HomeMy WebLinkAboutCAPSTONE COTTAGES - PDP - PDP140004 - CORRESPONDENCE -Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals(cDfcgov.com
Topic: General
Comment Number: 4 Comment Originated: 01/14/2015
01/14/2015: The one central trash and recycling location for the entire project does
meet code. Please provide further details as notes on the site plan that discuss the
convenient trash and recycling pickups.
Comment Number: 5 Comment Originated: 01/14/2015
01/14/2015: Are the raised cross walks acceptable by other interests of the project?
Comment Number: 6 Comment Originated: 09/15/2015
09/15/2015: Eaves are allowed to encroach a setback 2.5 feet LUC 3.8.19(A)(6).
Post of the porch is required to meet the setback.
Comment Number: 7 Comment Originated: 09/15/2015
09/15/2015: The project t is meeting the Handicap spaces. However, the location of
the handicap space near the maintenance building may be under used.
There are not handicap spaces near the Club house, perhaps this would be a better
location for one.
Comment Number: 8 Comment Originated: 09/18/2015
09/18/2015: Please add street tress along Lemay. Please include the landscaping
around the detention pond and round about when design details are complete.
Please add trees in along the drive from Duff
Page 20 of 20
Topic: General
Comment Number: 1 Comment Originated: 05/28/2014
01/15/2015: The site plan is difficult to verify if the stop shown meets our needs for
ADA accessibility. Please revise the plan to show the bus stop upgrades we have
discussed on phone calls and in the Staff Review meeting. I have also provided
some example stop designs for your review, this stop needs to be a type II I stop.
Take a look at the options and choose the one that works best for you. Due to line
of sight concerns and potential traffic back up in the roundabout, please move the
stop to the west side of the drive aisle into the development. I'm happy to discuss
this further to help out as needed.
05/28/2014: The City of Fort Collins values providing accessible transportation
options to all residents and in accordance with the LUC Section 3.6.5 all new
development shall provide ADA accessible bus stop facilities in appropriate
locations. The location of this project is served by one existing route on Lincoln
Avenue and one planned route on Future Lemay Avenue. Please provide a bus stop
pad on Lincoln Avenue, approximately 50'-80' west of International Boulevard and
one just north of the property line on Future Lemay Avenue. The bus stop pads shall
be 22' wide adjacent to the street and 12' deep, they need to be attached to the
sidewalk and curb and be within the public right-of-way or in a Transit Easement.
Please refer to Larimer County Urban Area Street Standards detail 711 for more
information and feel free to contact me if you need assistance locating the stops.
Comment Number: 2 Comment Originated: 01/15/2015
01/15/2015: Please also include the bus stop on the opposite side of the street.
Comment Number: 2 Comment Originated: 01/15/2015
01/15/2015:
Department: Water -Wastewater Engineering
Contact: Basil Hamdan, 970-224-6035, bhamdan(a)fcgov.com
Topic: Construction Drawings
Comment Number: 4
Comment Originated: 09/17/2015
09/17/2015: Please differentiate between City of Fort Collins sewer lines, by calling
out all publicly owned COFC lines on the plans, differentiating them from private
utilities or ELCO lines.
Topic: General
Comment Number: 2
Comment Originated: 01/13/2015
01/13/2015: Please add notes on the cover sheet to show that sanitary sewer
service for this site is provided by City of Fort Collins Utilities and water service is
provided by ELCO. Please update the contact list names for Fort Collins Utilities as
it is outdated.
Topic: Plat
Comment Number: 1
Comment Originated: 01/13/2015
05/29/2014: Minimum easement width for sanitary sewer is 30 feet (15 feet each
side of the sewer). This will apply to the existing sewer crossing the site and the
new proposed sewers.
Comment Number: 3
Comment Originated: 09/17/2015
09/17/2015: The plat shows that these units will be platted as single family attached
lots. City code requires a sewer service be extended to each property which would
require that each single family attached unit have a separate sewer service. City
staff will consult with the City Attorney's Office and investigate this code requirement
and how it applies in this case.
Page 19 of 20
Comment Number: 10
Comment Originated: 05/27/2014
09/17/2015: There is still text that needs to be masked. Mask all text in hatched
areas. See redlines.
01/14/2015: There are still masking issues. See redlines.
05/27/2014: Please mask all text within hatched areas, or as marked. See redlines.
Comment Number: 11
Comment Originated: 05/27/2014
09/17/2015: There are still line over text issues. See redlines.
01/14/2015: There are still line over text issues. See redlines.
05/27/2014: There are line over text issues. See redlines.
Comment Number: 47
Comment Originated: 09/18/2015
09/18/2015: The titles in the sheet index do not match the titles on the noted sheets.
See redlines.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinsonMcnov.com
Topic: Site Plan
Comment Number: 5
Comment Originated: 01/14/2015
01/14/2015: The TIS acknowledges the need for a southbound right turn lane at
Lemay / Lincoln, and this development is currently proposing to add 15% to that
movement. This improvement is not shown in the plans. Will this be a variance
request?
Comment Number: 6
Comment Originated: 01/14/2015
01/1412015: This TIS acknowledges that at the site access and Lemay the
northbound right turn will warrant a right turn lane. The warrant is 40. The proposed
turns are 106. The TIS recommends not installing the lane since it is 'temporary'.
Will this be a variance request?
Comment Number: 9
Comment Originated: 01/14/2015
01/14/2015: The long term geometry at new Lemay and Duff includes a northbound
right turn lane and a westbound left turn lane. The ultimate layout (and ROW
dedicated now) should accommodate this, and Duff should be built for this.
