HomeMy WebLinkAboutPROSPECT INDUSTRIAL PARK, LOT 15 - PDP - 28-98 - CORRESPONDENCE -V�•
d. On -site detention may be required and would have a 2-year release rate
or less if downstream restrictions dictate it. The downstream street
capacity may be limiting the site release rate.
e. The applicant was give a copy of the old drainage plan for the area that
was prepared by Stewart & Associates.
Please contact Glen, at 221-6065, if you have questions about these comments.
7. This development request will be subject to the Development Review Fee
Schedule that is available in the Current Planning Department office. The fees
are due at the time of submittal of the required documents for the Overall
Development Plan, Project Development Plan, and Final Compliance phases of
development review by City staff and affected outside reviewing agencies.
8. This development proposal is subject to the requirements as set forth in the
City's LUC, specifically Articles 2. Administration (Development Review
Procedures), Article 3. General Development Standards, and Article 4. [Zoning]
Districts.
C. The required number of parking spaces for each building is set forth in
Section 3.2.2(K)(3) of the LUC.
d. All parking lots must provide a minimum of 6% interior landscaping.
Please contact Jenny, at 221-6767, if you have questions about these
comments.
5. Roger Buffington of the Water/Wastewater Department offered the following
comments:
a. There is an existing 6" water main in Midpoint Drive.
b. There is an existing 8" sanitary sewer main in Midpoint Drive. There is an
existing 42" sanitary sewer main that cuts diagonally through the property.
A 30' wide utility easement (15' either side of the main) must be
maintained for this large sewer main.
C. There are some existing utility services stubbed into this site that must
either be used with the new development or abandoned back at the
mains.
d. The City's water conservation, standards for landscaping and irrigation
systems will apply to this site. Information on these standards can be
obtained at the Water Department and the Current Planning Department.
d. Plant investment fees and water rights will apply to this development and
they will be due at time of issuance of building permits.
Please contact Roger, at 221-6681, if you have questions about these
comments.
6. Glen Schlueter of the Stormwater Utility offered the following comments:
a. The site is located within the Poudre River Basin, which currently does not
have any new development fees. The site is also located within inventory
grid #12K.
b. The standard drainage and erosion control resorts and plans are required
and they must be prepared by a professional engineer registered in the
State of Colorado.
C. Water quality needs to be considered and addressed in some way.
Extended stormwater detention is a recommended method.
development and a hydrant must be within 300' of each building. Both buildings,
being in excess of 5,000 square feet, must be compartmentalized or equipped
with fire sprinkler systems. Please contact Ron, at 221-6570, if you have
questions about his comments.
3. Sheri Wamhoff of the Engineering Department offered the following comments:
a. A Transportation Impact Study (TIS) is required with your Project
Development Plan (PDP) submittal. Please contact Eric Bracke of Traffic
Operations, at 221-6062, to schedule a "scoping" meeting to discuss the
information needed in the analysis.
Also, there is a Multi -Modal Level of Service Study (pertaining to bicycle,
pedestrian, and transit modes) that is required as part of your TIS. Please
contact Kathleen Reavis of Transportation Planning, at 224-6140, for
information on this study.
b. This development proposal must meet the City's street standards. The
spacing of driveway access points will be evaluated with a development
proposal. All driveways into the site must be set back a minimum of 10'
from a side property line.
c. Street.oversizing fees will apply to this development. New fees were
recently approved by City Council, and they are now based on vehicle trip
generations by the development. The fees are $3.70/square foot for office
uses and $0.74/square foot for warehouse uses and will be collected at
the time of issuance of building permits.
d. The standard utility plan requirements must be submitted to.the City for
review and approval.
e. This development will be responsible for constructing all sidewalks on -site
and off -site along Midpoint Drive if they are not already in.
Please contact Sheri, at 221-6750, if you have questions about these comments.
4. Jenny Nuckols of the Zoning Department offered the following comments:
a. The property is in the I - Industrial Zoning District. The proposed uses are
permitted in this District, subject to administrative (Type 1) reviews.
b. The proposed building would be subject to the. building orientation and
build -to lines requirements as set forth in Section 3.5.3 of the Land Use
Code (LUC).
MEETING DATE: March 30, 1998
ITEM:
APPLICANT:
LAND USE DATA:
Lot 15, Prospect Industrial Park
Joe Frye
Vaught -Frye Architects
1113 Stoney Hill Drive
Fort Collins, CO. 80525
Request for a mixed use office/warehouse facility in two 1-story buildings on Lot 15 of
the Prospect Industrial Park located on the northeast side of Midpoint Drive in the
industrial park. The proposal is for a 6,500 square foot building and a 7,500 square foot
building on a 1.37 acre lot. The property is in the I - Industrial Zoning District.
COMMENTS:
1. Bruce Vogel of the Light & Power Department offered the following comments::
a. There are existing electric mains and services in the area along the other
side of Midpoint Drive.
b. The normal electric development charges will apply to this project.
C. There will be separate development charges for each portion of Lot 15
when it is subdivided and/or developed.
d. Two separate transformers may be necessary, one for each building.
They must be located no more than 10' from a paved area that can be
accessed by Light & Power trucks. Please coordinate the transformer
locations with the City.
Please contact Bruce, at 221-6700, if you have questions about these
comments.
2. Ron Gonzales of the Poudre Fire Authority stated that there could be
emergency (vehicle) access and water supply issues associated with this
development proposal. Also, fire hydrants must be spaced at 600' in the
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO80522-0580 (970) 221-6750
CURRENT PLANNING DEPARTMENT
Commi ty Planning and Environmental rvices
Current Planning
RECER'LO J"I'MY 1 2.1991
City of Fort Collins
April 10, 1998
Joe Frye
Vaught -Frye Architects
1113 Stoney Hill Drive
Fort Collins, CO. 80525
Dear Joe,
For your information, attached is a copy of the Staffs comments concerning the request
for Lot 15, Prospect Industrial Park, which was presented before the Conceptual
Review Team on March 30, 1998.
This is a request for a mixed use office/warehouse facility in two 1-story buildings on Lot
15 of the Prospect Industrial Park located on the northeast side of Midpoint Drive in the
industrial park. The proposal is for a 6,500 square foot building and a 7,500 square foot
building on a 1.37 acre lot. The property is in the I - Industrial Zoning District.
The comments are offered informally by Staff to assist you in preparing the detailed
components of the project application. Modifications and additions to these comments
may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in the
review process, please feel free to call me at 221-6750.
Sincerely,
ISSeolt
Project Planner
xc: . Stormwater Utility/Glen Schlueter
Streets/Eric Bracke
File