HomeMy WebLinkAboutCAPSTONE COTTAGES - FDP - FDP150046 - CORRESPONDENCE - (4)Comment Number: 1 Comment Originated: 03/11/2016
03/11/2016: Based on the discussion on Wednesday, it sounds like the south side
stop may be relocated if the sidewalk configuration is changed. If so please ensure
that the stop area is connected to the sidewalk. I will need to review the stop again if
changes are made.
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson(a)fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 01/12/2016
01/12/2016: Irrigation plans are required no later than at the time of building permit.
The irrigation plans must comply with the provisions outlined in Section 3.2.1(J) of
the Land Use Code. Direct questions concerning irrigation requirements to Eric
Olson, at 221-6704 or eolson@fcgov.com
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals(a)fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 01/13/2016
03/09/2016: Please place the streets in the parkway not behind the sidewalk.
01/13/2016: On sheet L5.0 Please include street trees along Duff Drive.
Page 11 of 11
Comment Number: 36
Comment Originated: 03/10/2016
04/11/2016: This has not been corrected. The note needs to be exactly as shown in
previous comment.
03/10/2016: Please change the name & note on all sheets showing International
Boulevard to: International Boulevard (Final Name To Be Determined By City
Council By Resolution). Please use this exact wording. See redlines.
Topic: Plat
Comment Number: 6
Comment Originated: 01/12/2016
04/11/2016: All reception numbers for documents recorded by separate document,
must be added prior to producing mylars.
03/10/2016: All reception numbers for documents recorded by separate document,
must be added prior to producing mylars.
01/12/2016: All reception numbers for documents recorded by separate document,
must be added prior to producing mylars.
Topic: Site Plan
Comment Number: 9
Comment Originated: 01/12/2016
04/11/2016: This has not been corrected. The note needs to be exactly as shown in
01/12/2016 comment.
03/10/2016: The note needs to be exactly as shown in previous comment.
01/12/2016: Please change the name & note for the "Minor Arterial" to the following.
International Boulevard (Final Name To Be Determined By City Council By
Resolution). Please use this exact wording. See redlines.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson(oDfcgov.com
Topic: General
Comment Number: 2
Comment Originated: 01/13/2016
04/13/2016: 1 know this exists, and we discussed it at a meeting, but I still don't
have a hard copy for the files.
01/13/2016: Can you provide a brief design report related to the roundabout? It
would be helpful to have a summary document that bullets the key components,
ICD, R values, truck turning templates, etc. We'll have striping comments at the
design meeting on Thursday.
Comment Number: 5 Comment Originated: 04/13/2016
04/13/2016: On sheet C937 for eastbound bike lane, please extend the solid bike
lane stripe on the approach to 12th street to within 100 feet of the intersection. Just
skip the last 100 feet.
Comment Number: 6
Comment Originated: 04/13/2016
04/13/2016: 1 see the roundabout construction phasing plans. These should be for
reference only, and ultimately work area traffic control plans will need to be
submitted, reviewed and approved through the WATC permit process. Please
contact Syl Mireles at 970-221-6815 or smireles@fcgov.com to begin planning for
construction.
Department: Transportation Planning
Contact: Emma Belmont, 970-224-6197, ebelmont(dfcgov.com
Topic: General
Page 10 of 11
Comment Number: 16
Comment Originated: 01/12/2016
04/11/2016: There are line over text issues
03/10/2016: There are line over text issues
01/12/2016: There are line over text issues
Comment Number: 17
See redlines.
See redlines.
See redlines.
Comment Originated: 01/12/2016
04/11/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
03/10/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
01/12/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
Topic: Construction Drawings
Comment Number: 20
Comment Originated: 01/12/2016
04/12/2016: There are still some issues. See redlines.
03/10/2016: There are still some issues. See redlines.
01/12/2016: There are titles in the sheet index do not match the titles on the noted
sheets. See redlines.
Comment Number: 22
04/12/2016: There are line over text issues
03/11/2016: There are line over text issues
01/12/2016: There are line over text issues
Comment Number: 23
Comment Originated: 01/12/2016
See redlines.
See redlines.
See redlines.
Comment Originated: 01/12/2016
04/1212016: This has not been corrected. The note needs to be exactly as shown in
1/12/16 comment.
