Pressure Calculation Worksheet
Complete this form for the most pressure -demanding lateral, and submit it to -the City with the
irrigation plan. You might want to make copies of this form so you have an adequate supply
y
''
a. Pressure available at point -of -connection
a'•.
_{,' '-' it d:'
tJ(.� o.;•
. u
1.
6. Pressure loss through the meter
psi
;.
c. Pressure foss through backflow prevention device -
psi
d. Pressure loss in mainline pipe from backflow prevention
device to remote control valve -
psi
e. Pressure foss through remote control valve -
psi
f. Pressure loss in lateral pipe from remote control valve
to most remote sprinkler -
psi
g. Elevation change from point -of -connection to most remote
sprinkler (0.43 psi per foot of elevation):
pressure loss - psi
or
pressure gain + psi
h. Miscellaneous losses through other valves, strainers, etc.
(in some cases this will not be applicable) - psi
i. Total possible pressure loss (add b through h) - psi
i. Remaining pressure (subtract i from a) psi
j. Minimum pressure required at sprinkler psi
k. Difference (Subtract j from i. If the value is negative,
a booster pump may be needed. If the value is more than
+15 psi, pressure reduction may be necessary for this
zone, and/or other zones.) psi .
ATTACHMENT B,,
Instructions for ,completing an Annual Water. Use ;Chart
1. Use the Water Use Chart below, including notes, as an example of what the City of Fort Collins requires to be
included on an irrigation plan +tt r �� r + w F` c y, L j
2. The discharge figures for each lateral can be*61ci late'd"by summiniif the appropriate discharge values in the N
manufacturer's catalogs for the spec fled sprinklers, bubblers or�dnp emitters 2W.
. .w..,"., _�ar•:ttts.".C� `fit;— ,.,..,^'`•p.._"F—.= •>r.•—c; .r Y a, '` s ,' d{f•4 ttf' .i 'S}r[ ....r b`tF a .r., �✓J� �v,t 'fir" �'.
IT
3. Irrigated areas for each lateral can be calculated using a scale and/or. planete, This should be a , best
estimate; splitting areas betweenzones'as necessary. For�drp irrigation, ttie.irrigated area shout proxunate
the area actually wetted by the 6mitters.As a,gene% guideluie,;you can_use one square footfor each peren.n 1 .1
four squazerfeet for�each sthrub az►daweI a square feet fo ueach_tree i r
4. To calculate precipitation.rate.(inches per hour), multiply the discharge (gallons per minute) times the
conversion factor ofy 96.26, and thendrvide by -the irrigated area (square feet).
I}71�.«ni,x jt9eS fi.'i .f Y-]F .
5. The average annuai'depth'of irrigaU6 ttan 6e determined by iefemng"to'Attdclimenl A
6. The annual volume of water (gallons) can be determined by multiplying the irrigated_area (square feet) by the
average annual depth of irrigation (inches), and then dividingby the conversion factor 1 6 .
r iSiJi .-,.i. �':r an '.Y-a.•� `.'^; ''� Ti i.7i. F", a.....` r sX1!!liiT,dr ,:' ,,
7. The annual cost for the wfl.ater is deteimmed by multiplying the volume of water by the applicable water, rate. It
is the responsibility of thdirrigaiicn designer to4find out which water district serves the project, and +to make ,
sure'the current water rate is used'in the calculation. The water districts are: City of Fort Collins, 221-6681;
_. 6 .
ELCO, 493-2044;'and' Fort Collins -Loveland, 226-3104.
:� ANNUAL 'WATER USE CHART (an example) 5 -' h _
xxx
i
..................................................::.:............. :
i. .
