HomeMy WebLinkAboutCOURTYARD COMMONS - PDP - 38-98 - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTVICINITY MAP
1 "= 2000'
APPENDIX
REFERENCES
1. Storm Drainage Design Criteria and Construction Standards.
City of Fort Collins, Colorado, May, 1984.
2. Drainage Criteria Manual. Urban Drainage and Flood Control
District, Wright -McLaughlin Engineers, Denver, Colorado,
March, 1969.
3. Final Drainage and Erosion Control Study for JFK Parkway, by Parsons &
Associates, dated May 19, 1992
4. Final Drainage and Erosion Control Study for Shopko. by TST
5. Final Drainage and Erosion Control Study for the Landings, by Northern
Engineering Services
I
I
1
1
I
1
1
I
L
1
.1
I
1
I
Drainage Conceit
The proposed drainage concepts presented in this study and shown on the grading and
drainage plans adequately provide for the conveyance and detention of developed runoff from the
proposed development.
If groundwater is encountered during construction, and dewatering is used to install
utilities, a State of Colorado Construction Dewatering Wastewater Discharge Permit will be
required.
Stormwater OualitX
Because water quality is important to this developer, water quality mechanism will be
incorporated into all aspects of final design of drainage systems.
Erosion Control Concepts
Per the City of Fort Collins Erosion Control Reference Manual for Construction Sites, at
the time of Final Design, the erosion control performance standard will need to be calculated and
appropriate measures taken to control rain and wind erosion from the site
1
I
I
constructed as a part of this project, to direct emergency spills to the Latimer No. 2.
Since construction, the existing pond has been revegetated and will provide a significant
water quality component to this project, as well as the other developed flows entering the pond. It
is therefore our opinion, that this pond should not be disturbed for the addition of temp siltation
pond.
IV. EROSION CONTROL
General Conceut
Courtyard Commons lies within the Moderate Rainfall Erodibility Zone, and the
Moderate Wind Erodibility Zone, per the City of Fort Collins zone maps. The desired
effectiveness goal for this site was estimated to be approximately 85%
The intent ofthe erosion control plan for the site include the following guidelines. As
these measures can vary depending on the time of year construction activities take place, as well
as the construction window involved, we would look to the contractor to work closely with the
City to insure the intent of the plan is generally complied with.
It is the intent of the owner to move quickly ahead with development once overlot
grading `takes place. It is anticipated that overlot grading would start sometime around January,
1999, or sooner if possible. Therefore, once overlot grading and utilities have been completed,
the owner would like to restabilize all disturbed areas, either with vegetative means, or by hard
surfaces. In no cases shall restabilization occur more than 30 days after disturbance.
In addition; silt fence will be provided around most of the exterior of the disturbed areas;
gravel inlet filters will be installed at all curb inlets, curb openings, and pipe entrances. Straw
bale check dams will be placed in all open channels, at a minimum of 250' intervals. Temporary
vehicle wash pads will be located at the anticipated construction traffic entrances to the site.
All construction activities must also comply with the State of Colorado permitting process
for Stormwater Discharges associated with construction activities. A Colorado Department of
Health NPDES discharge permit will be required before any construction grading can begin.
V. CONCLUSIONS
Compliance with Standards
11 All computations within this report have been completed in compliance with the City of
Fort Collins Storm Drainage Design Criteria.
I
Developed flows from subbasins .C-9 and 10 will be directed towards the south, and will
be intercepted by area inlets, and directed to the existing detention pond, detained, and released
into the Larimer No. 2
Subbasins C-11 and C-12 represent those area adjacent or including the detention pond.
Developed flows from these subbasins will be directed via surface flows to the pond, where
storage capacity has been verified, and ultimately in to Latimer No. 2.
