HomeMy WebLinkAboutWOODWARD TECHNOLOGY CENTER (FORMERLY LINK-N-GREENS) - PDP - PDP130001 - CORRESPONDENCE - RESPONSE TO APPLICANT5) As part of Phase One, this project is required to obtain FEMA approval of a
Conditional Letter of Map Revision (CLOMR) and a Letter of Map Revision (LOMR)
in order to update the floodplain maps.
6) A variance to allow hazardous material critical facilities in the 100-year
floodplain prior to approval of the LOMR was granted by the Water Board on
January 17, 2013. This project is required to comply with all conditions set forth in
the floodplain variance.
Condition Number One was not approved:
1) A 15 feet wide public access easement shall be provided along the western
property boundary to accommodate a future trail connection from Lincoln Avenue
to the Poudre River Trail.
If you have any questions regarding this action by the Planning and Zoning Board,
please feel free to call our office at 221-6750.
Sincerely:
4Q0AV--1
Jason Holland, PLA I City Planner
Planning Services
City of Fort Collins
281 North College Avenue
Fort Collins, CO 80522
711
-A
City
Planning, Development and
of
■
Transportation Services
Planning Services
F6rtCollins
North College Ave.
P.O.P.Box 580
Fort Collins, CO 80522-0580
970.221.6750
970.224.6134 - fax
fcgov. com/currentplanning
February 22, 2013
NewMark Merrill Mountain States
c/o Allen Ginsborg
2720 Council Tree Ave., Suite 230
Fort Collins, CO 80525
RE: Decision letter for Woodward Link-n-Greens Project Development Plan, PDP
#130001 and Modifications of Standard.
Dear Allen:
On Thursday, February 21, 2013 at a special meeting of the City of Fort Collins
Planning and Zoning Board, the Board voted 7 — 0 to approve the Link-n-Greens
Project Development Plan, PDP #130001, Modification of Standard to Section
4.20(D)(3)(a)(1) and Modification of Standard to Section 4.20(D)(3)(a)(2), subject
to the following conditions:
2) This project shall provide adequate access for emergency vehicles and for those
persons rendering fire protection and emergency services by complying with Article
9, Fire Department Access and Water Supply, of the Uniform Fire Code as
adopted and amended pursuant to Chapter 9 of the City Code.
3) A horizontal design for the double left turn lane for southbound Lemay Avenue
to eastbound Mulberry Street shall be provided (included as a part of the final
approved utility plan set) and the right-of-way needed to accommodate this design
shall be dedicated on the final plat. The double left turn lane shall be built in
conjunction with any phase of the project which triggers the need for the double
turn lane based upon the Traffic Impact Study for that phase. If the double left turn
lane construction becomes the responsibility of the City the timing shall be at the
City's discretion.
4) The final design of the utility infrastructure and any associated easements, other
than for Phase 1 for which final design and easements shall be included as a part
of the Final Development Plan documents, shall be provided, approved, and
accepted concurrent with and prior to the approval of the minor amendment(s) for
each additional phase(s), building(s) and/ or prior to the start of any construction
work on these items.