HomeMy WebLinkAboutRIVER SONG WALDORF SCHOOL - PDP - 11-98 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTPROJECT: Waldorf School SEQUENCE FOR 1998-99 ONLY COMPLETED BY: Chris Carlson DATE: 2/9/98 Indicate by use of a bar line or symbols when erosion control measures will be installed. Major modifications to an approved schedule may require submitting a new schedule for approval by the City Engineer. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. OVERLOT GRADING WIND EROSION CONTROL Soil Roughing Perimeter Barrier Vegetative Methods Mulching / Sealant RAINFALL EROSION CONTROL STRUCTURAL: Detention Pond Pond Outlet Filters Straw Barriers Silt Fence Barriers 1111111111111110 Sand Bags Bare Soil Preparation Contour Furrows Asphalt / Concrete Paving VEGETATIVE: Permanent Seed Planting Mulching / Sealant Temporary Seed Planting Sod'. Installatiorif Nettings / Mats / Blankets BUILDING CONSTRUCTION: STRUCTURES INSTALLED BY: Contractor VEGETATION/MULCHING CONTRACTOR: Contractor DATE SUBMITTED: 219/98 MAINTAINED BY: Contractor APPROVED BY CITY OF FORT COLLINS ON: Figure 5. Construction schedule. 11 Ayres Associates During overlot and final grading, the soil will be roughened and furrowed perpendicular to the prevailing winds (northwest to southeast). All areas not covered by asphalt, concrete, or foundations and not seeded within two weeks of final grading will have 2 tons/acre of straw mulch either crimped 4 or more inches into the soil or sprayed with a tackifier. The inlet filter and silt fences will remain in place until construction is complete. They should be checked after each storm event to determine whether repairs or alterations are needed. With proper precautions, damage to off -site areas from a greater than historic sediment load ' can be eliminated and the loss of sediment from the site minimized. Calculations for performance standards and effectiveness will be submitted with the final drainage and erosion control plan. The proposed construction sequence is shown in Figure 5. f 10 Ayres Associates Table 5. Detention Pond 179 - Outlet Rating Curve. WSEL Volume (ac-ft) Discharge (cfs) 5103.50 0.000 0.00 5104.00 0.035 0.24 5104.50 0.206 0.37 5105.00 1 0.377 1 0.47 100-year WSEL = 5104.34 100-year Volume = 0.15 ac-ft 100-year Peak Discharge = 0.49 cfs 2-year WSEL = 5104.04 2-year Volume = 0.049 ac-ft 1 2-year Peak Discharge = 0.25 cfs NOTE: UDSWMM output is to the nearest cfs and tenth of an ac-ft. The volumes and discharges shown are the highest possible derived from that output. Runoff basin 80 will flow through a swale directly into the drainageway. The swale will have 4:1 side slopes and be lined with grass. Since the swale slope is less than 2.0 percent, a perforated underdrain will be placed 6 inches below the surface and along the swale centerline. The underdrain pipe will improve drainage of low flows and standing water. The drainageway's left bank will be improved with side slopes ranging between 8:1 and 4:1. With the exception of approximately the first 0.5 foot of channel depth, most of the right bank will remain unimproved. The existing retention pond will be relocated slightly farther to the west and the area cleaned up. The retention area will be placed as part of the drainageway. The existing drainageway makes a 90 degree left bend, runs for approximately 85 feet then makes another 90 degree right bend. These bends have historically created flooding of the adjacent residential lots in Mountaire Subdivision. The proposed drainageway will follow the same course, but will be improved to contain runoff within the channel banks and to eliminate flooding of these lots. Along the parking lot, the channel will be contained within in (2) 2.5 foot high retaining walls. EROSION CONTROL PLAN Erosion from the site can be classified into erosion caused by wind and rainfall. Since construction will occur during the winter and spring months, effective wind erosion plans must be established. On moderate erodibility soil, significant erosion could occur without steps taken to protect the