HomeMy WebLinkAboutPALMER RETAIL - MINOR SUBDIVISION - 8-97 - CORRESPONDENCE - REVISIONSC. The calculations for the retaining walls indicated on the Grading Plan have been
included at the end of Appendix I of the final Drainage and Erosion Control
Report. A copy of the detail is presented in the utility plans on detail sheet 6.
Design of the retaining walls were computed by the structural engineering firm for
this project, RNF Consultants.
d. The Larimer No. 2 Canal Ditch Company has signed an access agreement and has
signed on the Minor Subdivision Plat, utility plan title, grading and drainage study
and erosion control plans.
e. A standard ramp detail for vertical curb and gutter driveway entrance has been
included on detail sheet 6.
4. The 2 existing trees along the west side of the Canal will be saved and pruned as part of
this project, however it should be noted that these trees are in the ditch easement and are
subject to removal by the ditch company. Also the ditch company access will be from the
east side of the ditch on an existing dirt road.
5. We plan to attend the public hearing scheduled for Tuesday April 15, 1997 at 1:30 pm.
T
g ds
Vice -President
Vaught*Frye Architects
cc: Spiro Palmer
Westec
NAUGHT
FRYE
architects
April 1, 1997
Mr. Steve Olt
Community Planning
281 N. College Ave.
Fort Collins, CO 80522
Dear Steve,
Thank you for your comments on the Palmer Retail, Minor Subdivision. We would like to offer
the following response.
Public Service Company
a. Careful coordination between the City Light & Power and PSC gas will be
necessary along the south property boundary.
b. The PSC will locate the main gas line in the center of the 9 foot utility easement
east of Mitchell Drive. Coordination between the City Water Utility Department
will be necessary to place new waterline, fire water lines and sewer service across
this easement. Existing water service curb stops and valve boxes will be removed
in accordance with city guidelines. A New curb stop will be placed at the ease
edge of the 9 foot easement, the water meter box will be located immediately east
of the easement. These new and existing service is shown on the Horizontal
Control and Utility Plan.
2. Mapping Department
Utility companies will need to coordinate activities to provided services to the
building. If an easement is required following installation an easement will be
recorded afterwards.
3. Engineering Department
a. "Minor Subdivision' has been added to the utility plan title, the subdivision plat
title and all utility plan titles.
b. All utility patches on Mitchell Drive, indicated on the Utility and Horizontal
Control Plan, extend to the lip of the existing gutter and are perpendicular to the
gutter flowline.
land planning • architecture