Subbasin LC-1 represents that portion of the site, which is adjacent to and includes the
Larimer No. 2. This area will not be disturbed, and will be allowed to continue to sheet flow to
the canal. Peak runoff was calculated to be approximately 4.3 cfs. These flows were subtracted
from the allowable release rate for the site identified by the JFK Parkway drainage study by
Parsons & Associates, approved by the City
Subbasins D2 and D3 correspond to the subbasins identified in the Landings drainage
study by Northern Engineering. Developed runoff from Subbasin D2 (Landings Drive), including
portions of the Landings project, will be conveyed to the north via curb and gutter to an existing
inlet located at the proposed driveway section for Courtyard Commons. This is currently a Type
R inlet, which will be reconstructed as am area inlet, will still intercept these flows, convey them
through the High Pointe detention facility, and ultimately to the Larimer No. 2. Developed flows
from subbasin D3 (JFK Parkway) are conveyed to the south via curb and gutter to an existing 15'
curb inlet located at the comer of JFK and Boardwalk. This project does not significantly increase
the flows to this inlet.
A subbasin has been identified on our plan as subbasin LD2, which represents that portion
of Landings Drive, currently existing, which is not intercepted by the curb inlet, and which
currently is conveyed to the north via curb and gutter. This project does not significantly affect
the performance or nature of these flows.
Subbasins JFK 19 2 and 3 represent basins associated with JFK Parkway and roughly
approximate basins A, E, and F identified in the Parsons study for JFK Parkway. Detention for
these basins is being provided in the existing detention pond. A new curb inlet (32.5' Type R) will
be constructed at the northerly boundary of basin JFK1, and will intercept the majority of the
flows from JFK1, as well as C-1,2,3. The remainder will continue north to an existing curb inlet
located at the Latimer No. 2. All of the developed flows will be conveyed to the existing pond,
and released into the Latimer No. 2.
The existing pond, referred to in the Parsons study as pond B, has been certified as a part
of the Shopko project, and volume has again been checked as a part of this study. The allowable
release rate from the pond was identified to be 12.54 cfs. The Shopko project will be allowed to
bypass approximately 5.02 cfs through the pond. Subbasin LC 1 is free releasing into the canal.
This results in an allowable release from our site of 3.22 cfs, which was the basis of our volume
verification. The 100 year WSEL was determined to be approximately 30.51. The pond would
currently overflow at approximate elevation 30.85. Detention storage provided to elevation 30.51
was calculated to be approximately 1.192 acre feet. An emergency overflow weir will be
M. DEVELOPED DRAINAGE
Design Criteria and References
Drainage criteria outlined in both the City of Fort Collins Storm Drainage Design Criteria
Manual. and Storm Drainage Criteria Manual by the Urban Drainage and Flood Control District
have been used for this,Drainage Study.
Hydrologic Criteria
The Rational Method was used to estimate peak stormwater runoff from the proposed site.
The 10 year storm event and the 100 year storm event was used to evaluate the proposed drainage
system. Rainfall intensity data for the Rational method was taken from the City of Fort Collins
Stormwater Utility Intensity curves (Figure 3-1).
Hydraulic Criteria
City of Fort Collins Storm Drainage Criteria has been used for all hydraulic calculations.
In addition, the detention volumes required for this development have been verified using the
FAA method for detention ponds developed by the UDFCD was used.
Drainage Concepts
The site has been broken down into 12 smaller subbasins onsite, as well as 6 subbasins
adjacent to the site.
Subbasins C-1, 2, and 3 represent the majority of the office park portion of the project.
Developed runoff from these basins will be directed towards the center of the parking area, and
conveyed'via concrete pans, curb openings, and sidewalk culverts to JFK Parkway. At JFK, these
flows will combine with the developed flows from JFK1, and be conveyed north to a proposed
32.5' type R curb inlet to be constructed at the northernmost limits of the new curb and gutter
being installed with this project. Ultimately, detention is being provided in the existing pond, and
the detained flows from these basins, as well as JFK 1, will be released into the Larimer No. 2.
Developed flows from subbasins C-4 and 5 will be conveyed via curb and gutter towards
the center of the site and will be intercepted by a proposed Type C area inlet. Flows from the area
inlet will be piped to the existing detention pond, detained, and released into the Larimer No. 2.