Comment Number: 10
Comment Originated: 01/14/2015
01/14/2015: There is some parking shown to be very close to intersections. (Such
as site access to new Lemay). Are parking setbacks to ROW met? Throat
distances to major intersecions (such as Lemay and International) should be
reviewed.
Topic: Traffic Impact Study
Comment Number: 7
Comment Originated: 01/14/2015
01/14/2015: The TIS acknowledges that the pedestrian LOS is not met. Additional
information on what is not met, why, and to what extent Capstone IS providing ped
facilities I think will be needed as the project moves forward.
Comment Number: 8
Comment Originated: 01/14/2015
01/14/2015: The TIS notes that three intersection do not meet LOS standards.
Additional information/narrative/explanation on these specific intersections, and to
what extent Capstone is impacting these intersections (especially
Lemay/Buckingham and LemayNine) I think will be needed as the project moves
forward.
Department: Transportation Planning
Contact: Emma Belmont, 970-224-6197, ebelmontcDfcaov.com
Page 18 of 20
Comment Number: 31 Comment Originated: 09/17/2015
09/17/2015: Please make sure that all Lots, Tracts & Outlots are labeled on all
sheets. See redlines.
Comment Number: 32 Comment Originated: 09/17/2015
09/17/2015: Please label all surrounding properties with "Unplatted" or the
subdivision name. This includes properties across right of ways. See redlines.
Comment Number: 33 Comment Originated: 09/17/2015
09/17/2015: Should the little triangle noted on sheet 2 be conveyed to other owner?
See redlines.
Comment Number: 34 Comment Originated: 09/17/2015
09/17/2015: All easements must be labeled & locatable. See redlines.
Comment Number: 35 Comment Originated: 09/17/2015
09/17/2015: All internal Lots must be tied to the Plat boundary in some way.
Comment Number: 36 Comment Originated: 09/18/2015
09/18/2015: There are line over text issues. See redlines.
Comment Number: 37 Comment Originated: 09/18/2015
09/18/2015: Specific names are needed for the ownership in the Land Use Table.
See redlines.
Comment Number: 38 Comment Originated: 09/18/2015
09/1812015: Please add dedication information for all street rights of way. See
redlines.
Comment Number: 39 Comment Originated: 09/18/2015
09/18/2015: Is International Blvd. the correct name for the street running along the
east side of the property?
Comment Number: 40 Comment Originated: 09/18/2015
09/18/2015: Please add "Matchline" to the lines on sheets 2 & 3. See redlines.
Comment Number: 41 Comment Originated: 09/18/2015
09/18/2015: Please remove "Proposed Right Of Way", and add "EAE" to the
legend. See redlines.
Comment Number: 42 Comment Originated: 09/18/2015
09/18/2015: What is the line noted along Lot 5? is this the Sight Distance
Easement? See redlines.
Comment Number: 43 Comment Originated: 09/18/2015
09/18/2015: Please add bearings and/or distances as marked. See redlines.
Comment Number: 44 Comment Originated: 09/18/2015
09/18/2015: Please remove all mark lines on sheet 3. See redlines.
Comment Number: 45 Comment Originated: 09/18/2015
09/18/2015: All reception numbers for documents recorded by separate document,
must be added prior to producing mylars.
Comment Number: 46 Comment Originated: 09/18/2015
09/18/2015: Please show what was reset for the easterly boundary corner as noted
on sheet 3. See redlines.
Topic: Site Plan
Page 17 of 20
Topic: Building Elevations
Comment Number: 1 Comment Originated: 05/27/2014
09/17/2015: There are still line over text issues. See redlines.
01/13/2015: There are still line over text issues. See redlines.
05/27/2014: There are line over text issues. See redlines.
Comment Number: 12 Comment Originated: 01/13/2015
09/17/2015: There is still text that needs to be masked. Mask all text in hatched
areas. See redlines.
01/13/2015: There is text that needs to be masked. See redlines.
Comment Number: 25 Comment Originated: 09/17/2015
09/17/2015: Please add the title of "Capstone Cottages" to all sheets.
Comment Number: 26 Comment Originated: 09/17/2015
09/17/2015: There seem to be some sheets missing, or the sheet numbering is not
consecutive.
Topic: Construction Drawings
Comment Number: 4 Comment Originated: 05/27/2014
09/17/2015: There are still line over text issues. See redlines.
01/13/2015: There are still line over text issues. See redlines.
05/27/2014: There are line over text issues. See redlines.
Comment Number: 27 Comment Originated: 09/17/2015
09/17/2015: The titles in the sheet index do not match the titles on the noted sheets.
See redlines.
Topic: Landscape Plans
Comment Number: 28 Comment Originated: 09/17/2015
09/17/2015: The sheet numbering does not match the sheet references shown in
the sheet keys. See redlines.
Topic: Lighting Plan
Comment Number: 19 Comment Originated: 01/14/2015
09/17/2015: No plans were provided for review, so we cannot verify this was
addressed.
01/14/2015: There is text that needs to be masked. See redlines.
Topic: Plat
Comment Number: 23 Comment Originated: 01/16/2015
09/17/2015: Note #4 is contradictory. If it is not known whether or not there is a
Lienholder, please add a signature block. This can be removed later, if it is not
needed.
01/1612015: Are there any Lienholders for this property? If so, please add a
signature block. If not, please add a note stating there are none, and include
response in written comments.