Al ... _..40.0 ;12.100 :: • ._ 0.32.._ _.. _..16 120,700 $130
'-A2 _._.:"42.0 •:4.13,050 .0.31 _.1-430,150',—
A3. -... ...._48.0 _ ..;_..13,300 __ . _ _.._,_0.35 _:.. _._—.16 ' ..132,650 .-. • ., 143 ,
r.A4_ 25.0_.:_'w _,.__11500'..._..: .__.1.60`:._.__.:_ .___:.-16 i-- I5,000 k' 16' `}
A5 . _. »w 46.0 ,,.,. .:2,850 �, G ...•,1.55, ...n .. 1
�-28,400
A6. —i.. _5 5 . �. _M 490. 1.08 _. _. _g td 2 450 t �" 3 r
,.... ...- �. _ ..wr.. .i u. , .'+ b .�..
c , 4.t i. -+a'[ .�".` 7• } ! 1. J r _ a't.J _! 6.:1,. ,t �., h,4aT.
Notes: "'"--._..�__._�.__.� _,U,— ���.._._....�._...._ .._....,:�,_ .�.�_,:-... _..__._W_ ._.. _ ,,.•
1. This table±assumes the _City of Fort Coll ins.1996•water rate. of $1'08 per 1,000 gallons.:'_:
2. The water use data corresponds with the June 3, 1996 landscape plan by Acme Landscaping.,
.. r f.:y !. •t � ..e.� ::iS: n r •:%.! �: )S,' ..:.,. .. ?� ':�:.� :i iT Z) Tf. ., Lt i,.. lr.[,J:? .,: (I ,:i ..
r
13. A pressure reducing valve shall be installed on the -mainline, or as a feature of the remote
control valves, if it is anticipated that the operating pressure at any spray sprinkler, minus the
maximum recommended pressure for that particular sprinkler, is equal to 20 psi or more.
14. A rain sensor shall be installed with each irrigation system, in order to interrupt irrigation in the
event ofa significant rainfall'
15. When drip irrigation is used, emitter discharges within any single zone shall not vary by more
than 5%. If necessary because of long runs and/or elevation _UT
changes, prenure-comperisatffig
emitters shall Fi j
I qopi,
16. Remote control valves shill liiVei'how control'stems.
Sprinkler spacing
For both cases below, the radius of throw is defined as the value sh6wnis'in the manufacturer's
1,f.11. .,- sprinkler: specifications for the specific de-si'gh'op'e-m-tingp'r'e"s's'tire orthesprinkler.
17. With a square pattern layout, sprinklers shall be spaced no further apart than 1.0 times the
manufacturer's publish6dridi�u's-"6ftlii6w:.-� ;".'!---
Z.L
18. With a triangular spacing layout, sprinklers shall be spaced no further apart than 1.1 times the
manufacturer's publishedradius of throw..
Hydraulic considerations
19. Where Kmtiic'ky -Bluegrass 'and/or Perennial Ryegrass is used for turfgrin, the tap Sii6 shall be
sufficiently sized to deliver 0.25 inches of irrigation water over the turf9iUss area within an 8-
hour period. Where Turf -type Tall Fescue is used, the tap size shall be sufficiently sized to
deliver 0.20 inches of irrigation water over the turfgrass area withiri'ain'4-houi period. For'
special circumstances, the City may allow exceptions to this standard. (See Attachment Q
20. The maximum system discharge shall be lessithan or equal to the'rhaxin1din *allowable, relative
to the meter size, as determined by the City of Fort Collins Water Utilities. This shall be as
follows: 3/4" - 10 gpm,-I" -25 16m, 1-11/2" = 50 gpffi, 2"780 6T, 3" -160 gpm. Tlie's-e
maximum discharges assume a disk -type meter. In certain cases of irrigation -only taps that are
1-1/211 or larger, turbine meters are allowed, which have somewhat higher maximum discharge
limits. Contact the Water Utilities for more information..