soil. Those portions of the site not covered with pavement, concrete, or buildings and not seeded within a month of final grading will have 2 tons/acre of straw mulch applied for water erosion control, which will also prevent wind erosion. All mulches will be properly anchored. The effects of rainfall erosion will be eliminated by the use of several erosion control techniques to prevent sediment from leaving the site. A silt fence, which will prevent sediment from flowing off the property will be placed along the drainageway. A silt fence will also be placed along the west property line. A straw bale inlet filter will be placed at the detention pond outlet until construction is complete. 9 Ayres Associates C0 N N , tO CM M 21 O V C:) C)O O m O r U N y } U to to O to a .. N pl C v IT CO Iq N c c Q o o 10 0 o Cl Cl 0 0 00 O O R O C6 L N > 0� J S CQ N a 13 C (A (O (D O CO O O N 0 0 0 Cl i O O O O O C N NCM L 0 to LO N v C1q, LO CO M r r U C J (a T > 02 0 0 0 o 0 U- 'SSOE _ S to to N ' to to S a C6 C m O O N N CL O O C C C C C C L L C O .0 U U a U v OCO r CO r 00 r to O U r O O r > CO O ti 00 r r r U y C U 0 (a p" T 3} d '0 m a) y i-J (O CO CO a0 CON CO O O 0 = . (L U r y a;C')N i p y } tO Cl) 0 r 0 r 0 r m 4) p U 0 (N C n� O 0CSO` n' C.i } v tO t0 to r r CV y l0 c w w 000 U C] 0=0 tm O1 `m O N o f6 N O. E y ) c O U 3 0 of )i .. M M M N 7 'O > 0 U O O O CO p C C)= N N x lL�}v m u N O u'1 Ui r r CO m m N C a}` O O O N .20 ado v r r r a>i r N 0 CO ` M M N r v} r r r r N E N d N N C O C y N 'p O Nt y E m a v o, - m L C pl C L 3 O C 3 3 3 3 0 0 0 0 lL LL lL lL C r CD 00 (O (O CO W (O 8 Ayres Associates Table 1. Subbasin Constants. Parameter Value Manning's, n for impervious surfaces 0.016 Manning's n for pervious surfaces 0.25 Surface retention storage for impervious surfaces 0.1 in. Surface retention storage for pervious surfaces 0.3 in. Maximum infiltration rate 0.51 in/hr Minimum infiltration rate 0.50 in/hr Decay rate 0.0018 Storm duration 3 hours Time step 1 minute Table 2. Basin Parameters. Subbasin Connected To: Width (ft) Area (ac) Percent Impervious Slope I(ft/ft) 80 180 157 0.573 26.0 0.010 81 179 136 0.782 64.0 0.005 82 179 121 0.836 21.0 0.020 0 7 Ayres Associates J N Q Q W ma0 w �r �wLLJ� �cn2U) ai N of 00 00 M511 o w 0 00 � O LLJ 0 i o woo w Z zQw o O Q LLJz } Z o W w Z > w � F N Z Z 0 J w C O O J aZZJ J 0 m U O L� V)Q¢W wma0 ���2 rn 0 CE ��Q� (n2N 6 Ayres Associates During the 2-year storm event, the peak runoff in the drainageway leaving the site is 5 cfs with the Scenic Views development and 12 cfs without the Scenic Views development (flows shown for element 61). SWMM output is shown in the Appendix. PROPOSED DRAINAGE CONDITIONS A detailed site, grading, and drainage plan (enclosed in pocket) shows the building layout and storm drainage facilities that will be used for the Waldorf School site. The map uses a 1-foot contour interval. A schematic of the proposed conditions SWMM network is shown in Figure 4. ' The developed site will consist of 3 subbasins that contribute drainage to a detention pond and the drainageway. SWMM, which was used for determining the existing condition runoff, was used to determine the proposed condition 2- and 100-year peak discharges and ' detention pond volumes. Subbasin constants are shown in Table 1, basin parameters in Table 2, and conveyance elements and runoff in Table 3. I Subbasins 81 and 82 contribute drainage to a detention area labeled 179. Curb and gutter and overland flow will convey the runoff to the pond outlet structure. The pond will release runoff into a 15-inch diameter ADS pipe which will daylight in the drainageway. Subbasin 80 will contribute undetained runoff directly into the drainageway. Although improvements will be made to the drainageway itself, offsite conditions will not change. A I comparison of SWMM results between the Master Plan fully developed model, the existing conditions model, and the proposed conditions model is shown in Table 4. STORM DRAINAGE FACILITIES A major portion of runoff flows off of the parking lot through a curb