Comment Number: 29 Comment Originated: 09/17/2015
09/17/2015: The Sight Distance Easement is not needed if there is no easement on
the Plat. See redlines.
Comment Number: 30 Comment Originated: 09/17/2015
09/17/2015: Please add the distance for the Basis Of Bearings. See redlines.
Page 16 of 20
Comment Number: 9
Comment Originated: 01/13/2015
1/13/2015: Please document the contributed flows from offiste drainage area to the
north of this site. Show how these will be routed through,
Topic: Landscape Plans
Comment Number: 12
Comment Originated: 09/15/2015
09/15/2015: The proposed detention pond along Lincoln Avenue does not meet the
spirit or the letter of the detention pond landscaping standards. The pond needs to
be naturally landscaped, less symmetrical, . An alternate design that emphasizes
the use of the pond as a multi -purpose amenity with a naturalized function and
some recreational use is recommeded. The City would like to participate in a
discussion on what can be done to enhance this facility prior to re -submittal.
Contact: Jesse Schlam, 970-218-2932, ischlam(a�fcgov.com
Topic: Erosion Control
Comment Number: 6
Comment Originated: 01/13/2015
09/09/2015: Repeat Comment - Saw acknowledgment
03/17/2015: Repeat Comment - Saw acknowledgment
01/13/2015: The site disturbs more than 10,000 sq-ft, therefore Erosion and
Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials Submitted
does not meet requirements. Please submit; Erosion Control Plan, Erosion Control
Report, and an Escrow / Security Calculation. If you need clarification concerning
this section, or if there are any questions please contact Jesse Schlam
970-218-2932 or email @ jschlam@fcgov.com
Contact: Wes Lamarque, 970-416-2418, wlamargue(oDfcgov.com
Topic: General
Comment Number: 14
Comment Originated: 11/09/2015
11/09/2015: Additional documentation is needed to determine if the site is meeting
the LID requirements. Calculations need to show how much of the site is being
treated with a LID technique. It has been discussed that the site needs to treat
100% of the site's impervious area before flows enter the detention basin and
wetland mitigation area.
The documentation needs to verify sizing of rain gardens for the area that drains to
them. For the porous pavers, documentation needs to show how much impervious
area drains onto the pavers and to make sure this area is not greater than 3 to 1.
Comment Number: 15
Comment Originated: 11/09/2015
11/09/2015: In general, the rain gardens used to meet the City's LID requirements
need to be sized for the areas that drain to them. Due to the site plan layout, if the
size and volume required is not able to be achieved, using other secondary LID
techniques in series can be allowed to help achieve this requirement for small
shortages.
Comment Number: 16
Comment Originated: 11/09/2015
11 /09/2015: The placement of the rain gardens should be in tracts and be within a
drainage easement that is maintained by a governing HOA. If this can not be
achieved, discussion needs to take place on how to ensure the maintenance of
these facilities and to ensure future compliance.
Department: Technical Services
Contact: Jeff County, 970-221-6588, icountyCo?fcgov.com
Page 15 of 20
Comment Number: 21
Comment Originated: 09/15/2015
09/15/2015: HYDRANT PLACEMENT
A hydrant is required within 300' of every building within the complex. That distance
is to be measured along the path of vehicle travel. Code language provided below.
The proposed plan shows some areas of deficiency in hydrant coverage. An
additional hydrant will be required as follows:
> In the area of the landscape island at the east end of the head -in parking, south of
Bldg. 16.
> In the area of the landscape island at the east end of the head -in parking, north of
Bldg. 38.
> Along Lemay Avenue, between old Lemay and International Blvd.
> IFC 508.1 and Appendix B: COMMERCIAL REQUIREMENTS: Hydrants to provide
1,500 glom at 20 psi residual pressure, spaced not further than 300 feet to the
building, on 600-foot centers thereafter.
Comment Number: 22
Comment Originated: 09/15/2015
09/15/2015: PUBLIC -SAFETY RADIO AMPLIFICATION SYSTEM
New buildings require a fire department, emergency communication system
evaluation after the core/shell but prior to final build out. For the purposes of this
section, fire walls shall not be used to define separate buildings. Where adequate
radio coverage cannot be established within a building, public -safety radio
amplification systems shall be designed and installed in accordance with criteria
established by the Poudre Fire Authority. Poudre Fire Authority Bureau Admin Policy
#07-01
Comment Number: 23
Comment Originated: 09/16/2015
09/16/2015: STREET NAMES
A plan for the naming of streets shall be submitted for review and approval by time
of final development plan. Monument signage and a plan for way finding within the
complex should be ready for review at that time as well.
Department: Stormwater Engineering
Contact: Basil Harridan, 970-224-6035, bhamdan(a)fcgov.com
Topic: Drainage Report
Comment Number: 13
Comment Originated: 09/17/2015
09/17/2015: Currently plans show offsite flows being routed through the detention
pond. Please discuss how this will affect detention pond design, allowing off site
flows to be routed over spillway rather than by increasing release rate.
Topic: Floodplain
Comment Number: 5
Comment Originated: 01/13/2015
05/30/2014:
Add notes to both the plat and the site plan, 1) The entire site is located within the
FEMA-regulatory Poudre River 500-year Floodplain (shaded Zone X). 2) At -Risk
Population and Essential Service Critical Facilities are not allowed within the limits of
the 500-year floodplain.