21. The maximum velocities shall be less than or equal to 5.0 feet per second.for mainline pipe and
less than or equal to 7.5 feet per second for lateral pipe. (See AttachmentC
22. The irrigation system'shall be designi6d such'that the point-ot-connection design pressure,
minus the possible system pressure losses, is greater than or equal to the design s rinkler,y
operating pressure.(See Attd&hment D).SS
"
23. The lateral pipe shall be sized such that there is less than or equal to a 10% variation between,
the highest and lowest sprinkler operating. pressures on a zone
LM
A-
:(;I- 4Y
3 ..: City of Fort Collins
IRRIGATION SYSTEM STANDARDS:
for Water Conservation
10194
,, f..., - ,. « '" ! � t. r.l � is }r. r..,�:• `,: L � �LI.«.�. � >...t: r
1ation
�
Irri Plan
9 � }
..,.,:> •.. �;.�
1. If areas of planting are extensive,the installation of an underground irrigation system shall
/ f Obit f It ,r ,r} ,yqJ, ,+ .1b c 3 �f.
N
toto�.the
andapproved byr
Ar required and an irrigation planshall be submitted City,.pno,the j�,ixt ti'
If building w
issuance of a final certificate of occupancy. no permit is required,,the.plan�isidue
prior to commencing construction. If the water requirements of the plants are low enough to be'.
.t
F-
met with natural precipitation, and if a means of temporary irrigation is available to establish• .
"'t14. �• t}Ji .V ;3 _ I ,.
plants, the City may waive the requirement for, an underground urigation,system
:zthe .When
required, theirrigationplan shall be accurate: and clear, drawn to the same scale as the„z
associated landscape plan, and include the following:, } t'
...t<_�.:..0 ,.,........ ....., ..., r l,j .... :'e.• : u3. n "51� t .., f!lf..'•fSE +.i1 1f �.n ��.i!.'
a. an annual Water Use Chart that includes:.the square footage of irrigation zones,,,_,,,,,:,
lateral precipitation rates (inches/hour), and seasonal water use and cost. The 'seasonal
water use data shall reflect the water requirements of the plants identified in the
landscape plan associated with the irrigation plan. The irrigation plan shall'reference
the specific landscape plan, with its date and the designer's name. "(See Attachment B)
b. a general note stating the point -of -connection design pressure and the peak flow. For
' example, the system design assumes a minimum dynamic pressure for the irrigation
system of 75 psi at a maximum discharge of 50 gpm. at the 17-112-inch `tap insd point -
of -connection. The irrigation contractor shall verb pressure and, flow on the site
prior to construction.
c. the design criteria to assist the installer with field adjustments,.in a general note oHn
the legend. The criteria shall include the sprinkler and nozzle specifications, the
sprinkler discharge at the design operating pressure, and the maximum distance
between sprinklers.
ld adjustment or redesign `of this irrigation system
d. a general note stating that, Any fie
' must conform to the City'of Fort Collins Irrigation Standards.
e. in the specifications, or as a general note, a requirement for the contractor. installing
the system to provide the owner with as -built drawings after installation is complete.
f. details of the installation method for bubblers or dri emitters, when the irrigation
design includes these components. It must also include the number and discharge rate
of emitters or bubblers per type of, plant material.
. ... .........
Irrigation methods and layout w '
.a.,. _..at :C..�.tv_fat.<. r... .•1 A?-,,..:>i„r .1j,r..:i.: �.-F' - ,f:: ,. *:: ay".. sti};.
...... !1 iff+i .> ,:f. nRr .. t t••, .t :: (i� 1,:..1 [ `:f r., ; 1 'j!. t. :'. 7rL�n. t.fl ' .I',.
2. Where untreated, raw water is available from a nearby irrigation ditch or lake, it should be
considered as a possible water source.
3. As much as practical, plants with dissimilar water requirements shall not be irrigated on the
same zone. For example, turfgrass areas should be on separate zones from planting beds. (See
Attachment A for water requirements of specific plants)
-
Cf
City of Fort Collins _
Water-Cohservation'Standards for
LANDSCAPING and IRRIGATION SYSTEMS
-= General Information
7/96
vd !f1-,;( .qqn hap s if:3"1 5ib3 ,,dl;lflilino t)IOn ffi€-a" > u l t :Ti. iljrti^ fo tr'
rri'i`'- t",t11;ri R �h. 73f°i`?fJ.�...9'l� ,,tY3'ri�. TN:r`?iI% t'r 'Si�...9 fk:;'!F;.r"":a'C.4'149'a�•�"+ ,1.T��.1.�.iir ';:�..G -'i. +:r 7.,,
What are the water conservation standards?