03/11/2016: Some sheet have this note shown incorrectly. The note needs to be
exactly as shown in previous comment.
01/12/2016: Please change the name & note for the "Minor Arterial' to the following
on all sheets showing the street. International Boulevard (Final Name To Be
Determined By City Council By Resolution). Please use this exact wording. See
redlines.
Comment Number: 26
Comment Originated: 01/14/2016
04/12/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
03/11/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
01/14/2016: There is text that needs to be masked. Mask all text in hatched areas.
See redlines.
Comment Number: 30
Comment Originated: 01/14/2016
04/12/2016: There is text that needs to be rotated 180 degrees. See redlines.
03/11/2016: There is text that needs to be rotated 180 degrees. See redlines.
01 /14/2016: There is text that needs to be rotated 180 degrees. See redlines.
Topic: Landscape Plans
Comment Number: 12
Comment Originated: 01/12/2016
04/11/2016: This has not been corrected. The note needs to be exactly as shown in
01/12/2016 comment.
03/10/2016: The note needs to be exactly as shown in previous comment.
01/12/2016: Please change the name & note for the "Minor Arterial' to the following.
International Boulevard (Final Name To Be Determined By City Council By
Resolution). Please use this exact wording. See redlines.
Topic: Lighting Plan
Page 9 of 11
Comment Number: 10
Comment Originated: 04/12/2016
04/12/2016: STREET NAMES
The proposed plan for street naming does not currently meet local standards. To be
consistent with typical naming, each north -to -south drive should be named
independently and east -to -west drive should be named independently. This would
result in six unique street names being provided internal to the site.
Ultimately, street naming will need to be approved by city GIS. Please contact Todd
Reidenbach at 970-416-2483.
Comment Number: 11
Comment Originated: 04/12/2016
04/12/2016: PRIVATE MAINTENANCE SIGN
Please update private maintenance sign at four entry's to include fire hydrants and
water utilities per engineering verbage.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamargue(a)jcgov.com
Topic: General
Comment Number: 14 Comment Originated: 03/09/2016
03/09/2016: The run-on area for the porous paver system is over the manufacturer
recommended maximum by double. The concern is the maintenance and
sustainability of these pavement systems may be compromised the the additional
loading.
Also, the sub -basins that drain onto the porous pavement may need some altering
which may help reduce the run-on area. It appears that some of the roof tops that
are planned to drain over the pavement system may not drain that way per the
grading plan.
Comment Number: 16 Comment Originated: 03/09/2016
04/13/2016: Reminder
03/09/2016: In Basin 14c, the private drive is designed to drain to the detention pond.
The grading plan does not show a way for these flows to drain to the pond. Please
revise.
Comment Number: 17
Comment Originated: 03/09/2016
04/13/2016: Reminder
03/09/2016: Please provide and label all high point spot elevations for the grading
around the structures.
Comment Number: 21
Comment Originated: 03/11/2016
04/13/2016: Some of the rain gardens are on individual lots. These need to be in a
drainage easement and maintained by the HOA.
03/11/2016: Please provide drainage easements for the rain gardens.
Comment Number: 22 Comment Originated: 04/13/2016
04/13/2016: Please specify dimensions and type of riprap in the rain garden chase
detail.
Comment Number: 23 Comment Originated: 04/13/2016
04/13/2016: Please see other minor redlined comments.
Department: Technical Services
Contact: Jeff County, 970-221-6588, Icounty(r�fcgov.com
Topic: Building Elevations
Page 8 of 11
Comment Number: 6 Comment Originated: 01/12/2016
01/12/2016: Drawings show an electrical line along the north side of Lincoln, just
south of the development. This needs to be double checked since our maps do not
show any electrical on the north side of Lincoln, but rather on the south side. This
could be telephone line since the drawings show telephone being feed in the area.
Comment Number: 7 Comment Originated: 01/12/2016
01/12/2016: If any existing electrical lines need to be relocated to accommodate the
round -a -bout, modification charges will apply.
Comment Number: 8 Comment Originated: 01/12/2016
01/12/2016: Street lighting and electrical design will be done for the existing Lemay
Ave. Once the new Lemay Ave is installed, modification charges will apply for the
relocation of street lighting and electrical infrastructure.