Topic: General
Comment Number: 2
Comment Originated: 01/13/2015
05/27/2014: Larimer County has to sign off on the release rate for this development
due to the outfall being the county maintained Lincoln Channel.
Comment Number: 8 Comment Originated: 01/13/2015
01/13/2015: Please make sure that the storm sewer crossing in International
Boulevard will meet the minimum cover requirements per LCUASS standards
Page 14 of 20
Comment Number: 17 Comment Originated: 09/15/2015
09/15/2015: BUILDINGS OVER 30' IN HEIGHT
Only five of the three-story building footprints meet access requirements for aerial
fire apparatus. Compliant buildings are #29,30,31,32,& 45. All other 3-story footprints
appear to exceed the 30' maximum distance to the edge of the fire lane. The
Clubhouse also exceeds 30' in height and needs to meet the same access
requirement. See code language below and also Appendix D of the 2012
International Fire Code for more details.
> AERIAL FIRE APPARATUS ACCESS ROADS - WHERE REQUIRED
IFC D105.1: Where the vertical distance between the grade plane and the highest
roof surface exceeds 30 feet, approved aerial fire apparatus access roads shall be
provided. For purposes of this section, the highest roof surface shall be determined
by measurement to the eave of a pitched roof.. the intersection of the roof to the
exterior wall, or the top of parapet walls, whichever is greater.
> AERIAL FIRE APPARATUS ACCESS ROADS - WIDTH
IFC D105.2; FCLUC 3.6.2(B)2006; and Local Amendments: Aerial fire apparatus
access roads shall have a minimum unobstructed width of 30 feet, exclusive of
shoulders, in the immediate vicinity of the building or portion thereof.
> AERIAL FIRE APPARATUS ACCESS ROADS - PROXIMITY TO BUILDING
IFC D105.3: At least one of the required access routes meeting this condition shall
be located within a minimum of 15 feet and a maximum of 30 feet from the building,
and shall be positioned parallel to one entire side of the building. The side of the
building on which the aerial fire apparatus access road is positioned shall be
approved by the fire code official.
Comment Number: 18 Comment Originated: 09/15/2015
09/15/2015: RESIDENTIAL AUTOMATIC FIRE SPRINKLERS
As of August 2014, full NFPA 13 sprinkler systems are required in multifamily
residential occupancies.
Comment Number: 19 Comment Originated: 09/15/2015
09/15/2015: CLUBHOUSE
The location of the clubhouse does not meet minimum standards for fire department
access. The building also exceeds 5000 square feet. As such, an automatic fire
sprinkler system will be required. Please contact Assistant Fire Marshal, Joe
Jaramillo with any fire sprinkler related questions at 970-416-2868.
Comment Number: 20 Comment Originated: 09/15/2015
09/15/2015: FDC
> IFC 912.2: Fire Department Connections shall be installed in accordance with
NFPA standards. Fire department connections shall be located on the street side of
buildings, fully visible and recognizable from the street or nearest point of fire
department vehicle access. The location of the FDC shall be approved by the fire
department.
Page 13 of 20
Comment Number: 2
Comment Originated: 01/14/2015
01/14/2015: Larimer County:
I have a new comment to include for this preliminary plat. I noticed that you have a
signature block for a total of three owners.
We have four owners and this is how they hold title: Technically the Ft Collins
Business Center holds title under two different ownerships.
87072-00-002 NORTH VALLEY BANK
87072-00-016 FT COLLINS BUSINESS CENTER ONE
87072-00-017 FT COLLINS BUSINESS CENTER TWO
87072-00-019 NIFOROS TONIA L
Also, just to touch base again on the difference in the parcels tax districts, which
encompass the new sub, I understand that there will be an order recorded for
exclusion from the Boxelder Sanitation District which will accomplish getting all the
parcels into one tax district. I'm hoping this gets done before your final recording of
this plat. If you have questions on the exclusion process, please contact Lisa Ford
in our office as she can answer any questions you may have on this process. Her
direct line is 970-498-7068.
Megan Harrity
Subdivisions Larimer County Assessor
970-498-7065
mharrity@larimer.org
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler(a)poudre-fire_org
Topic: General
Comment Number: 15
Comment Originated: 03/16/2015
03/16/2015: WATER SUPPLY
The installation of private hydrants require special approved and permitting from the
fire department. Private fire hydrants shall have an approved maintenance plan as
per IFC 507.5.3. Fire hydrants must be the type approved by the water district
having jurisdiction and the Fire Department.
Comment Number: 16
Comment Originated: 09/15/2015
09/15/2015: FIRE ACCESS
Minimum width of any fire lane serving a commercial property is 20'. The
Emergency Access Easement overlaid on the private drive connecting the property
from the west side of the complex to Lemay Ave is currently shown as 19'.
Page 12 of 20
Comment Number: 1 Comment Originated: 01/14/2015
01/14/2015: Boxeldder Sanitation.
Lisa Ford (Larimer County Assessor) was in touch with our office yesterday as
three parcels that are part of Capstone Cottages are in the Boxelder Sanitation
District. These parcels (individually) need to petition for exclusion from the District.
I am attaching the information you will need to provide to the property owners or you
may have them contact me. The soonest the petitions for exclusion could be
addressed is at the February 26 board meeting.
Here is the ownership and respective parcel number per the Larimer County
Assessor office. I suspect that ownership has changed and if so, please let me
know.