There are two separate standards for water conservation (1) Landscaping and' t�w ,
m.
x� -.J •3 t...tGt t.. t,3 !.' � i ,.+ x! •.e.
(2) Irrigation Systes.The standards for Lm ]Landscaping promote the stallatioii of y
. •s •..: �., .,,r\L,�aatea'. U.`• l..••. c. u.i. ..c. d•..�.n+.t.y uur .L.. $1:; �'JI7�w 1'
landscapes that require less water: The standards for Irrigation Systems ensure irrigation
systems are designed to apply water efficiently to meet the needs of the landscape.
What projects are subject to the standards? ..,...a f:;:. -. i"; :.•.:i ,
All projects within the city limits that are required to, submit a landscape plan to the City
as part of the development review process. In general, this includes all` commercial,
industrial, institutional, and multi -family projects. Duplexes are also included when they
are part of a planned unit development. The standards apply to common. areas of single_ -
family developments; but do'not apply to single-family residential' lots.
What do I have to do tocomply with the Landscaping standards?
Submit a landscape plan as part of the development review process. The plan must meet
the requirements in the document, Landscaping Standards for Water Conservation before
the development plan is approved. „
What do 1 have to do to comply with the Irrigation System standards?
Submit an irrigation plan as part of the construction permit review process. The plan must '
meet the requirements spelled out in the document, Irrigation System Standards for
Water ConservatiorL.T he City will review the plan, and then inspect the system after
installation. The irrigation plan and system inspection must be approved by the City `
before a certificate of occupancy is issued. If construction of the irrigation system is
delayed until after construction is completed, a certificate of occupancy can be issued '
only with an acceptable bond deposited with the City.
How strict are the1 standards?
The standards most important to water conservation are mandatoryrequirements,
identified with the word shall.. Other standards are more flexible, they use the phrases -, •:,> „,
should or to the extent practical. These are enforced on a case -by -case basis.
d t.fix- ie:i;!,, fiZ S.. 73/1 '.±i'cs [I, :!i2`lcJlt (...,'. .i ',..y•,;t [ ... _.", (:. r:e
Where. do I get morel information? : _'Art;
Call the Water Utilities at 221-6681.°f 'f:
Citv of Fort Collins
Project Name:
Date of Review:
Reviewed By:
Water Ut. es
Stormwater • Water • Wastewater
Water Conservation Standards for Landscapes
COMMENT SHEET
Ftetyde12 C6V4J'V
12- ISr-�"1
Laurie D'Audney, Utility Education Specialist, 221-6877
I have reviewed this landscape plan and it does not comply with the standards marked below.
Landscape Plan Requirements
❑ 1. The landscape plan shall contain a general note calling for the review and approval by the City .
of Fort Collins of any required landscape irrigation system, prior to the issuance of a Building
Permit.
2. The landscape plan shall include the total area (in square feet) for each landscape category.
Landscape categories are distinguished by their water requirements and intended maintenance
level. Examples of possible categories include, but are not limited to, high water turfgrass, low
water turfgrass, low water planting beds, moderate water planting beds, and non -plant areas
(paved areas, etc.).
Sze_
❑ 3. Mulches shall be used for planting beds. The mulch can be either organic or inorganic, and
shall be applied to a minimum depth of 3 inches. In order to prevent large expanses of barren
mulch, there shall be a minimum plant cover of 50 percent within 5 years of planting.