Developed flows from subbasins C-6, 7 and 8 will be conveyed towards the center of the
site via curb and gutter, and intercepted in a proposed 15' Type R curb inlet. Along with the
developed flows from C-4 and 5, these flows will be conveyed to the existing detention pond,
detained, and released into the Larimer No. 2
Final Drainage Report
for the
Courtyard Commons PUD
I. GENERAL. LOCATION AND SITE DESCRIPTION
The Courtyard Commons PUD project is located North of the Landings project, North of
Boardwalk Drive, East of JFK Parkway, and west of Landings Drive. The site is also bounded
on the north by the Larimer Canal No. 2. The site can also be described as a portion of Section
36, Township 7 North, Range 69 West of the 6th PM, City of Fort Collins, Larimer County,
Colorado. A vicinity map of the site is included in the appendix of this report.
This site includes approximately 6.32 acres, including the adjacent roadways. The site is
presently undeveloped, and consist mainly of native grasses. As mentioned above, the Landings
Office Park is currently being constructed on the south side of this site. The site generally slopes
from the south to the north at slopes less than 4%. There is also an existing detention pond
located on the site which was constructed with the Shopko project. This pond is referred to in the
Parsons study as Pond B.
Plans for this site include multi -family residential buildings, with associated parking and
garages, and 5 additional office buildings, similar to the product currently being constructed in
the Landings.
H. IUSTORIC DRAINAGE
As mentioned above, the site is presently undeveloped, and consists mainly of native
grasses and vegetation. JFK Parkway has been fully developed on the west side of the site, and
will be widened with this project. Landings Drive has also been fully developed, and will remain
essentially in tact as a result of this project. The Landings is currently being constructed on the
south side of this project.
Currently, runoff will be conveyed to the existing Larimer Canal No. 2, and to the
existing pond constructed with Shopko. Runoff from Landings Drive, to the approximate new
driveway to Courtyard Commons will be intercepted by an existing curb inlet, and routed
through the High Pointe detention pond to Larimer Canal No. 2. The remainder of Landings
Drive, approximated by LD2 continues to flow north across the Larimer No. 2 to the north.
Flows from JFK Parkway flows to the north to an existing curb inlet at the Larimer No.
2, through the existing pond, and to the Larimer No. 2.
August 7, 1998
Mr. Glen Schlueter
City of Fort Collins
Stormwater Utility
I 700 Wood Street
Fort Collins, Colorado 80522
RE: Courtyard Commons P.U.D.
Fort Collins, Colorado
' Project Number: 9837.00
1 Dear Glen:
Northern Engineering is absolutely ecstatic to submit this Final Drainage Report
' for the Courtyard Commons for your review. It represents a study of existing and
proposed stormwater characteristics of the project site.
This report was prepared in compliance with technical criteria set forth in the, City
Of Fort Collins, Storm Drainage Design Criteria and Construction Standards manual.
If you should have any questions or comments as you review this report, please
feel free to contact me at your convenience.
1
Sincerely,
NORTHERN ENGINEERING SERVICES, INC.
Roger A. Curtiss, P.E.
cc: Jon Prouty
420 SOUTH HOWES, SUITE 202, FORT (OLLINS, (OLORADO 80521, (970) 221-4158, FAX (970) 221-4159
Final Drainage Report
for
Courtyard Commons P.U.D.
Fort Collins, Colorado
August 5, 1998
Prepared For:
Lagunitas Companies
3307 South College Ave
Suite 200
Fort Collins, Colorado 80525
Prepared By:
Northern Engineering Services, Inc.
420 South Howes, Suite 202
Fort Collins, Colorado 80521
(970)221-4158
Fax(970)221-4159
Project Number: 9837.00
1st Submittal
Final Drainage Report
for
Courtyard Commons P.U.D.
j Fort Collins, Colorado
August 5, 1998
0
ENGINEERING