Comment Number: 9 Comment Originated: 01/12/2016
01/12/2016: Distinguish between City street lighting and private lighting on the
landscape drawings. Some proposed City street lights are missing from the
drawings. Contact Todd Vedder if a copy is needed for proposed street lighting.
Local residential streets shall have one light at each intersection. If the intersection
lights would exceed 320 feet apart on a straight street, mid -block lights shall be
added so lights do not exceed 320 feet spacing. If the street has a curve, judgment
shall be used to reduce the spacing to less than 320 feet.
Shade trees are required to maintain 40 feet of clearance with street lights and
ornamental trees are required to maintain 15 feet of clearance with street lights.
(clearances is from the trunk of tree to light)
Comment Number: 10 Comment Originated: 03/08/2016
03/08/2016: In regards to comment #5, it will be the responsibility of the
developer/electrician to provide the secondary service from the transformer to the
meter. This pertains to any single family attached units and where there is ore than
one meter on a lot. Please contact Todd Vedder with any questions.
Comment Number: 11
Comment Originated: 03/08/2016
03/08/2016: On sheet L2.0 there is a proposed street light on the northwest corner
too close to an existing trees. Street lights need to maintain 40' separation from
shaded trees and 15' separation from ornamental.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler(a)poudre-fire.orq
Topic: General
Comment Number: 8
Comment Originated: 04/12/2016
04/12/2016: FIRE LANE MARKING
Additional No Parking - Fire Lane signage and red curbing is required per redlines.
Refer to LUCASS detail 1418 for sign type and omit the language "by order of the
Fire Marshal" and replace with directional arrows.
Comment Number: 9
Comment Originated: 04/12/2016
04/12/2016: PRIVATE HYDRANTS
A draft of the maintenance plan to address the private hydrant and utility
infrastructure system has been submitted by Northern Engineering and is currently
under review by the fire marshal.
Page 7 of 11
Contact: Tim Buchanan, 970-221-6361, tbuchanan(cDfcgov.com
Topic: Landscape Plans
Comment Number: 27
Comment Originated: 03/08/2016
03/08/2016:
The tree inventory and mitigation plan did not appear to the in the landscape plan
set. Email this plan to the City Forester and also include the tree inventory and
mitigation plan in the landscape plan.
Comment Number: 28
Comment Originated: 03/08/2016
03/08/2016:
Not all of the medians along Lincoln or new landscape area on the south side of
Lincoln show up on the Landscape plan.
Comment Number: 29
Comment Originated: 03/08/2016
03/08/2016:
The locations of the Autumn Brilliance Serviceberry's closest to the round -about
appear like they will cause a line of site problem for pedestrians crossing the street.
Review and remove these from the plan if necessary.
Comment Number: 30
Comment Originated: 03/08/2016
03/08/2016:
To provide more tree diversity in the medians (not the round -about) explore the use
of some Red Baron Crabapple or Chanticleer Pear.
Department: Light And Power
Contact: Todd Vedder, 970-224-6152, tvedder(a)fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 01/12/2016
01/12/2016: New development and system modification charges may apply. A link
to our online electric fee estimator is below.
hftp://www.fcgov. com/utilities/business/builders-and-developers/plant-investment-de
velopment-fees/electric-development-fee-estimator?id=3
Comment Number: 2
Comment Originated: 01/12/2016
01/12/2016: Transformer and meter location needs to be coordinated with Light &
Power. It is preferred to have the meters gained on one side of the building opposite
from gas meters. Coordination is important since this is a congested site and
power lines need to be separated by 10 feet from water lines and 3 feet from gas
lines.
Comment Number: 3
Comment Originated: 01/12/2016
01/12/2016: A C-1 form needs to be filled and a one -line diagram needs to be
provided for the clubhouse in order to size the transformer properly. It is preferred to
serve the clubhouse with single phase if possible. A link to a copy of our C-1 form is
below.
http://zeus.fcgov.com/utils-procedures/files/EngWiki/WikiPdfs/C/C-1 Form. pdf
Comment Number: 4 Comment Originated: 01/12/2016
01/12/2016: Please provide breaker panel sizing for each unit.
Comment Number: 5 Comment Originated: 01/12/2016
01/12/2016: For any multifamily units, it will be the responsibility of the
developer/electrician to provide the service from the transformer to the meter.