(more)
P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6681
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: December 17, 1997 TO: Water Consery
PROJECT: #36-97 Advantage Center
Type I (LUC) PDP/FC
All comments must be received by Leanne Harter no later than the staff
review meeting:
Wednesday, December 14, 1998
A
Date: /2 -too —
CHECK ME )F YOU WISH TO RECEIVE COPIES OF REVISIONS
PIS _ Site . Dra V Report _ Oler
_ Utility _ Reim Utility _lands*
City of Fort Collins
JAN. -05' 98NON1 10:08 124 W MAPIOL1A FT. CL TELAIF0224 111 F. 001
PROJECT
COMMENT SHEET
Current Planning
DATE: December 17, 1997 TO: U S West
PROJECT: #36-97 Advantage Center
Type I (LUC) PDP/FC
All comments must be received by Leanne Barter no latex than the staff
review meeting:
Wednesda ,-Beeember 4,1998
Review of these plans should not be constfued as a commitment that telephone facilities sufficient to
serve this project are presently available. U S WEST will provide telephone service in accordance with
Via rates and tariffs on file with the Colorado Public Utilities Commission.
The owner is responsible for provision of all conduk ditch crossings, and street crossings for telephone
balities within the project. The owner also provides terminal room space (usually 8' X 4') and power for
the telephone terminal, generally in a utility room. Contact the U S WEST engineer for conduit
specifications for the telephone entrance cable.
All rabaation of ebsting telephone facilities required by these plans will be paid for by the developer.
Susan Myers Peterson
Capacity Provisioning Field Engineer
970-224-7473
smpetelCuswest.com
Dane:
CM BE g YOU M M RBM
§ ft x3b
= (F )MM
10. The report needs to include PS and EFF numbers and a discussion of all BMP's
proposed for use. How is the swale being taken care of? Reseed/mulch? When?
RESPONSE:
11. The plans need a legend, standard erosion control notes, and BMP details.
RESPONSE:
12. How/when do you work a gravel/sediment tap on the area inlet in the
pond/turnaround?
RESPONSE:
PROJECT DEC 111997
COMMENT SHEET.,
City of Fort Collins
Current Planning
DATE: December 17, 1997 TO: Stormwater
PROJECT: #36-97 Advantage Center
Type I (LUC) PDP/FC
All comments must be received by Leanne Harter no later than the staff
review meeting:
Wednesday, December 14,1998
1. Please include a plat with all drainage and utility easements delineated. Please obtain
drainage easements for all offsite drainage.. Temporary construction easements will also
be needed. Please show all ROW's on the plan.
RESPONSE:
2. At conceptual review, it was stated that the outfall located in the southeast corner of
the State Farm site was a limitation. Since the flow from the detention pond is being
routed to that site, it is pertinent that documentation be provided which shows adequate
drainage capacity on the State Farm site.
RESPONSE:
3. When computing the time of concentration for the historic flows, the equation was not
correct. Please adjust and make appropriate changes throughout the report.
RESPONSE:
Date:
L=nrr, 1-lorr4 r
ma HERE IF YOU WISH To RECEIVE COPIES OF REVISIONS yyr}i Assacla+aS
✓�Pl{� ''8e — Ok
✓U(lll� " � Ubky _ L416* Citv of Fort Collins
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: December 17, 1997 TO: PFA
PROJECT: #36-97 Advantage Center
Type I (LUC) PDP/FC
All comments must be received by Leanne Harter no later than the staff
review meeting:
Wednesday, December 14,1998
1. Signage is required to designate fire lane(s) and emergency access turn around. Signs
shall be spaced 30 feet apart.
2. LOCAL Amendment (table 38B - Uniform Building Code)
Proposed building exceeds 5,000 square feet for type V construction and must be fire
contained, construction type upgraded, or fire sprinklered.
3. Fire hydrant as shown meets PFA requirements.
Date: / 2- Z 3- 9 7
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS
_ PW _ Site _ ftW Rep_ Offer
_ Utility _ Redin Ugly _ Iaaaw
South Fort Collins
Sanitation District
December 23, 1997
Ms. Leanne Harter, Planner
City of Fort Collins
P.O. Box 580 .
