HomeMy WebLinkAboutLARIMER COUNTY DETENTION CENTER, FACILITY EXPANSION - SITE PLAN ADVISORY REVIEW - 8-98 - CORRESPONDENCE -I
hydrant will be needed in the southwest area of the site. The existing hydrant on the south
should be moved across the parking lot. Be sure there is adequate water pressure to serve
the four story structure. For further information, please contact Roger Frasco, Assistant
Fire Marshal, Poudre Fire Authority, 221-6570.
5. The facility is served by the City of Fort Collins Water and Wastewater Utility. The size
of the expansion may trigger the need to upgrade the incoming water service. This should
be verified. Based on the expanded occupancy, there will be an assessment for both water
and sewer plant investment fees as well as satisfying the raw water acquisition charge. For
estimates of these fees, please contact Mary Young, Permits Administrator, 221-6681.
6. The Water and Wastewater Utility is concerned about the extent of the system being
located behind a perimeter security fence. The water meter vault and hydrant should be
located outside the fence. For further information, please contact Roger Buffington,
Systems Engineer, 221-6681.
7. The City's Engineering Department will require the submittal of a ten sets of Utility Plans
prepared by a licensed professional engineer in the State of Colorado. This submittal will
be made directly to the Engineering Department. This plan set must include a Grading and
Drainage Plan and Erosion Control Plan. Sidewalks will be required to be constructed
along all public street frontages. If platted or dedicated utility easements are to be
vacated, then these easements must be described legally and taken through the City's
vacation procedure. Similarly, new utility easements must be dedicated either by
replatting or be separate dedication. Each round of Utility Plan review takes about one
month. For further information, please contact Sheri Wamhoff, 221-6750.
8. The area of ground dedicated to the expanded facility will be assessed the Street
Oversizing Fee. This fee is $7,282 per acre pro -rated to the expansion area only. For an
estimate of this fee, please contact Matt Baker, 221-6605.
9. The applicant is required to submit a Transportation Impact Study. Please contact Eric
Bracke, Traffic Engineer, 221-6630, to determine the scope of the study.
10. The site is located in the Foothills Drainage Basin. The Storm Drainage Fee in this basin
is $6,525 per developed acre, subject to the runoff coefficient and the amount of onsite
stormwater detention. A Drainage Report is required to accompany the Grading and
Drainage Plan and the Erosion Control Plan. The detained storm flows are required to be
released at no more than the two-year historic rate. For information on the drainage
design from the previous addition and for general information on fulfilling the
requirements of the Stormwater Utility, please contact Basil Harridan, Storm Drainage
Engineer, 221-6589.
X
CONCEPTUAL REVIEW STAFF COMMENTS
City of Fort Collins
MEETING DATE: July 21, 1997
ITEM: Larimer County Jail Expansion
APPLICANT: Larimer County c% Mr. Bob Brashears, Reilly Johnson
Architecture, 1775 Sherman Avenue, Suite 1320, Denver, CO.
80203.
LAND USE DATA: Request to expand the Larimer County Jail by adding a four-story
housing intake facility, two-storyjuvenile housing facility, two story
medium securityhousing facility, new offices and new parking lot.
COMMENTS:
The project is considered exempt from Planning and Zoning by virtue of a decision by the
City of Fort Collins Zoning Board of Appeals. There will be no need for application to the
Planning Department for the land use consideration of the facility's expansion. This
exemption, however, does not relieve the applicant's obligation from fulfilling the
requirements of other City Departments and Utilities.
2. A building permit will be required to be obtained from the City of Fort Collins. The
additions must comply with the 1991 Uniform Building Code with locally adopted
amendments. In addition, the buildings must comply with the newly adopted Energy
Code. For further information, please contact Sharon Getz, Plans Examiner, Building and
Zoning Department, 221-6760.
3. The facility is served by the City of Fort Collins Light and Power Department. Any
relocated electrical facilities will be at the developer's expense. The three foot separation
on the west side may be tight. The relocated transformer may cost between $2,000 and
$3,000. The new location must be within 10 feet of hard surface for emergency change -
out by a boom truck. If there is an increase in the entrance panel size, then the applicant
pays the difference in fees for the upgrade. The electrical contractor must complete the
Commercial One C'C-1 ") Form to determine the new electrical load. It is likely that
temporary power will be needed since the existing fine will need to be removed. This will
involve close coordination with Light and Power to minimize the time on the temporary
power. New development charges will be applied to the new parking lot area. For further
information, please contact Bruce Vogel, Light and Power Engineer, 221-6700.
4. The facility is served by the Poudre Fire Authority. The new additions must be equipped
with an automatic fire extinguishing system with fully automatic alarm system. A new fire
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO 80522-0580 (970) 221-6750
PLANNING DEPARTMENT
Community Planning and Environmentai Services
Current Planning
City of Fort Collins
Mr. Bob Brashears
Reilly Johnson Architecture
1775 Sherman Street
Suite 1320
Denver, CO 80203
Dear Mr. Brashears:
PN•Nt =
6-sY, 83 x - Of 13 r
6�CJ6
July 24, 1997
For your information, attached is a copy of the Staffs comments concerning the
Request for expansion of Larimer County Detention Center presented before the
Conceptual Review Team on July 21, 1997.
The comments are offered informally by Staff to assist you in preparing the detailed
components of the project application. Modifications and additions to these comments
may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in the
review process, please feel free to call me at 221-6750.
Sincerely,
T.�
Ted Shepard
City Planner
TS/vrm
cc: Eric Bracke, Streets Department
Stormwater Department
Project Planner
File
281 North College Avenue - P.O. Box 580 - Fort Collins, CO 80522-0580 - (970) 221-6750 - FAX (970) 416-2020