HomeMy WebLinkAboutEYE CENTER OF NORTHERN COLORADO - PDP - PDP150029 - CORRESPONDENCE - (4)The current proposal shows a large parking lot in between the building
Precision Drive. At this time this would detract form the pedestrian connectivity
and convenience to from adjacent uses.
The modification request for additional parking would be unsupportable with this
site layout.
Comment Number: 2
Comment Originated: 12/28/2015
12/28/2015: A trash and recycling enclosure is required. This needs to be
designed with walk-in access separate from the main -service gate and located
20ft from a public sidewalk on a concrete pad.
Comment Number: 3 Comment Originated: 12/28/2015
12/28/2015: The elevations need to be on 24"x36" sheet size.
Comment Number: 4 Comment Originated: 12/28/2015
12/28/2015: Need a sheet index on the sheet with the signature blocks.
Comment Number: 5
Comment Originated: 12/28/2015
12/28/2015: The signature block on the plat for the Planning Approval is
incorrect. Please match the same signature block that is on the Site Plan.
Comment Number: 6 Comment Originated: 12/28/2015
12/28/2015: The lighting plan needs to show the footcandles across the entire
property and 20ft beyond the property line.
Additionally it should include the cut -sheets for the fixtures that are proposed?
Comment Number: 7 Comment Originated: 12/28/2015
12/28/2015: Are there not any light fixtures proposed on the building?
Comment Number: 8 Comment Originated: 12/28/2015
12/28/2015: At this time it is unclear where the mechanical equipment (vents,
flues, meters, boxes, conduit, transformer...) is located and if it is properly
screened. Please identify these locations on the plans
Comment Number: 9 Comment Originated: 12/28/2015
12/28/2015: The cross access to the property to the south does not appear to
align.
12
Topic: Site Plan
Comment Number: 11 Comment Originated: 12/30/2015
12/30/2015: There is text that needs to be rotated 180 degrees. See redlines.
Comment Number: 12 Comment Originated: 12/30/2015
12/30/2015: Please change the legal description as marked. See redlines.
Comment Number: 13 Comment Originated: 12/30/2015
12/30/2015: Please remove the reference to Windsong At Rock Creek. This
project has not been filed. See redlines.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/29/2015
12/29/2015: The TIS has been reviewed and the conclusions accepted.
Comment Number: 2
Comment Originated: 12/29/2015
12/29/2015: The site plan shows head -in parking along the east side of the
building. Because this connecting roadway will see quite a bit of traffic, the
functionality of backing out into traffic is not ideal. Since the proposal has more
parking spaces than the max, can they be eliminated?
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 12/22/2015
12/22/2015: Irrigation plans are required no later than at the time of building
permit. The irrigation plans must comply with the provisions outlined in Section
3.2.1(J) of the Land Use Code. Direct questions concerning irrigation
requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
Department: Water -Wastewater Engineering
Contact: Shane Boyle, 970-221-6339, sboyle@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/30/2015
12/30/2015: Please ensure a minimum of 10' of separation between the curb
stop and the storm sewer.
Department: Zoning
Contact: Noah Beals, 970416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/28/2015
12/28/2015: The Property is located on the corner of two streets and is subject
to the Build -to -line Standards of 3.5.3 of the Land Use Code. This section
requires a building to build within 10-25ft from Ziegler Road and 0-15ft from
Precision Drive, with no vehicle use area between the building and the public
right-of-way.
11
Topic: Construction Drawings
Comment Number: 3
Comment Originated: 12/30/2015
12/30/2015: There are missing notes from the Benchmark Statement. Please
provide the following information in the EXACT format shown below.
PROJECT DATUM: NAVD88
BENCHMARK # w/ DESCRIPTION
ELEVATION:
BENCHMARK # w/ DESCRIPTION
ELEVATION:
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL
DATUM. SURROUNDING DEVELOPMENTS HAVE USED NGVD29
UNADJUSTED FOR THEIR VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE,
THE FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED
= NAVD88 - X.XX'.