Fort Collins, CO 80525
RE: #36-97 Advantage Center
Dear Ms. Harter,
The Fort Collins - Loveland Water District and the South Fort Collins Sanitation District have reviewed
the above mentioned project, received December 19, 1997, and submit the following comments:
The existing 4-inch water line is to be shown. The line is generally located 10 feet west of the
existing sanitary sewer line. A note to pothole the existing water line to verify the location is to be
included on the drawings.
The detention pond may have to be shifted to the west depending on the location of the existing
water line.
The District does not allow trees or other landscaping within the District's easement.
Please do not hesitate to contact me at 226-3104, ext. 14, if you have any questions or require additional
information.
Respectfully,
Uv
Mr. T�y W. Farrill
Systems Engineer
xc: Mr. Michael D. DiTullio, District Manager
PROJECT
COMMENT SHEET
City of Fort Collins
Current
DATE: 19 January, 1998 DEPT: Engineering
PROJECT: Advantage Center #36-97
ENGINEER: Michael Coley
Utility Plans
Sheet 1:
89 Plat must be included with Utility Plans.
Sheet 2:
Plat:
39 Street frontage does not appear to be in accordance with current City standards.
X Sidewalk should be with in ROW or public access easement.
39 All stormwater detention must be within a drainage & detention easement.
39 Offsite (temporary) construction easements seem to be necessary in several locations.
39 Show and label all easements on overall utility plan.
39 The width of the sidewalk connection to the public walk is inadequate.
89 Parking setback is not in accordance with City standards (see Table 5).
X Parking stalls must be 19' deep when no overhang is provided.
39 Show existing features within 150' of project boundaries.
39 Indicate ROW width of South College Ave. Service Road.
39 Plat needs two ties to section corners.
N Offsite drainage & detention easement by separate document.
X Label adjoining property.
X Change signature block for Planning Director approval as shown on redline plat.
*** See redline plans for additional comments***
Date: lZ 1 9 / 98 Signature:
PLEASE SEND COPIES OF MARKED REVISIONS:
® SITE
® UTILITY
❑ LANDSCAPE
936-97 Advantage Center
Type I (LUC) PDP/FC
Section 504 of the 1991 edition of the Uniform Building Code as adopted by the City of Fort
Collins requires that exterior walls of B2 buildings located closer than 10 feet from a property line
be of one -hour fire -resistive construction. No openings are allowed in such exterior walls located
less than 5 feet from the property line. A parapet extending 30-inches above the roof surface is
required unless the structure complies with the exceptions to Section 1710. Projections, such as
cornices, eave overhangs or exterior balconies shall not extend over the property line and must
comply with UBC Sections 1710 and 504.
Buildings shall be designed to comply with the Fort Collins Nonresidential Energy Code
(ASBRAE 90.1 with local amendments).
The City is currently reviewing the 1997 editions of the Uniform codes for adoption. The process
is slated for completion in mid-1998. Please contact the building inspection office for current
code editions and standards.
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: December 17, 1997 TO: Building Inspec
PROJECT: #36-97 Advantage Center
Type I (LUC) PDP/FC
All comments must be received by Leanne Harter no later than the staff
review meeting:
Wednesday, December 14, 1998
The site shall be accessible to persons with disabilities in accordance with Uniform Building Code
Section 3103 and UBC Appendix Section 3106. Provide a designated and marked "accessible
route of travel" among all the buildings on the site and building exits and entrances and the public
way (public sidewalk). Accessible routes shall comply with ANSI A117.1-1992 with running
slopes no greater than 1:20 and cross slopes no steeper than 1:50. Where routes cross lanes for
vehicle traffic, they shall be designated and marked as a cross walk. Provide parking and signs
per Appendix Section 3107. Parking and access aisles shall comply with ANSI A117.1-1992 with
slopes no greater than 1:50 in any direction.
Buildings which exceed 5000 square feet in area must be equipped with an automatic fire
suppression system or be compartmentalization by fire -resistive construction as required by
Section 3802, Uniform Building Code as amended by the City of Fort Collins.
