HomeMy WebLinkAboutBROOKFIELD SECOND FILING, TRACTS D & E - PDP/FDP - FDP150025 - CORRESPONDENCE - (3)Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson(cDfcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/04/2015
08/04/2015: Irrigation plans are required no later than at the time of building permit.
The irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of
the Land Use Code. Direct questions concerning irrigation requirements to Eric
Olson, at 221-6704 or eolson@fcgov.com
Department: Zoning
Contact: Ali van Deutekom, 970-416-2743, avandeutekom(o)fcgov.com
Topic: Site Plan
Comment Number: 1 Comment Originated: 10/28/2015
12/29/2015: Please show in plan view how the bike parking, trash and recycling
receptacles will lay out in the garage. Add a note to the site plan saying
"trash/recycling containers will be enclosed in each individual garage"
Page 5 of 5
Contact: Jesse Schlam, 970-218-2932, jschlam(a�fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 07/21/2015
12/10/2015: Resolved
11/02/2015: Per discussions with Stormwater Engineering, it is apparent these
slopes are going to require more significant BMPs, not just "as needed."
10/13/2015: Resolved
07/21/2015: Please submit, Erosion Control Plan with corrected redlines. Erosion
Control Report and Escrow Calc are acceptable. If you need clarification concerning
this section, or if there are any questions please contact Jesse Schlam
970-218-2932 or email @ jschlam@fcgov.com
Department: Technical Services
Contact: Jeff County, 970-221-6588, icounty(a�fcgov.com
Topic: Construction Drawings
Comment Number: 6 Comment Originated: 08/03/2015
12129/2015: There are some minor corrections to be made. See redlines.
10/22/2015: There are some minor corrections to be made. See redlines.
08/03/2015: Please make changes to the Benchmark Statement as shown. See
redlines.
Comment Number: 8 Comment Originated: 08/03/2015
12/29/2015: There are line over text issues. See redlines.
10/22/2015: There are line over text issues. See redlines.
08/03/2015: There are line over text issues. See redlines.
Comment Number: 9 Comment Originated: 08/03/2015
12/29/2015: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
10/22/2015: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
08/03/2015: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
Comment Number: 11 Comment Originated: 08/04/2015
12/29/2015: There are text over text issues. See redlines.
10/27/2015: There are text over text issues. See redlines.
08/04/2015: There are text over text issues. See redlines.
Topic: Site Plan
Comment Number: 24 Comment Originated: 08/04/2015
12/29/2015: There are line over text issues. See redlines.
10/22/2015: There are line over text issues. See redlines.
08/04/2015: There are line over text issues. See redlines.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson(a)fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 12/29/2015
12/29/2015: The typical sections are 30 ft wide roadways with parking on both sides
which leaves limited drive aisle space. If upon construction and occupancy function
of the roadway becomes problematic with complaints, parking may be restricted to
only one side.
Page 4 of 5
Comment Number: 5 Comment Originated: 12/14/2015
12/14/2015: MARKING
The proposed fire lane signage plan appears appropriate except for two locations.
The eastern loop drive, surrounding Bldg. 36 should have one sign located
approximately 15' back from both, north and south street connection. Fire lane
signage shall be placed at 75' intervals along the path of fire access and therefore
another sign is warranted farther to the east at each location.
Comment Number: 6 Comment Originated: 12/14/2015
12/14/2015: ADDRESSING & WAYFINDING
The project team is welcome to resolve this issue with Tech Services Dept.
however at some point the plan shall be reviewed and approved by the fire
department prior to implementation.
Department: Stormwater Engineering
Contact: Dan Mogen, , dmogen(a)fcgov.com
Topic: General
Comment Number: 4 Comment Originated: 08/04/2015
11/02/2015: Dry wells and grass swales are not considered to be LID. Please
revise to show the LID requirements are met using techniques accepted by the City
of Fort Collins.
08/04/2015: Please provide LID table showing requirements and how they are met.
Sample table available upon request by emailing dmogen@fcgov.com.
Comment Number: 5 Comment Originated: 08/04/2015
11/02/2015: Detail D-54 is seen on Sheet D7 and Paver Sections are seen on
Sheet SG1. Please review/revise for consistency between the details and also call
out media types, depths, etc. that are specific to this project.
08/04/2015: Please review City Paver Detail D-54 and modify paver sections shown
on sheet SG1 appropriately.
Comment Number: 6 Comment Originated: 08/04/2015
11/02/2015: Please revise cross section to be consistent with that shown in City
Detail D-53.
08/04/2015: Please provide detail for bio/grass swale (called out differently in
different locations).
Comment Number: 8
Comment Originated: 10/28/2015
11/02/2015: Please consult with the Erosion Control Inspector to determine BMPs
required to stabilize the steep slopes (>4:1) on the east side of the project and
discuss concerns with establishing vegetation long-term.
Comment Number: 9
Comment Originated: 11/02/2015
11/02/2015: For the rain garden, please provide:
- sizing calculations.
- easement for the basin area.