Comment Number: 4
Comment Originated: 12/30/2015
12/30/2015: Please remove the reference to Windsong At Rock Creek. This
project has not been filed. See redlines.
Topic: Landscape Plans
Comment Number: 5 Comment Originated: 12/30/2015
12/30/2015: There is text that needs to be rotated 180 degrees. See redlines.
Comment Number: 6 Comment Originated: 12/30/2015
12/30/2015: Please remove the Lot numbering from sheet 2. There is only 1
Lot for this subdivision. See redlines.
Topic: Lighting Plan
Comment Number: 7 Comment Originated: 12/30/2015
12/30/2015: Please remove "proposed" from the label. See redlines.
Topic: Plat
Comment Number: 8 Comment Originated: 12/30/2015
12/30/2015: The legal closes, the plat does not close. The boundary & legal do
not match. See redlines.
Comment Number: 9 Comment Originated: 12/30/2015
12/30/2015: Please label all surrounding properties with "Unplatted" or the
subdivision name. This includes properties across right of ways. See redlines.
Comment Number: 10
Comment Originated: 12/30/2015
12/30/2015: Please provide current acceptable monument records for the
aliquot corners shown. These should be emailed directly to Jeff at
jcounty@fcgov.com
10
Comment Number: 2
comment Originated: 12/29/2015
12/29/2015: WATER SUPPLY
If a hydrant is being added to the south as shown on the submitted plans,
minimum requirements for water supply appear to be met.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, ischlam@fcgov.com
Topic: Erosion Control
Comment Number: 1 Comment Originated: 12/09/2015
12/09/2015: The site disturbs more than 10,000 sq-ft, therefore Erosion and
Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted do not meet requirements. Please submit; Erosion Control Plan,
Erosion Control Report, and an Escrow / Security Calculation. If you need
clarification concerning the erosion control section, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Contact: Shane Boyle, 970-221-6339, sboyle@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 12/30/2015
12/30/2015: Based on the drainage report, detention is provided in the
subgrade of the paver sections. The plans are not clear how the flow control will
work in order to limit the release to that specified in the report. Please add
details and callouts to the Utility Plans to reflect what is being proposed.
Comment Number: 3 Comment Originated: 12/30/2015
12/30/2015: With detention provided in the paver sections, additional detail
needs to be added to the Drainage Plan in order to assess how each paver
section is functioning. Based on the site plan, each paver section will need to
have its own detention volume and flow control.
Comment Number: 4 Comment Originated: 12/30/2015
12/30/2015: Please expand the LID table so that each paver section is
analyzed independently. The 3:1 maximum ron-on ratio is per individual paver
section, not per basin.
Comment Number: 5 Comment Originated: 12/30/2015
12/30/2015: Please see additional minor redlines in the Drainage Report and
Utility Plans.
Department: Technical Services
Contact: Jeff County, 970-221-6588, ]county@fcgov.com
Topic: Building Elevations
Comment Number: 1 Comment Originated: 12/30/2015
12/30/2015: All plan sheets must be 24"06".
Comment Number: 2 Comment Originated: 12/30/2015
12/30/2015: There are line over text issues. See redlines.
Department: Light And Power
Contact: Coy Althoff, , CAlthoff@fcgov.com
Topic: General
Comment Number: 1 Comment Originated:
12/29/2015
12/29/2015: Primary electric distribution is currently running along the West
side of Ziegler Rd.
Comment Number: 2 Comment Originated:
12/29/2015
12/29/2015: Development charges, electric Capacity Fee, Building Site
charges and any system modification charges necessary will apply to this
development.
Comment Number: 3 Comment Originated:
12/29/2015
12/29/2015: Contact Light and Power Engineering to coordinate the
transformer and electric meter locations, please show the locations on the utility
plans.
Comment Number: 4 Comment Originated:
12/29/2015
12/29/2015: Transformers shall be within 10' of a paved surface and must have
8' clearance from the front and S clearance around the sides and back.