Page 6 of 11
Comment Number: 546
Comment Originated: 03/09/2016
04/12/2016: The response of providing the stripe out area for the east median I don't
think, necessarily addresses parks maintenance concerns with the largest median
being the western median. We would want to get their weigh-in on this.
03/09/2016: At the last streetscape team meeting, it was brought up that Parks
would want a pull out into the median along Lincoln west of the roundabout in order
to better maintain the median. This does not appear to have been accounted for in
the plans.
Department: Environmental Planning
Contact: Kelly Kimple, 970-416-2401, kkimple(aDfcgov.com
Topic: General
Comment Number: 1
Comment Originated: 01/11/2016
04/12/2016: This text still needs to be corrected. See redlines.
03/08/2016: On sheet L7.0 there is some text overlap in labeling the NHBZ. Please
correct and also remove the redundant "the buffer zone", which comes after "the
Natural Habitat Buffer Zone". The Natural Habitat Buffer Zone (NHBZ) will be
referred to in the Development Agreement and will be used for purposes of the DA,
future inspections, and for evaluating the overall establishment of the wetland and
buffer; therefore, it should be labeled consistently and clearly on all plans.
01/11/2016: On all plans showing the mitigation wetland and associated buffer,
please label more clearly to indicate the entire upland area around the wetland is the
NHBZ. A logical boundary would be the gray -dashed existing stormdrain line. Please
also provide a table of the area of the mitigation wetland, as well as the buffer.
Comment Number: 3
Comment Originated: 01/11/2016
04/12/2016: As outlined in an email to Linda Ripley dated 3/3/16, the City will require
a security for both the wetland creation and monitoring, as well as installation and
establishment of the NHBZ around the compensatory wetland. The securities can
be in the form of a letter of credit, bond letter, or escrow (cash or check), and are
due at the time of DCP.
Also, Environmental Planning did receive the monitoring plan Cedar Creek
submitted, however, it does not include information on the mitigation plan and a cost
estimate. Steve Long with Cedar Creek indicated that he would talk to Ripley Design
Inc., about the cost estimate. The City will need two separate cost estimates; one
for construction of the mitigation wetland and monitoring, and another for installation
and establishment of the NHBZ, including labor, irrigation, materials, weed
management and monitoring.
It would be helpful too if Cedar Creek could include further detail in their monitoring
plan regarding the project site, existing wetland conditions, wetland impacts,
mitigation concept plan and map, timetable for construction of the compensatory
wetland, as well as the cost and probability of success for the new wetland. Here's a
link to a good example of a more complete wetland mitigation and monitoring plan:
https://www-static. bou ldercolorado. gov/docs/bcc_wetland_mitigation_plan-1-20130
7051635. pdf
01/11/2016: As discussed, a mitigation and monitoring plan will need to be finalized
to indicate how the wetlands will be installed and monitored to ensure success. This
document will be attached to the development agreement. A letter of credit to
ensure the wetlands and buffer can be replaced, should the success criteria not be
met, will be required.
Department: Forestry
Page 5 of 11
Comment Number: 231 Comment Originated: 04/12/2016
04/12/2016: With the edge of pavement profiles provided for review, I'm seeing
concerns of access ramps that would not meet the no more than 2% cross slope
intersecting the public street. Please look at C920 for the access ramp at the
northwest leg of the roundabout (2.35%) and C922 for the access ramp at the
southwest leg of the roundabout (2.56%). In looking further at C933, the cross slope
checks at the northwest length (2.5%), southwest leg (4.15%) and southeast leg
(3.6) of the International/private drive appear to exceed 2%.
Topic: General
Comment Number: 525 Comment Originated: 01/13/2016
04/12/2016: 1 did not see this referenced on the site/landscape plans. In checking
with PFA, they would want to see that the "Begin Private Maintenance" sign also
discern that the fire hydrant/water system is part of this. It would seem the best
approach is to have the sign itself be revised to "Begin Private Maintenance (Roads,
Water/Sewer, Fire Hydrants)"
03/09/2016: 1 did find the detail for this on C706 of the civil, on sheet C200 please
have the references refer to the detail.. I'm not sure I'm finding it being referenced on
the site and landscape plans, but should be added as well.