cut and into the detention pond. Other areas drain directly to the detention pond. The detention pond, element 179, was sized to contain the 100-year runoff from subbasins 81 and 82. The site's storm drainage facilities consist of concrete pans, a detention pond, Runoff will be released at a controlled rate so that the total runoff leaving the site in the drainageway is equal to or below both the historical flows and the Master Plan fully developed flows. The detention pond's outlet structure will consist of a 15-inch diameter ADS pipe with a 4- ' inch diameter orifice. In the event the orifice becomes clogged, water will flow over an emergency spillway into the "drainageway. The spillway will be designed as part of final design. For a 3-hour, 100-year storm, the detention pond must detain 0.15 acre-foot (ac-ft) of water. The 100-year water surface elevation (WSEL) is 5104.34, corresponding to a maximum depth at the outlet of 0.84 feet. For a 3-hour, 2-year storm, the detention pond must detain 0.05 ac-ft of water. The 2-year WSEL is 5104.04, corresponding to a maximum depth at the outlet of 0.54 feet. The detention pond's outlet rating curve is shown in Table 5. 5 Ayres Associates CSU EQUESTRIAN CENTER N PLEASANT VALLEY AND LAKE CANAL 12 1 _ ----- ---- PROPOSED ,DE TENTIO >,1 ',POND �� 'PROPOSED-` CENIC VIEWS SUBDIVISION STREET SUBCATCHMENT BASIN BOUNDARY ------------- CHANNEL OR GUTTER 11 BASIN LABEL ® CONVEYANCE ELEMENT ®&05 DETENTION POND CONCENTRATION POINT RIVER SONG WALDORF SCHOOL - PROPOSED SITE 111111 No KIMBALL ®!I DETENTION ; W. r= i'w PEAR DETENTIO FPOND ) r) F --- � F ELIZ x 0 0 z 600 300 0 600 SCALE: 1"-600' NEW MERCER CANAL Of MOORE E:fi • FI.1 fb7ELEMENTARY SCHOOL 03 Q. E is ONSITE' • • `�P im - • COMMONS �1i95fis 1 • w Of 0 z w J 0 CRESTMORE PL. REGIOI` DETEN ,J'.d POt i Figure 3. Overall West Plum Street Basin. O N 0 191 v D N 00 M N ® N ON d t �I N 1 M F Ayres Associates VICINITY MAP Figure 1. Vicinity map. 2 Ayres Associates I INTRODUCTION This report summarizes the storm drainage investigations performed for the proposed River Song Waldorf School. A hydrologic analysis of the proposed development was completed to determine the magnitude and location of storm runoff, allowable release rates into an existing drainageway, develop a detention pond, and to determine downstream effects of the proposed development. This study and drainage plan was prepared to meet the City of Fort Collins Storm Drainage Design Criteria for the development. The River Song Waldorf School property is located along the south side of Orchard Place adjacent to the intersection with Orchard Place and Louise Lane as shown in Figure 1. The ' site is a 2.4 acre lot created by subdividing Happy Heart Farm and occupies part of the northwest quarter of Section 16, Township 7 North, Range 69 West, of the 6th Principal Meridian. PREVIOUS STUDIES Previous drainage studies of the area include (1) West Plum Street Basin Master Drainage Plan (RCI 1990), and (2) Update of Hydrologic Analysis for West Plum Street Basin (Ayres Associates 1995). These were reviewed to assist with the preparation of this report. EXISTING DRAINAGE CONDITIONS The River Song Waldorf School lies within the West Plum Street Basin. Orchard Place and Louise Lane lie to the north, Happy Heart Farm to the south, Mountaire Subdivision to the east, and unplatted natural land to the west. A major. drainageway runs -eastward across the property from the unplatted land to the Mountaire Subdivision. The drainageway collects all existing runoff from the area and is unimproved. There is an existing retention pond near the southeast corner of the property. Although the pond becomes submerged and overtopped during the 100-year storm, it is not of sufficient size to be included as a detention area. J Existing runoff calculations were performed to determine the 2- and 100-year runoffs for the site using the Storm Water Management Model (SWMM, UDFCD 1985). A schematic showing the linkages of the subbasins and conveyance elements for the existing conditions is shown