Comment Number: 5 Comment Originated:
12/29/2015
12/29/2015: Streetlights will be placed along public streets. A 40 feet
separation on both sides of the light is required between canopy trees and
streetlights. A 15 feet separation on both sides of the light is required between
ornamental trees and streetlights.
Comment Number: 6 Comment Originated:
12/29/2015
12/29/2015: Please provide a one line diagram and a C-1 form to Light and
Power Engineering. The C-1 form can be found at:
http://zeus.fcgov.com/utils-procedures/files/EngWikiMikiPdfs/C/C-1 Form.pdf
Comment Number: 7 Comment Originated:
12/29/2015
12/29/2015: Please contact Light & Power Engineering if you have any
questions at 221-6700. Please reference our policies, development charge
processes, and use our fee estimator at
http://www.fcgov. com/utilities/b usiness/bu ilders-and-developers.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, ilynxwiler@poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 12/29/2015
12/29/2015: FIRE LANES
Fire access is required to within 150' of all exterior portions of the building
perimeter. The proposed Emergency Access Easement plan creates an out of
access condition of approximately 450' and the EAE be need to be expanded
on both the north and south sides of the building to allow for better coverage.
There is also an EAE stub at the south property line will require a connection.
13
disease Fire blight. Most other cultivars are rated as resistant I,. ne Front
Range Tree Recommendation List.
Comment Number: 4
Comment Originated: 12/31/2015
12/31 /2015:
The Shade trees shown at some of the corners of the building with three
half-moon indentations on the perimeter of the symbol do not appear to be
identified in the plant list.
Department: Internal Services
Contact: Russell Hovland, 970-416-2341, rhovland@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
Comment Originated: 12/28/2015
12/28/2015:
Building Permit Pre -Submittal Meeting:
Pre -Submittal meetings are required to assist the designer/builder by assuring,
early on in the design, that the new commercial or multi -family projects are on track to complying with
all of the adopted City codes and Standards listed below. The proposed project should be in the early
to mid -design stage for this meeting to be effective and is typically scheduled after the Current Planning
conceptual review meeting. Applicants of new commercial or multi -family projects are advised to
call 416-2341 to schedule a pre -submittal meeting. Applicants should be prepared to present site plans,
floor plans, and elevations and be able to discuss code issues of occupancy, square footage and type of
construction being proposed.
Construction shall comply with the following adopted codes as amended:
2012 International Building Code (IBC)
2012 International Residential Code (IRC)
2012 International Energy Conservation Code (IECC)
2012 International Mechanical Code (IMC)
2012 International Fuel Gas Code (IFGC)
2012 International Plumbing Code (]PC) as amended by the State of Colorado
2014 National Electrical Code (NEC) as amended by the State of Colorado
Fort Collins has amendments to most of the codes listed above. See the
fcgov.com web page to view them.
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2009.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use
1. Single Family; Duplex; Townhomes: 2012 IRC Chapter 11 or 2012 IECC.
2. Multi -family and Condominiums 3 stories max: 2012 IECC residential
chapter.
3. Commercial and Multi -family 4 stories and taller: 2012 IECC commercial
chapter.
7
Comment Number: 4 comment Originated: 12/29/2015
12/29/2015: The landscape plan for this property should be consistent in
character with the plans for the Windsong Memory Care Center to the south.
Please review the list of species and planting pattern for Windsong to ensure
that there is consistency between the two properties. Native plant species,
fruit -bearing trees and shrubs, and pollinator -friendly plant species are
preferred, as they provide habitat for birds and other urban -adapted wildlife
species.
Comment Number: 5 Comment Originated: 12/29/2015
12/29/2015: Landscaping in the detention pond should include a mix of
deciduous trees, evergreen species, shrubs, flowering plants, and grasses.
Additionally, the side slopes in the detention area should be varied in grade to
create a more naturalistic appearance and allow for better establishment of
wildlife habitat, per the Stormwater Standards and Guidelines.
Topic: Lighting Plan
Comment Number: 1
Comment Originated: 12/29/2015
12/29/2015: In regard to LED light fixtures, cooler color temperatures are
harsher at night and cause more disruption to circadian rhythms for both
humans and wildlife. Please consider a warmer color temperature (closer to
2700K) for your LED light fixtures. Please also consider fixtures with dimming
capabilities so that light levels can be adjusted as needed.