Parcel #87072-00-016 Ft Collins Business Center One
Parcel #87072-00-017 Ft Collins Business Center Two
Parcel #87072-00-019 Niforos, Tonia L
Pat
Patricia S. Mathena
Assistant Manager & Controller
XXXXXXXXXXXXXXXXXXXXXXXXXXXX
Boxelder Sanitation District
3201 E. Mulberry St., #Q
P. 0. Box 1518
Fort Collins, CO 80522
970-498-0604, 970-498-0701 Fax
PMathena@boxeldersanitation.org
Page 11 of 20
416-2341
Comment Number: 2 Comment Originated: 09/25/2015
09/25/2015:
Dwellings on individual lots must have utilities installed to each property without
crossing adjoiing property lines unless there is an access easement agreement to
allow such.
Department: Light And Power
Contact: Todd Vedder, 970-224-6152, tvedder(a)fcgov.com
Topic: General
Comment Number: 3 Comment Originated: 01/13/2015
01/13/2015: Transformer and meter locations will need to be coordinated through
City of Fort Collins Light and Power, 221-6700. Transformers will need to be within
10ft of paved surface.
Comment Number: 4 Comment Originated: 01/13/2015
01/1312015: Development charges will apply. An online development estimating
guide can be found at
http://www.fcgov. com/uti I ities/business/builders-and-developers/plant-investment-de
velopment-fees/electric-development-fee-estimator
Comment Number: 5 Comment Originated: 01/13/2015
01/13/2015: One -line diagram needs to be submitted for the clubhouse
Comment Number: 6 Comment Originated: 09/14/2015
9/14/2015: Please show public street lighting on the Landscape Plan to ensure
proper clearance requireemnts are met with ornamental and shaded trees
Department: Outside Agencies
Contact: Pete Wray, 970-221-6754, pwray(aifcgov.com
Topic: General
Page 10 of 20
Comment Number: 1 Comment Originated: 05/27/2014
Building Permit Pre -Submittal Meeting
Pre -Submittal meetings are offered to assist the designer/builder by assuring, early
on in the design, that the new commercial or multi -family projects are on track to
complying with all of the adopted City codes and Standards listed below. The
proposed project should be in the early to mid -design stage for this meeting to be
effective and is typically scheduled after the Current Planning conceptual review
meeting. Applicants of new commercial or multi -family projects are advised to call
416-2341 to schedule a pre -submittal meeting. Applicants should be prepared to
present site plans, floor plans, and elevations and be able to discuss code issues of
occupancy, square footage and type of construction being proposed.
Construction shall comply with the following adopted codes as amended:
2012 International Building Code (IBC)
2012 International Residential Code (IRC)
2012 International Energy Conservation Code (IECC)
2012 International Mechanical Code (IMC)
2012 International Fuel Gas Code (IFGC)
2009 International Plumbing Code (IPC) as amended by the State of Colorado
2011 National Electrical Code (NEC) as amended by the State of Colorado
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2009.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use
1. Single Family; Duplex; Townhomes: 2012 IRC Chapter 11 or 2012 IECC.
2. Multi -family and Condominiums 3 stories max: 2012 IECC residential chapter.
3. Commercial and Multi -family 4 stories and taller: 2012 IECC commercial
chapter.
Fort Collins Green Code Amendments effective starting 1-1-2012. A copy of these
requirements can be obtained at the Building Office or contact the above phone
number.
Capstone Cottages — project specific concerns:
1. Fire -sprinkler systems are required for R-2 multi -family. A new code amendment
effective in 2014 will require a full NFPA-13 sprinkler system and not allow a 13-R
system. In addition effective Aug1 all duplexes and property -line townhomes require
fire -sprinkler systems.
2. Bedroom egress windows required below 4th floor regardless of fire -sprinkler.
3. All windows above the 1st floor require minimum sill height of 24"
4. Building code and State statute CRS 9-5 requires project provide accessible
units.
5. New Green Code requires:
a. Upgraded insulation is required for buildings using electric heat or cooling.
b. Exterior walls and roof must meet a STC (sound resistance) rating of 40 min. if
building located within 1000ft to train tracks.
c. Low -flow Watersense plumbing fixtures (toilet, faucets, shower heads) are
required.
d. Special combustion safety requirements for natural draft gas appliances.
e. Low VOC interior finishes.
City of Fort Collins
Building Services
Plan Review
Page 9 of 20
Comment Number: 21 Comment Originated: 01/14/2015
09/16/2015: CONTINUED
01 /14/2015:
Tree Selection Comments:
Please list Sensation Boxelder as a large deciduous tree.
Princess Kay Plum by City Forestry Division evaluation has not survived or thrived
well in the Fort Collins area. Consider using an alternative ornamental tree that
might include flowering crabs , Tatarian maple, tree lilac or another adapted
ornamental trees.
Include some Kentucky Coffeetree as street trees. Using Kentucky Coffeetree in
some of the perimeter street tree locations seems appropriate.
Use some additional Bur Oak as street trees possibly in place of some of the
Skymater English Oak.
Toba Hawthorn is listed as conditionally recommended on the Front Range Tree
Recommendation List because of some health and survival issues. Consider
reducing the quantity by using another ornamental tree(s).
Lot 2 Detention Pond Tree Selection Comments:
Change the 4 Greenspire Linden to Honeylocust in the parkway along the south side
of Webster Avenue for improved drought tolerance. Show irrigated turf in this area.
Using Bur Oak in place of English Oak along the International Boulevard side of the
detention pond area would provide for a more drought tolerant species.
Using Texas Red or Shumard Oak in place of the four Hackberry along the Lincoln
Boulevard side of the Detention Pond would provide for good fall color and some
increased drought tolerance.