Storage or use of hazardous materials must be in compliance with the Fire Code and Chapter 9 of
the 1991 Uniform Building Code as adopted by the City of Fort Collins. A list of such materials
with quantities and classifications should be submitted for review at the time of building permit
application.
More...
Date: JAIK�b
CM HERE T YOU WISH TO RECEIVE COPIES OF REVISIONS
_ PW _ Sid _ Report _ Mea
_ Utility _ Redline UElity _ Iandsape
9
o) Please show all rooftop mechanical equipment and how it is to be
screened. In addition, please show any lighting on the building.
p) What color "green"? Could you please provide samples of the colors
to get a better feel of what is proposed?
q) The pedestrian crossing should be defined using techniques outlined
in Section 3.2.2(C )(5)(b) of the Land Use Code.
r) Please see the attached redlines plans for additional comments.
This completes the review comments at this time. Additional comments may be
forthcoming as the various departments and reviewing agencies continue to
review this request.
Please provide a written response to each of the above stated comments with
the submittal of plan revisions. Please contact me at 221-6750 if you have any
questions or concerns that are related to the comments. If you would like to
schedule a meeting, please call me as soon as possible.
Revisions may be submitted at any time. With the submittal of revisions, please
include the enclosed redlined plans. Please contact me for the number of
revisions required.
yB,essAtt Regards, `` �
C�-1G�� wu, !/
Leanne A. Harter, AICP
Project Planner
xc: Mike Coley
Stormwater Utility
file/Project Planner
b) The sidewalk along the frontage road should be detached, and street
trees planted according to the requirements of the Land Use Code.
c) Please add Note #10 stating that the bicycle parking will be }
permanently affixed to the ground and detailing from what it will be
constructed.
d) In the land use table, please include the following information: amount
of landscaping in the parking lot (the Land Use Code requires a
minimum of 6% parking lot interior landscaping; the number of parking
spaces; the number of employees; and the maximum height of the
building.
e) On the signature blocks, please remove (Type 1 Review) under the
administrative hearing officer certification and remove (Site Plans)
under the owner's certification.
f) Please include the following information in a "Plant Material Schedule":
common and botanical names, symbols, sizes (refer to Section
3.2.1(D)(4) for sizes), quantities, and method of transplant.
g) Please show the zoning on the vicinity map and include a north arrow.
h) Is there an area for trash collection? This should be designed to allow
for the possibility of recycling. Please show the location of the trash
collection area on the site and landscape plans and provide a detail of
it.
i) Please provide a detail of the fence.
j) Can ornamental trees or coniferous trees be added along the north
property line to help provide a break between the drive aisle and the
building?
k) Is there a sidewalk connection at the north of the turn -around?
1) Please add trees (evergreen, shade or ornamental) along the east
property line (immediately to the west of the fence.) In addition, carry
through the five foot buffer indicated by the zoning department along
the entire east property line.
m) Please show the bicycle parking on the landscape plan.
n) On the south elevation, it appears as if there are steps where the
handicap accessible route follows? Please clarify this issue.
a) Signage is required to designate fire lane(s) and emergency access
turn around. Signs shall be spaced 30 feet apart.
b) LOCAL Amendment (table 38B-Uniform Building Code) requires that
as the proposed building exceeds 5,000 square feet for type V
construction, it must be fire contained, construction type upgraded, or
fire sprinklered.
c) The fire hydrant as shown meets PFA requirements.
6. Comments from the Stormwater Utility are attached.
7. Comments from US West are attached.
8. Comments from Water Conservation are attached..
9. The Zoning Department offered the following comments:
a) Please show the building envelope and distances to the property lines.
b) Parking lots with six (6) or more spaces are required to be screened
from adjacent uses. The landscape plan shows nothing to block the
view of the parking from the use located to the south. There also
doesn't appear to be enough room. There is a 12' easement but that
is no actually part of the property.
c) Please omit last phrase in #7 of the plant notes as it doesn't apply.
d) There is a rear five (6) foot landscape buffer required on the east
property line adjacent to the parking/tum-a-round.
e) Please list building dimensions.
f) Article 3.5(D)(2)(a)(3) of the Land Use Code requires similar design
characteristics on the north side of the building as shown on the south
side. The could probably be accomplished by adding gable or
dormers as well as similar fascia treatments.
g) The rear stairway must be inside the building envelope.
