11/04/2016 11/04/2016: Sheet 5 on the civil set should provide more clarity as to what the included sections refer to and in general provide cross section information for Precision Drive and Technology Parkway abutting the property. Comment Number: 6 Comment Originated: 11/04/2016 11/04/2016: The indication on Sheet 4 Note 11 is that curb and gutter would need to be removed for the construction of the access ramps. It appears that the curb openings for the ramps were accommodated for however and there may not be a need to remove the curb and gutter (and no need for potential associated street cuts). Page 1 of 12