Comment Number: 23 Comment Originated: 09/16/2015
09/16/2015:
Use the newly developed project landscape, tree protection and street tree notes.
These notes are avaialbe from the Project Planner Pete Wray or the City Forester.
Department: Internal Services
Contact: Russell Hovland, 970-416-2341, rhovland(&fcgov.com
Topic: Building Insp Plan Review
Page 8 of 20
Comment Number: 12
Comment Originated: 01/14/2015
09/16/2015: CONTINUED
Providing only drip irrigation to trees with no other irrigation to turf will not sustain
street trees long term as they grow and mature. Providing spray irrigation to the turf
in parkways appears the best way to provide for the future irrigation of City street
trees in parkways.
01/14/2015:
Prairie Turf (Reduced Irrigation) is indicated in the perimeter parkways. Parkway turf
needs to receive irrigation by a pop-up spray or equivalent system. This should be
clarified by possibly describing it as Irrigated Prairie Turf. Providing for reduced
irrigation in landscape areas is a great concept but the irrigation of street trees still
needs to be adequately provided for. Significant reductions in turf irrigation would
limit the growth and survival of street trees.
Provide specific information on how irrigation with this concept will be adequate to
establish and sustain street tree growth. Incorporate information and or design
elements into the project design plan that clearly defines the level of irrigation that is
needed and will be provided for the street trees.
Comment Number: 15
Comment Originated: 01/14/2015
09/16/2015: CONTINUED
01/14/2015:
Include 35 upsized mitigation trees on the project. Identify upsized mitigation trees in
the Landscape Material Legend and by direct labeling of trees used as mitigation
trees. Typically placing an asterisk with footnote by mitigation trees in the
Landscape Material Legend and placing an M by those that are direct labeled has
been an effective way to identify mitigation trees.
Canopy Shade trees 3.0 inch caliper
Ornamental trees 2.5 inch caliper
Evergreen trees 8 feet height.
Comment Number: 16
Comment Originated: 01/14/2015
09/16/2015: CONTINUED
01/14/2015:
Include species diversity percentages in the Landscape Material Legend. Adjust
quantities if necessary to meet the standard in LUC 3.2.1 D 3 Minimum species
diversity.
Comment Number: 20
Comment Originated: 01/14/2015
09/16/2015: CONTINUED
Provide a final landscape plan for the round- about at final plan. Follow the
requirements in the streetscape and median standards. Contact Clark Mapes in the
Planning Department to obtain information on how the round- about will be reviewed
by the City streetscape and median team
01/14/2015:
Will a landscape plan be provided for the round about?
Page 7 of 20
Comment Number: 9
Comment Originated: 09/15/2015
09/15/2015: Prior to Final Plan approval, the following will be needed:
-Additional groundwater monitoring data as recommended by the Ecological
Consultant
-A detailed mitigation and weed management plan
-An itemized estimate of the amount of bond required for wetland mitigation costs
associated with this development
Comment Number: 6
Comment Originated: 09/15/2015
09/15/2015: Within the natural habitat buffer zone, according to Article 3.4.1(E)(1)
(a), the project shall be designed to preserve or enhance the ecological character or
function and wildlife use of the natural habitat or feature and to minimize or
adequately mitigate the foreseeable impacts of development, and Article 3.4.1(E)(1)
(g), the City has the ability to determine if the existing landscaping within the buffer
zone is incompatible with the purposes of the buffer zone. From a quantity
perspective, additional material should be provided to meet these standards and
planting enhancements should include appropriate native vegetation, species
diversity and variety in vertical structure. Thus, please provide the following on the
landscape plans at or before the time of Final Plans:
A. Provide additional plant material in accordance with these standards.
B. Label each individual species that will be planted within the natural habitat buffer
zone so staff can fully evaluate the plan for appropriateness.
C. A table listing each specific plant species, quantity, and caliper.
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan(cDfcgov.com
Topic: Landscape Plans
Comment Number: 3
Comment Originated: 05/29/2014
09/16/2015: CONTINUED
01 /14/2015:
This comment is continued from 5/29/14. If not already indicated show the location
of stop signs with a defined symbol in the site plan legend. Adjust street tree
locations to a distance of at least 20 feet from stop signs.
05/29/2014:
Please show the locations of street lights and stop signs and adjust street tree
locations as necessary.
Street lights: 40 feet for shade trees and 15 feet for ornamental trees
Stop signs: 20 feet for any tree
Comment Number: 11
Comment Originated: 01/14/2015
09/16/2015: CONTINUED
01 /14/2015:
Some street trees at the following locations appear to not be labeled as to species.
Four street trees located at Duff Drive and North Club House Drive on n North Club
House Drive.
Some street trees located at the corner of Cottage Drive and International
Boulevard.
Some street trees located at Cottage Drive and North Club House Drive NE corner.
Page 6 of 20
Comment Number: 42
Comment Originated: 09/15/2015
11/09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09/15/2015: Additional right-of-way on Lemay Avenue should be dedicated to
ensure that upon the realignment of Lemay Avenue the sidewalk along Lemay
across the private driveway is fully in right-of-way.
Contact: Sheri Langenberger, 970-221-6573, slangenberger(aDfcgov.com
Topic: General
Comment Number: 1
Comment Originated: 05/13/2014
05/13/2014: Additional $60.12 due for PDP fees. This is based on a submittal for
33 single family detached du, 148 non single family detached du, 9,450 sq non
residential, 28.264 acres.
