1.9 The City Planner stated the Neighborhood Resources department could City Planner to
be of assistance with contact persons for any neighborhood associations provide
that may have interest in the Project. Architect
contacts
1.10 The Civil Engineer indicated an item of immediate and substantial Civil Engineer
concern for both design and cost considerations is the proposed lowering will discuss
of LaPorte and Howes streets. There are significant issues involving the storm drain
grading of the site and the elevation of the building. This is part of a masterplan
long standing discussion and study regarding the storm drainage system with Storm
for the downtown area. It was determined the Civil Engineer will contact Water
Bob Smith at the Storm Water Department to ascertain what provisions if department
any of this ongoing study are applicable to this Project.
1.11 The City Planner distributed submittal requirements guidelines for the Information
ODP, PDP and Subdivision plat submittal requirements to the Architect
and Landscape Architect.
DATE OF NEXT MEETING
No specific date was established for the next Planning Department meeting.
CFJBA Meeting Report Page3
The document represents our understanding of subjects discussed, decisions reached, and action to be taken. If any items are not to your
understanding, please advise this office.
Larimer County Courthouse
Planning Department Meeting #1
PROJECT 9801.000
Date 24-Feb-98
the current Courthouse Basement and First Floors to verify adequate
clearance between the building and the lot lines.
1.3 The Facilities Director stated that vacation of all the alleys on Block 31 is Information
currently scheduled for both initial reading and hearing dates before the
City Council on March 17 and April 1 respectively.
1.4 The City Planner stated that there are no set back requirements in the Information
Civic Center sub district and that proximity to the property lines being
defined by the City and County will not be a problem as far as set back
requirements are concerned.
1.5 The City Planner stated that due to the phased nature of the site
development anticipated, he recommended that an Overall Development
Plan (ODP) be provided. This is a "bubble diagram" type drawing
depicting the projected uses on the site. The City Planner suggested the
use descriptions - in accordance with the Land Use Code - be provided
but building envelops, areas, and heights are not required. Possible
pedestrian and vehicular circulation such as future curb cuts and
pedestrian paths should be indicated as they relate to the overall site
masterplan.
1.6 The City Planner indicated that it is acceptable to submit the ODP
concurrently with the Project Development Plan (PDP).
1.7 Since the Conceptual Review Meeting has already been held for this
Project, the next step is neighborhood notice and the Neighborhood
Meeting. The City Planner will forward a map of the area adjacent to the
Project site which will indicate the area where Land Owner notification is
required. The Applicant then will provide mailing labels for each land
owner within the notification area for the Planning Department to use in
mailing the appropriate notices. The Planning Department will assess a
fee of $.50 per name for processing the notifications.
Information
Information .
City Planner to
provide map of
notification
area
1.8 Once the Land Owner notifications are sent out, the City Planner will Facilities
schedule a Neighborhood meeting to occur approximately two weeks Director to
later. The City Planner recommended any traffic study work currently in verify traffic
progress be shared at the Neighborhood meeting by the Traffic Planning planning
Consultant.
CFJBA Meeting Report Paget
The document represents our understanding of subjects discussed, decisions reached, and action to be taken. If any items are not to your
understanding, please advise this office.
C.W. FENTRESS J.H.
BURN
MEETING ARCHITECTURE, INTERIORRS, PLANNINGD ASSOCIATES, P.C.
421 BROADWAY PHONE: (303) 722-5000
90
REPORT E-MAIL , DRESS:DO80203 FAX: brad um.c m
E-MAIL ADDRESS: studio@fentressbradburn.com
WORLD WIDE WEB: www.fentressbradbum.com
PROJECT: New Larimer County Courthouse ` PROJECT No: 9801.000
Planning Department Meeting #1
LOCATION: Planning Department
281 North College
Fort Collins, CO
AUTHOR: Brian Chaffee
PRESENT: Ted Shepard
Dave Spencer
Rob Von Uffelen
Jana McKenzie
Greg Billingham
Brian Chaffee
COPIES TO: Jerry Pault
Alan Bliesmer
Conference Room DATE OF 24-Feb-98
MEETING:
DATE PRINTED: 26-Feb-98
Fort Collins Planning Department
Larimer County Facilities Director
Parsons & Associates, Inc.
EDAW, Inc.
C.W. Fentress J.H. Bradburn and Assoc., P.C.
C.W. Fentress J.H. Bradburn and Assoc., P.C.
Hensel Phelps Construction Company
Hensel Phelps Construction Company
The purpose of this meeting was to discuss the site ownership issues, the limits of consideration for
the site subject to planning approval and the initial details of the Planning Department approval
process itself for the Block 31 planning effort.
OLD BUSINESS
None
NEW BUSINESS
1.1 The County Facilities Director stated that though the City and the County
are in ongoing discussions regarding the actual split of the entire property
into their respective ownership it has been generally agreed that the
County will retain full ownership of lots 13 through 23 including the full
width of the alley west of these parcels and lots 24 through 29. The
further division of the remaining property on Block 31 is yet to be
determined.
1.2 The Architect recommended maintaining some flexibility in the property
delineation as the building design is still fluid and there appear to be
areas where the property line may be close to the building. The Facilities
Director indicated the agreement between the City and County will
maintain some flexibility. The Architect will overlay the lot lines with
ACTION BY
ACTION BY
Information
Arch to
provide lot line
layout overlain
on the current
design