01/13/2016: Carrying forward a PDP comment as unresolved, looking to have
"Being Private Maintenance" informational signs at the entrances to the site off of the
public streets. A detail should be added to the civil detail sheets, and their locations
referencing the detail should be shown on the site/landscape and civil plans.
Comment Number: 530 Comment Originated: 03/09/2016
04/12/2016: Carried over for reference, this language has been added to the
working development agreement draft.
03/09/2016: We've received comments from the business property owners to the
east (who have also contacted Larimer County, being not in City limits) regarding
construction build -out of the project. They are looking to have the following occur
with the construction of the project:
"A barrier installed at the ends of Webster and Duff (and Link if necessary)
prohibiting vehicle and pedestrian access through the FCBA subdivision. Perhaps a
4� orange fence across that entire area would work."
�No Construction Access sign installed at Lincoln and Link."
The City is OK with their requests and would want to verify if the Developer is
amenable to these items, and their placing in the development agreement. Larimer
County Engineering has indicated support of the items listed above as well, and with
the second item occurring outside City limits, they are OK with the following input:
"County is fine with a 6No Construction Access6sign being installed at Lincoln and
Link, We would expect the Developer to install it. The sign should conform to
MUTCD requirements and mounting posts need to meet break away requirements.
They should also be required to obtain utility locates before installing the posts.
We would not require it to be on plans. But if City requires it to be on the plans, it is
not necessary for me to sign the sheet.
Any questions at the time of installation can be directed to Bill Gleiforst, Larimer
County Traffic Operations Manager at (970) 498-5707.
There are no County permits required for the installation. "
Page 4 of 11
Comment Number: 220 Comment Originated: 01/13/2016
04/12/2016: I'm still finding a few discrepancies between the spot elevation sheets
and the flowine plan and profiles. West side of International just south of Duff (spot
elevations wouldn't appear to be correct), south side of Webster east of International
showing a 5.5% when no flowline profile grades exceed 2.65%. I'm still wondering if
there's ADA issues with cross slopes at access ramps (beyond #206), Along Duff
Drive across the driveway has a 4.3%, north side of Webster at International shows
a 3.9%. In general are the access ramps being checked for not exceeding 2% along
public rights -of -way?
03/09/2016: With the spot elevations not provided, some general concerns:
On the west leg of Duff and International (C516) along Duff, the flowline grades
shown on the spot elevations do not coincide with the plan and profile deisgn
(grades of 5% and 20% when the plan and profile show in the .5 to 2% range,)
Flowline grades shown on International's spot elevations also do not match the
International flowline plan and profile (2.3% instead of .6%).
Along Lincoln in front of South Clubhouse Drive the grades within the flowine are at
.3% below the .5%, similarly along International at Cottage Drive, flowline grades fall
below .5%
There appear to be exceed of 2% cross slope for ADA at access ramps, such as
crossing Webster at International, also at Cottage Drive at International, and the
midblock private drive at Duff Drive.
01/13/2016: Intersection spot elevations are needed for the public streets
intersections in accordance with Figure 7-27 and 7-28 of LCUASS.
Comment Number: 265 Comment Originated: 01/13/2016
04/12/2016: 1 didn't see this in my submittal, if by chance it was provided to
Martina/Traffic Ops, that's fine, I would just like to have a copy of it for our records.
03/09/2016: Can the report "Lincoln & International Roundabout Design Criteria and
Calculation Package" please be signed and stamped as a document we can retain
for the project?
01/13/2016: I'm presuming a report on the parameters used for the design of the
roundabout will be provided and further discussion will occur on the Thursday
morning meeting. Turning templates for emergency and WB-50 vehicles should be
provided in the report, and how does a WB-67 track through the intersection?
Comment Number: 206 Comment Originated: 03/09/2016
04/12/2016: There appears to still be the issue of the cross slope for the access
ramps exceeding 2%.
03/09/2016: On sheet C507, there's a concern with a grade break exceeding .4%
from 4.79% to 2.75% and 4.22% to 2.75% in the flowlines of Duff east of
"International". Additionally, the cross slopes at the access ramps here would
exceed 2% and not result in an ADA compliant crossing.
Comment Number: 242 Comment Originated: 03/09/2016
04/12/2016: These three cross sections don't appear to be showing accurate
information and not clear.
