Ted Shepard
Harmony Technology Park ODP
Page 4
Road sites will be reserved for high profile businesses.
23. Done
24. Done
25. Harmony Technology Park will consist primarily of large footprint
users. For example, the first phase of Celestica, which is the first
development within the park will be a 200,000SF building with the
potential for expansion to 600,000SF. Also, each of the large users
will be engaged in acitivities that require a secure campus. The site
requirements to accommodate these large users combined with the
need for secured entrances makes if difficult or impossible to provide
the 660' intersection spacing intervals.
26. Our understanding of the specific future use of the adjacent areas,
especially to the south and east is as yet undetermined. Additionally,
in a phone conversation with the transportation department,and with
our traffic consultant, it is unclear whether Cambridge will be
extended farther to the south. Because of these uncertainties, it is
difficult to commit to a specific treatment of these edges. I would like
to point out, however, that we have established specific setbacks,
screening and buffering requirements for landscaping within the
design guidelines that are currently being formulated by Hewlett
Packard.
This concludes our responses. We have attached 10 copies of the revised
ODP plan for your use. Please call if we need to meet to discuss or if you
need more prints.
Sincerely,
bha sign inc. b
Bruce A. ndee, ASLA
Principal
design
Ted Shepard
Harmony Technology Park ODP
Page 3
15. A 12" water line is now shown down the central spine road (
Technology Parkway) at this time. It is possible to revise the ODP at
a later date if it is decided that the east side of the site is a better
location.
16. We have located the future lift station at the southeast corner to
facilitate this
17. We have located the future lift station at the southeast corner to
facilitate this
18. The preliminary estimate of 3600 gallons per day per acre was used
for water and wastewater. This is equivalent to water usage of 6
units per acre which is consistent with the City of Fort Collins Water
and Wastewater Utility. More detailed flows will become available
with each new user.
19. Caution is noted.
20. Noted.
21. Thank you for pointing out the stormwater issues associated with
quantity, quality, and character of off site drainage release. The intent
is to obtain the required off site easement across the adjacent
property. This may not occur in time for the first development on the
property. If it is not obtained, a retention volume will be provided
within the park that meets the requirements for retention based on the
developed area. The detailed aspects of this issue will be addressed at
the time of the first PDP.
22. We have divided the ODP into the bubbles requested with the
exception of the convenience retail. This activity may or may not
occur depending on future businesses at the business park. The
location will be determined as the future of the business park tenants
becomes more clear. It is anticipated that the user will occupy an
interior site of approximately 3 acres. More prominent Harmony
design
Ted Shepard
Harmony Technology Park ODP
Page 2
like to have the flexibility to work with their site plan needs. We are
aware of the City standards and requirements and will coordinate
closely with the City during plan development.
4. Addressed by Matt Delich.
5. Addressed by Matt Delich.
6. Addressed by Matt Delich. Plan has been labeled.
7. A buffer zone has been indicated.
8. No response.
9. Addressed by Matt Delich.
10. Addressed by Matt Delich.
11. Addressed by Matt Delich.
12. Addressed by Matt Delich.. Each major street within the HTP will be
dedicated and will meet city standards for bike lanes and pedestrian
walks.
13. A Tranfort bus shelter will be located along CR9 ( Fossil Creek
Road) if appropriate however, Technology Parkway is anticipated to
be the major circulation roadway for this park. Technology Parkway
will be a major circulation roadway for employers with significant
employment on both sides of the roadway. For that reason we would
like to have the City consider the potential for a future Transfort stop
(or 2) along this roadway.
14. It is understood that this is the case and future developments in
design will follow the above advise.
design
June 27, 1997 LANDSCAPE ARCHITECTURE
URBAN DESIGN
Mr. Ted Shepard PLANNING
Senior Planner
City of Fort Collins Planning
281 N. College
Fort Collins, CO. 80522-0580
RE: Harmony Technology Park ODP
BHA DESIGN, INC.
2000 VERMONT
Dear Ted, FT. COLLINS, CO 80325
TEL 303 213-75]]
Thanks you for your letter of June 6, 1997 regarding planning and other staff 1^1 113 11'-3855
comments to the proposed ODP plan for the Harmony Technology Park
(HTP). Matt Delich has responded to the comments from transportation
regarding the TIS. I have added my two cents where it seemed appropriate to
elaborate. I have attached a copy of his response for your records. Outlined
below are responses to other comments. The comments are numbered
according to their number on your original letter.
Also, for the purposes of initiating discussion on a street name, CR9 has
been named Fossil Creek Road. Of course we understand there needs to be
dialogue, or this is the City's decision but, we would like to get a permanent
name for the road so that we can accurately indicate it in our covenants,
design standards, and master plan drawings.
Addressed by Matt Delich. The first phase of development (Celestica
will takes its phase one access off of CR 9. The access control plan
modification is beginning currently. It is anticipated that by the time
the second phase is ready to commence ( 1 '/s years +-), the permit
will have been addressed completely through CDOT.
The north/south street through the site is to be called Technology
Parkway. The ODP has been modified to reflect this change.
2. Addressed by Matt Delich.
3. Addressed by Matt Delich. The layout has been modified to indicate
a preliminary internal street system. Please keep in mind that each
user will have separate requirements and that most users are likely to
be large footprint users. To accommodate these large users we would