Department: Environmental Planning
Contact: Kelly Kimple, , kkimple(a)fcgov.com
Topic: General
Comment Number: 3
Comment Originated: 01/13/2015
09/15/2015: Prior to issuance of the Development Construction Permit (DCP), and
prior to prairie dog removal, please submit the results of a burrowing owl survey
completed by a professional, qualified wildlife biologist, and in accordance with the
Division of Parks and Wildlife standards. Note the timing requirements of these
surveys are between March 15 and October 31, as no burrowing owls are expected
to be present between November 1 and March 14. This issue will be included in
Development Agreement language and is required due to the presence of prairie
dogs on the site.
Comment Number: 4
Comment Originated: 01/13/2015
09/15/2015: Prior to issuance of the Development Construction Permit (DCP),
please submit a letter explaining how and when prairie dog removal occurred at the
site and in accordance with the Division of Parks and Wildlife standards. This issue
will be included in Development Agreement language.
Comment Number: 5
Comment Originated: 01/13/2015
09/15/2015: The Natural Habitat Buffer Zone (NHBZ) of fifty feet (50 ft) is required in
Land Use Code 3.4.1(E) for wetlands less than one-third (1 /3) acre in size. The
NHBZ needs to be labeled on the site, grading, utility, and landscape plans
delineated for all wetlands and mitigated wetlands.
Comment Number: 8
Comment Originated: 01/13/2015
09/15/15: Please add this note. I do not see this note on current plans.
01/13/2015: Please add the following statement to the notes on any
sheets(including site, landscape, utility, grading, and storm sewer plan) that show
the Natural Habitat Buffer Zone:
"The Natural Habitat Buffer Zone area is meant to be maintained in a native
landscape. Please see Section 3.4.1 of the Land Use Code for allowable uses within
the Natural Habitat Buffer Zone."
This will help preserve the intention behind the natural habitat buffer zones and the
natural features into the future.
Page 5 of 20
Comment Number: 26 Comment Originated: 01/14/2015
11/09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09/15/2015: The landscaping required may need to be part of the condition
contemplated in Comment 20.
01/14/2015: The Landscape Plan should be identifying the landscaping of the
medians on Lincoln and International as well as the roundabout. A corresponding
underdrain system beneath the medians will also then need to be designed and
provided on the civil plans.
Comment Number: 29 Comment Originated: 01/14/2015
11 /09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09115/2015: The striping plans should be labelling the widths of the travel lanes, turn
lanes, and bike lanes along with indicating taper and storage lengths used for the
turn lane designs.
01/14/2015: The design and right-of-way dedication for realigned Lemay Avenue
needs to account for the separate right turn lane for northbound Lemay onto
eastbound Duff.
Comment Number: 33 Comment Originated: 09/15/2015
11/09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09/15/2015: With the premise that the some of the entrances off of public streets
will have street names on the private drive, and others do not, please have the plans
specify the placement of "Begin Private Maintenance" informative signs as was
designed with the Lakeview Subdivision completed by Northern Engineering.
Comment Number: 34 Comment Originated: 09/15/2015
11/09/2015: From my point of view this is a pre -hearing item and not something
that's addressed at time of Final. The number of units shown on the site plan should
presumably be the same as the number of lots on the plat.
09/15/2015: The site plan indicates the total number of units as 201, however the
plat appears to show a total of 200 lots. Under the premise that the lots shown on
the plat equate to units on the site plan, there would appear to be a discrepancy.
Comment Number: 35 Comment Originated: 09/15/2015
11/09/2015: Can the overlay exhibit be one of the items provided to the hearing
officer? This information I believe makes the relationship of lots to the site plan more
clear.
09/15/2015: The plat's indication of the 200 lots being created along with their
indicated lot numbers isn't clearly depicted on the site and landscape plan, which
makes understanding the legal status of the lots in combination with the proposed
development plan site design difficult to understand and review. The lots lines being
created as single family attached along with their unit number would seem to need
to be the most predominant feature on the site, landscape and civil plans.
Topic: Landscape Plans
Comment Number: 25 Comment Originated: 01/14/2015
11/09/2015: Is there a reason why this comment can't be updated at this time, and
not deferred until time of Final plan?
09/15/2015: Carried over pending verification of Comment 10.
01/14/2015: The Landscape Plan doesn't label the sight distance easement shown
on the plat and shows several Vanderwolfs Pine trees encroaching onto the sight
distance easement. Only limbed deciduous trees can be within a sight distance
easement per the notes on the plat, and the landscaping would need to be revised
with the pine trees out of the easement.
Topic: Plat
Page 4 of 20
Comment Number: 22 Comment Originated: 01/14/2015
11/09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09/15/2015: The plans show the extension of sidewalk along the south side of Duff
Drive to go past the property boundary of the development. From my perspective, it
would appear to be sufficient to stop the sidewalk at the property boundary and then
place the required Type III barricades at the property line. The termination of the
sidewalk shown on the plans appears to be at an odd location midway through the
abutting lot.
01/14/2015: The extension of Duff Drive to existing Duff Drive to the east should be
showing more existing features such as existing driveways on both sides of the
street. The new driveway onto Duff might have distance between driveway edges
that are not met in Table 7-3 of LCUASS.
Comment Number: 43 Comment Originated: 09/15/2015
11/09/2015: Noted as unresolved with the intention of addressing at time of a Final
plan review.
