HomeMy WebLinkAboutFIRST ASSEMBLY OF GOD PUD - PRELIMINARY - 1-97 - CORRESPONDENCE - STREET RELATED DOCUMENTLocal Connector Street Costs
prepared by.Stan X Myers P.E.
Based on input from Western Mobile 4/28/97
Sidewalk 4.5 feet wide (per s.f.)
Curb & Gutter (2ft. pan) (per I.f.)
3-1/2inch Asphalt Pvmnt and 6 inch Base Course (per s.y.)
Total Street Improvements per I.f.
Cost per Street Extension (273 I.f.)
Total Estimated Cost for Both Extensions to Custer Drive
Unit
Cost per I.f.
Cost
of Roadway
$1.75
$15.75
$7.50
$15.00
$9.25
$32.89
$63.64
$17,373.42
$34,746.83
1
Starr A. Myers P.E.
1318 Tarryton Drive
Fort Collins, CO 80525
223-7973 (H) 482-5922 (W)
April 29, 1997
Mike Herzig
City of Fort Collins
Planning Office .
281 N. College Ave.
Fort Collins, Co 80521
Re: First. Assembly of Fort Collins - Cost of Offsite Roadway Improvements
Dear Mike:
Please find attached an estimate of the offsite roadway connections agreed to by First Assembly.
These are based on a flowline to flowline width of 36 feet. The extensions are based on a field
measured distance of 273 feet from the north property line of the church site to the south flowline
of Custer Drive (extended east as a collector).
I trust this will provide you with the documentation you requested.. If you have questions please
contact me.
Sincerely,
Stan A. Myers P.E.
cc: Frank Estep; FirstAssembly
Lowe Ross; The Larson Group