- verification that rain garden is in compliance with statewide drain time
requirements.
- media types and depths consistent with City Detail D-53. Biorention Sand Media
Specifications are available here
(http://www.fcgov. com/utilities/img/site_specific/uploads/Bioretention_Sand_Media_
S pecs. pdf) .
Comment Number: 10
Comment Originated: 11/02/2015
11/02/2015: Please expand the drainage report write up to provide a more detailed
description of the proposed drainage as well as the treatment methods being used.
It would also be helpful to call out items including inlets, Snouts, dry wells, manhole
numbers, etc on the utility plan, drainage plan, or other such plan.
Page 3 of 5
Department: Environmental Planning
Contact: Rebecca Everette, 970-416-2625, reverette(cDfcgov.com
Topic: General
Comment Number: 18
Comment Originated: 12/29/2015
12/29/2015: The top of bank line does not appear to be in the correct location. I
believe the top of bank is what is currently labeled as "Fossil Creek Ditch." This label
can be updated to read "Fossil Creek Ditch Top of Bank" instead. The 50' buffer
along the ditch is measured from the top of bank.
Comment Number: 19 Comment Originated: 12/29/2015
12/29/2015: It would be simpler for maintenance and inspections of the Natural
Habitat Buffer Zone if it followed the east edge of the sidewalk, rather than the strict
50' buffer. Let's discuss whether it makes sense to adjust the boundary of the
buffer.
Department: Forestry ,�4wj
Contact: Tim Buchanan, 970-221-6361, tbuchanan(a)fcgov.com
Topic: Landscape Plans
Comment Number: 3
Comment Originated: 08/07/2015
11/04/2015: CONTINUED
Canopy shade trees used as street trees need to be positioned 40 feet from street
lights. Ornamental trees can be 15 feet from lights. Review current placement of
trees near lights and provide the required separation.
08/07/2015:
Show the actual location of street lights and stop signs and place street trees away
to LUC standards.
Street lights: 40 feet separation for shade trees and 15 feet for ornamental trees
Stop signs: 20 feet separation for trees
Department: Light And Power
Contact: Coy Althoff, , CAlthoff(a)fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 08/06/2015
08/06/2015: Light & Power has existing electric facilities along the N. side of
Precision Dr. between Brookfield and Northern Lights; and as far North as the -rlo dint
existing clubhouse. Electric would need to be extended North along Brookfield and F y
along Northern Lights to feed this development. Any modification or relocation to
existing electric facilities will be at the applicants expense.
Comment Number: 2
Comment Originated: 08/06/2015
08/06/2015: Electric Capacity Fee, Building Site charges and any system
modification charges necessary will apply to this development.
Comment Number: 7
Comment Originated: 10/29/2015
10/29/2015: Please contact Light & Power Engineering if you have any questions at
221-6700. Please reference our policies, development charge processes, and use
our fee estimator at
http://www.fcgov.com/utilities/business/builders-and-developers.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler(a�poudre-fire.org
Topic: General
Page 2 of 5
City of
Fort Collins Ao 4 2 ,�
LO-OJ'}'' December 30, 2015
Morningside Land Company, LLC
1170 W Ash St Ste 100
Windsor. CO 80550
RE: Brookfield Second Filing Tracts D and E, FDP150025, Round Number 3
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins. CO 80522
970.221.6750
970.224.6134 - fax
fcgov.com/deve/opmentrev/ew
Please see the following summary of comments from City staff and outside reviewing agencies for
your submittal of the above referenced project. If you have questions about any comments, you may
contact the individual commenter or direct your questions through the Project Planner, Rebecca
Everette, at 970-416-2625 or reverette@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Jason Holland, 970-224-6126, jholland(a)fcgov.com
Topic: General
Comment Number: 9 Comment Originated: 08/02/2015
Where are accessible units located and how do you get from the HC parking places
to an accessible unit via a sidewalk? Am 1., (yt r�� ��(� �� 4C SPKQC
Contact: Rebecca Everette, 970-416-2625, reverette(cDfcgov.com huh- -w 4 Bp P�
Topic: Building Elevations
Comment Number: 18 Comment Originated: 12/29/2015
12/29/2015: See elevations for one minor redline.
Department: Engineering Development Review
Contact: Sheri Langenberger, 970-221-6573, slangenbergerofcgov.com
Topic: General
Comment Number: 28
Comment Originated: 12/29/2015
12/29/2015: Make sure that the ped ramp on the east side of Northern Lights lines
up with the ramp at the corner opposite of it. With the change to the directional
ramps at the corner this one doesn't line up right now.
Comment Number: 29
Comment Originated: 12/29/2015
12/29/2015: Sheet G4 - the match line is over some elevations. Either mask or
make sure the numbers are rotated so that they are readable.
Comment Number: 30
Comment Originated: 12/29/2015
12/29/2015: Forebay detail. This looks like it needs somemore information. How
does the concrete cover work - base it sits on? Is there a handle? Rebar in this
cover? Standard cover ordered somewhere or built?