in Figure 2. The overall basin is shown in Figure 3. Both figures contain information from the West Plum Street Master Drainage Plan SWMM model. The hydrologic analysis used the Master Plan SWMM model with those subbasins representing the Waldorf School area altered to reflect existing conditions. Runoff leaves the site only through the drainageway. Although the Master Plan contains a large detention pond as part of the proposed Scenic Views development, it is our understanding that the pond has not been approved or constructed at this time. Existing condition SWMM models were developed with and without the Scenic Views development and detention pond in order to determine the highest flow condition through the site. For the 100-year storm, results indicate 103 cfs with the Scenic Views development and 89 cfs without the Scenic Views development (flows shown for element 61). Ayres Associates TABLE OF CONTENTS INTRODUCTION..................................................................................................................1 PREVIOUSSTUDIES...........................................................................................................1 EXISTING DRAINAGE CONDITIONS..................................................................................1 PROPOSED DRAINAGE CONDITIONS...............................................................................5 STORM DRAINAGE FACILITIES.........................................................................................5 EROSIONCONTROL PLAN.................................................................................................9 LIST OF FIGURES Figure1. Vicinity map.....................................................................................:....................2 Figure 2. Existing conditions and master plan SWMM network............................................3 Figure 3. Overall West Plum Street Basin............................................................................4 Figure 4. Proposed conditions SWMM network...................................................................6 Figure 5. Construction schedule.........................................................................................11 LIST OF TABLES Table1. Subbasin Constants...............................................................................................7 Table2. Basin Parameters...................................................................................................7 Table 3. Conveyance Elements and Peak Discharges.........................................................8 Table 4. SWMM Results Comparison..................................................................................8 Table 5. Detention Pond 179 - Outlet Rating Curve.............................................................9 i Ayres Associates /SIRES ASSOCIATES February 10, 1998 Mr. Basil Hamdan City of Fort Collins Stormwater Utility 235 Mathews Street Fort Collins, Colorado 80524 Re: River Song. Waldorf School Dear Basil, Enclosed please find our "Preliminary Drainage and Erosion Control Report For River Song Waldorf School." This report was prepared in accordance with the City of Fort Collins Storm Drainage Criteria as revised in January 1997. We appreciate your time and consideration in reviewing this submittal. Please call if you have questions. Sincerely, Owen Ayres & Associates, Inc. �� CI Chris Carlson, E.I.T. Civil Engineer r Lyle W. Zevenbergen, Ph.D., P.E. Hydraulic Engineer CC/LWZ/sp Enclosure u C Owen Ayres & Associates, Inc. Engineers/Scientists/Surveyors HAMD-2A.LTR 3665 JFK Parkway, Building 2, Suite 300, P.O. Box 270460, Fort Collins, CO 80527 34-0615.01 (970) 223-5556, Denver Metro (303) 572-1806, FAX (970) 223.5578 Printed on recycled paper PRELIMINARY DRAINAGE AND EROSION CONTROL REPORT FOR RIVER SONG WALDORF SCHOOL Prepared for River Song Waldorf School Fort Collins, Colorado AV ■ as ASSOCIATES P.O. Box 270460 - Fort Collins, Colorado 80527 (970) 223-5556, FAX (970) 223-5578 Ayres Project No. 34-0615.01 WALDORF2.TXT February 1998