03/09/2016: STA 42+50, STA 43+00 and STA 43+50 should be showing the
additional pavement widening that's being proposed along the north side of Lincoln
Avenue. There should be a 4 foot recycled asphalt shoulder past the edge of
pavement to help contain the new asphalt and provide some shy distance for the
bikelane edge. Behind the shoulder should be 4:1 grading to tie back into existing.
Page 3 of 11
Topic: Site Plan
Comment Number: 2 Comment Originated: 03/08/2016
03/08/2016: SP 1: General Notes #5, change duplex to "two-family".
Comment Number: 4
Comment Originated: 03/08/2016
03/08/2016: SP2/SP3: Project approved for 201 units and plan now shows 202. aAd
line to describe extra unit is part of maintenance building.
Comment Number: 14
Comment Originated: 04/12/2016
04/12/2016: SP1 - Update general notes to include any new language from word file
provided. Add description for two family unit in legend.
Comment Number: 15 Comment Originated: 04/12/2016
04/12/2016: SP2-SP4 - Show sidewalk lines see redlines. IN residential unit
summary table, add line description for extra unit (202) that is part of maintenance
building.
Comment Number: 16 Comment Originated: 04/12/2016
04/12/2016: SP5 - show edge of pavement on Lincoln sidewalk at bollard.
Comment Number: 17 Comment Originated: 04/12/2016
04/12/2016: SP6 - add details for other building types.
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirataPfcaov.com
Topic: Construction Drawings
Comment Number: 205
Comment Originated: 01/13/2016
04/12/2016: Carried over for reference, with the understanding that an offsite
easement will be obtained from the property owner to the north.
03/09/2016: The response indicates the grading has been revised to be within
right-of-way or within a grading easement. Is a grading easement specifically being
identified as the grading plans don't appear to depict an easement. The grades
within right-of-way are not meeting at least a 4:1 slope however and would need to
be revised (which would likely then require the grading easement). The cross
section at 31+50 again shows the need for some sort of grading easement from the
property owner to the east.
01/13/2016: The cross sections for Duff Drive show grading past the platted
right-of-way for Duff Drive along the north and would require an offsite grading
easement. Note that the right-of-way from STA 27+50 on is not depicted for the
north side as well as the south side east of the new minor arterial. Offside grading
easement might be needed for the south side of Duff Drive east of this property.
Page 2 of 11
Fort Collins
April 15, 2016
Linda Ripley
RIPLEY DESIGN INC.
401 WEST MOUNTAIN AVE
Fort Collins, CO 80521
RE: Capstone Cottages, FDP150046, Round Number 3
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins. CO 80522
970.221.6750
970.224.6134 - fax
fcgov. com/developmentrevlew
Please see the following summary of comments from City staff and outside reviewing agencies for
your submittal of the above referenced project. If you have questions about any comments, you may
contact the individual commenter or direct your questions through the Project Planner, Pete Wray, at
970-221-6754 or pwray@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray(ZDfcgov.com
Topic: Building Elevations
Comment Number: 21 Comment Originated: 04/12/2016
04/12/2016: Need building elevations for clubhouse.
Topic: General
Comment Number: 22 Comment Originated: 04/13/2016
04/13/2016: Utility Plans - see redlines for sidewalk connections.
Comment Number: 23 Comment Originated: 04/15/2016
04/15/2016: After the 3rd round of FDP review, staff is prepared to allow an informal
PDF round of review prior to mylars. Please coordinate with me to get new routing
sheet for remaining staff with comments. I will set a 2 week review depending on
when we get submittal package. the actual time needed for review will depend on
accuracy of revised plans.
Topic: Landscape Plans
Comment Number: 7 Comment Originated: 03/09/2016
03/09/2016: 1-7: 1 am not sure what the 4 blank rectangles are in the median?
Comment Number: 18 Comment Originated: 04/12/2016
04/12/2016: L1 - Update Forestry Notes all pages with file provided.
Comment Number: 19 Comment Originated: 04/12/2016
04/12/2016: L2, L3 - Sidewalk connections see redline.
Comment Number: 20 Comment Originated: 04/12/2016
04/12/2016: L10, L14 - Update notes per file provided.
Page 1 of 11