09/15/2015: The Lemay/Lincoln cross section on the cover sheet labels the correct
cross-section but displays the minor arterial cross section and should be updated.
Topic: General
Comment Number: 10 Comment Originated: 05/28/2014
11/09/2015: I'm presuming that this comment can be addressed at time of Final,
can this be confirmed?
09/15/2015: The response indicated that the easement is negated by the access
being only a right -in movement with no exit movement, has it been vetted that this
access would not be open to two way traffic upon the realignment of Lemay
Avenue? I am under the impression that the right -in movement was only intended in
the interim condition of existing Lemay Avenue. I'm concerned with the premise of
the enforceability of the right -in movement upon Lemay's realignment and the
exaggerated movement no longer being necessary. Under the premise that the
private drive would be open to two way traffic upon the Lemay realignment, the
roadway should be designed to be wider at this time to better allow for two way
traffic, and the sight distance comments would still be applicable.
01/14/2015: Understanding the parameters used in the response letter, a variance
request should still be provided for review prior to hearing.
05/28/2014: The parameters used to calculate sight distance should be provided.
The present standard in LCUASS Figure 7-16 requires a corner sight distance of
1030 feet based on the 50 mph design speed for Lemay Avenue. This doesn't
appear to be parameters used for the sight distance easement prescribed on the
plat.
Comment Number: 16 Comment Originated: 01/14/2015
11109/2015: The response indicated that this will be addressed with Final, I'm not
sure what this entails, as Engineering is still requiring this local street portion as
originally commented on.
09/15/2015: The response is noted, but the local portion is still obligated with this
development at time of first building permit. If an arrangement is worked out where
the party that acquires the property provides the local street obligation, then that's
certainly fine as well.
01/14/2015: How is Tract H envisioned to be developed? We may need the local
street portion obligation of realigned Lemay Avenue abutting this parcel at this time if
it's not evident that this Tract is developable. (Further staff discussion on this has
the City requiring the local portion of this tract be obligated with the development.)
Page 3 of 20
Comment Number: Comment Originated: 11/09/2015
09/15/2015: Please include the following comment(s) from GIS:
1. "Cottage" and "Club House" already exist within the Larimer Emergency
Telephone Authority service area. Please request new names for these private
drives. Street names can be verified at http://Iarimer.org/streets/.
2. A street direction, as in South Club House Drive, is only assigned based on the
location from the center of town. Omit this from the street name request.
3. Addresses will be assigned by the GIS Department after the plans have met final
approval through Development Review and are recorded with the City.
4. Projects with three or more tenant units require the Unit Level Addressing form
to be completed and submitted to the GIS Department once plans have met final
approval through Development Review and are recorded with the City. This can
occur anytime during construction, but before any utilities or address signs are
installed. All addressing will be determined by the GIS Department and submitted to
Poudre Fire Authority, USPS, Building Services, and Fort Collins Utilities. Failure to
contact GIS and determining addresses through other means may result in address
changes.
The Unit Level Addressing form can be obtained by contacting the GIS office at
gis@fcgov.com or (970) 416-2483.
Comment Number: 1 Comment Originated: 11/09/2015
11/09/2015: Incorporate rain garden/ drainage pre-treatment and wetland mitigation
facilities into revised site, landscape and utilitiy plans.
Comment Number: 4
Comment Originated: 11/09/2015
11/09/2015: Based on staff review comments on 11/10/15, a revised plan set is due
by 11/19.
Topic: Landscape Plans
Comment Number:
Comment Originated: 09/15/2015
09/15/2015: Add Landscape Plan cover sheet that starts with overall landscape for
first page.
Topic: Site Plan
Comment Number:
Comment Originated: 09/15/2015
09/15/2015: Private Drive off of Duff - add sidewalk on east side to conect to Tract
A so there is a sidewalk on both sides of drive similar to other entry drives. This
change will remove 1 parking space.
Comment Number:
09/15/2015:
Comment Number:
Comment Originated: 11/09/2015
Comment Originated: 11/09/2015
09/15/2015: Add 30' bus stop on Lincoln Ave (see redlines).
Comment Number: 2 Comment Originated: 11/09/2015
11/09/2015: Is the intent to show the site plan adns plat overlay that includes detail
of lot line exhibit to be a separate sitel plan sheet?
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata(a)fcgov.com
Topic: Construction Drawings
Page 2 of 20
Ecity of
Fort Collins
November 13, 20'
Linda Ripley
RIPLEY DESIGN INC.
401 WEST MOUNTAIN AVE
Fort Collins, CO 80521
RE: Capstone Cottages, PDP140004, Round Number
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
icgov. com/de vetopmentm view
Please see the following summary of comments from City staff and outside reviewing agencies for
your submittal of the above referenced project. If you have questions about any comments, you may
contact the individual commenter or direct your questions through the Project Planner, Pete Wray, at
970-221-6754 or pwray@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Clark Mapes, 970-221-6225, cmapes(aDfcgov.com
Topic: Building Elevations
Comment Number: 21
Comment Originated: 01/13/2015
01/13/2015: Please consider variation in building details such as doors, trim, corner
boards, bracket details on gable ends, lintels/head casings above windows, and
porch posts and details.
Contact: Pete Wray, 970-221-6754, pwraycDfcgov.com
Topic: Building Elevations
Comment Number: 3
Comment Originated: 11/09/2015
11/09/2015: For the next revised plan set, will you be including more detail for
illustrating building elevations and materials in color so at hearing more information
is available?
Topic: General
Page 1 of 20