10. The Current Planning Department offered the following comments:
a) Where is the main entrance? The bicycle parking should be located
near the main entrance, and designed according to the requirements
of the Land Use Code.
by fire -resistive constructions as required by Section 3802, Uniform
Building Code as amended by the City of Fort Collins.
c) Storage or use of hazardous materials must be in compliance with the
Fire Code and Chapter 9 of the 1991 Uniform Building Code as
adopted by the City of Fort Collins. A list of such materials with
quantities and classifications should be submitted for review at the
time of building permit application.
d) Section 504 of the 1991 edition of the Uniform Building Code as
adopted by the City of Fort Collins requires that exterior walls of B2
buildings located closer than 10 feet from a property line be of on -hour
fire -resistive construction. No openings are allowed in such exterior
walls located less than 5 feet from the property line. A parapet
extending 30-inches above the roof surface is required unless the
structure complies with the exceptions to Section 1710. Projections,
such as cornices, eave overhangs or exterior, balconies shall not
extend over the property line and must comply with UBC Sections
1710 and 504.
e) Buildings shall be designed to comply with the Fort Collins
Nonresidential Energy -Code (ASHRAAE 90.1 with local amendments.
f) The City is currently reviewing the 1997 editions of the Uniform codes
for adoption. The process is slated for completion in mid-1998.
Please contact the building inspection office for current code editions
and standards.
3. Comments from the Engineering Department are attached.
4. The Fort Collins -Loveland Water District and the South Fort Collins
Sanitation District offered the following comments:
a) The existing 4-inch water line is to be shown. The line is generally
located 10 feet west of the existing sanitary sewer line. A note to
pothole the existing water line to verify the location is to be included on
the drawings.
b) The detention pond may have to be shifted to the west depending on
the location of the existing water line.
c) The District does not allow trees or other landscaping within the
District's easements.
5. The Poudre Fire Authority offered the following comments:
Commu._ _.y Planning and Environmental, .vices
Current Planning
City of Fort Collins
January 20, 1998
Bud Frick
WJ Frick Design Group
526 South College Avenue
Fort Collins, Colorado 80524
RE. Staff comments on the Advantage Center PDP/Final Plan
Dear Bud:
Staff has reviewed the Advantage Center PDP/Final Plan that was submitted
on December 16, 1997, and would like to offer the following comments:
1. The Advance Planning Department stated "The entire landscape plan is
very awkward in terms of species and placement. Instead of explaining all
the problems, we suggested solutions. We're not sure how the front area will
end up after detaching the sidewalk so we didn't offer specific solutions there.
Any questions, call Clark at 221-6225 or Doug at 221-6226." (Please see
the attached redlined landscape plan.)
2. The Building Inspections Department offered the following comments:
a) The site shall be accessible to persons with disabilities in accordance
with the Uniform Building Code Section 3103 and UBC Appendix
Section 3106. Provide a designated and marked "accessible route of
travel" among all the buildings on the site and building exits and
entrances and the public way (public sidewalk). Accessible routes
shall comply with ANSI Al 17.1-1992 with running slopes no greater
than 1:20 and cross slopes no steeper than 1:50. Where routes cross
lanes for vehicle traffic, they shall be designated and marked as a
cross walk. Provide parking and signs per Appendix Section 3107.
Parking and access aisles shall comply with ANSI Al 17.1-1992 with
slopes no greater than 1:50 in any direction.
b) Buildings which exceed 5000 square feet in area must be equipped
with an automatic fire suppression system or be compartmentalization
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 0 (970) 221-6750 • FAX (970) 416-2020