HomeMy WebLinkAboutMARTINEZ PUD - PRELIMINARY - 4-97 - CORRESPONDENCE -5. A copy of the comments received from Sheri Wamhoff of the Engineering
Department is attached to this letter. Red -lined Site and Utility Plans, with
additional information related to these comments, have been forwarded to M.
Torgerson Architects. A red -lined Landscape Plan, with additional information
related to these comments, has been forwarded to Jim Sell Design. Please
return these plans with your revisions.
You may contact Sheri at 221-6750 if you have questions about her comments.
As a reminder, please be aware of the following dates and deadlines to assure your
ability to stay on schedule for the April 28, 1997 Planning and Zoning Board hearing:
Plan revisions are due no later than the end of the working day, April 9, 1997*.
Please contact me for the number of folded revisions required for each
document.
* NO REVISIONS WILL BE REVIEWED AFTER THE ABOVE DEADLINE. IF REVISIONS
ARE NOT RECEIVED BY THIS DATE, THE ITEM WILL EITHER GO TO THE
PLANNING AND ZONING BOARD WITH A STAFF RECOMMENDATION BASED ON
THE ORIGINALLY SUBMITTED DOCUMENTS OR THE APPLICANT WILL HAVE THE
OPTION TO CONTINUE THE ITEM TO THE NEXT MONTHS BOARD AGENDA.
PMT's (photo reduction of Site Plan, Landscape Plan, and Building Elevations to
8.5" x 11"), rendering (one each colored full-size Site Plan na d/or Landscape Plan
and Building Elevations), and 8 folded copies of the final full-size Site Plan,
Landscape Plan, and Building Elevations revisions ( for the Planning and Zoning
Board members packets) are due on April 21, 1997.
Please contact me at 221-6750 if you have questions or concerns regarding these
comments or if you would like to schedule a meeting to discuss the comments.
Ve
erely,e Olt
Project Planner
cc: Sheri Wamhoff
Chris Maldonado
Stormwater Utility
Traffic Operations
Parks Planning
Mikal Torgerson
Shear Engineering
Jim Sell Design
Community Planning and Environmental Services
Current Planning
City of Fort Collins
March 27, 1997
Jim Leach
Wonderland Hill Development Company
745 Poplar -Avenue
Boulder, CO. 80304
Dear Jim,
The attached comments for the Martinez PUD - Preliminary have been received from
other City departments since my development review comment letter to you dated
March 18, 1997:
A copy of the comments received from Kathleen Reavis, the City's
Bicycle/Pedestrian Transportation Planner, is attached to this letter. A red -
lined Site Plan, with additional information related to these comments, has been
forwarded to M. Torgerson Architects. Please return this plan with your revisions.
You may contact Kathleen at 221-6608 if you have questions about her
comments.
2. A copy of the comments received from Roger Buffington of the
Water/Wastewater Department is attached to this letter. A red -lined Landscape
Plan, with additional information related to these comments, has been forwarded
to Jim Sell Design. Please return this plan with your revisions.
You may contact Roger at 221-6681 if you have questions about his comments.
3. A copy of the comments received from the Stormwater Utility is attached to this
letter.
You may contact Basil Harridan or Glen Schlueter at 221-6589 if you have
questions about the storm drainage comments.
4. Rick Richter of the Engineering Pavement Department stated that a final soils
report and a pavement design report will need to be submitted after underground
work is completed and streets are rough cut.