Comment Number: 2
Comment Originated: 12/29/2015
12/29/2015: Please extend the footcandle calculations 20 feet beyond the
property line in all directions to ensure that the lighting does not exceed 0.1
footcandles at those points. See Land Use Code Section 3.2.4(D)(8) for
reference.
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Comment Number: 1
Comment Originated: 12/31/2015
12/31/2015:
Show locations of City Street lights and if needed place street trees to the LUC
separation standard.
Canopy Shade Trees - 40 feet from lights
Ornamental trees —15 feet from lights
Comment Number: 2
Comment Originated: 12/31/2015
12/31/2015:
Street Tree Selection:
For better adaptability along an arterial street change the Redmond Linden to
either Bur Oak or Hackberry on Ziegler.
Change the Discovery Elm used as a street tree along Precision to Accolade
Elm which is on the City Street Tree list.
Comment Number: 3 Comment Originated: 12/31/2015
12/31/2015:
Autumn Blaze Pear in some locations may have some susceptibly to the
A
Comment Number: 215
comment Originated: 12/31/2015
12/31/2015: Both this project and Windsong at Rock Creek appear to show no
grading in right-of-way needed to construct the respective sidewalks along
Ziegler Road. It would be ideal if both properties were to commit to having the
entire stretch of Ziegler Road sidewalk in place between Precision and Rock
Creek, such that upon the first CO of either building, a connected network is in
place. As their may be some opportunities for sharing parking and access
resources between the two properties, perhaps this sidewalk construction can
be part of that discussion as well.
Comment Number: 220 Comment Originated: 12/31/2015
12/31/2015: The parkway width along Ziegler Road doesn't appear to be a
consistent width, is a minimum 10' wide parkway being maintained? (It seems
to be based upon the scaling of the plans). Please have the width of the
parkway (max and min) depicted on the plans to go along with the indication of
the 6 foot detached sidewalk.
Comment Number: 225 Comment Originated: 12/31/2015
12/31/2015: The 10 foot irrigation easement identified on the plat will need the
irrigation easement owner's signature on the civil plans, since the area within
the easement is being regraded. It may want to be vetted sooner rather than
later whether the attorney certifying the plat may find that the irrigation easement
owner would also need to the plat under the requirements of the attorney
certification in the City's Land Use Code.
Comment Number: 230
Comment Originated: 12/31/2015
12/31/2015: Please label what appears to be the drive approach planned for
Mainstreet on the north side of Precision Drive on the plans to give indication
that this project's driveway is intended to align with Mainstreet's proposed
driveway.
Topic: Plat
Comment Number: 300
Comment Originated: 12/31/2015
12/31/2015: Please update the streets on the vicinity map (CR 36 is Kechter,
CR7 is Strauss Cabin, Cambridge is Lady Moon, remove indication of CR 9).
Topic: Site Plan
Comment Number: 400 Comment Originated: 12/31/2015
12/31/2015: Please confirm that the future expansion areas shown on the site
plan are part of the total building gross square footage allotment of 32,903. A
breakdown of this should ideally be indicated in the table of the proposed and
future, totaling the 32,903 sq. ft.
Department: Environmental Planning
Contact: Rebecca Everette, 970-416-2625, reverette@fcaov.com
Topic: Landscape Plans
Comment Number: 3
Comment Originated: 12/29/2015
12/29/2015: Annual ryegrass is considered a nuisance species by the City's
Natural Areas staff. Please remove this species from the native seed mix and
consider a seed mix that includes flowering plant species in addition to
grasses. I will provide an example seed mix at the staff review meeting.
5
of the Windsong aL Rock Creek project. What would be the imp.,,:ations on if
Windsong did not already complete this ahead of this project? Would this
project need to extend the waterline past its property boundary, or would a
dead-end line be acceptable?
Comment Number: 105
Comment Originated: 12/31/2015
12/31/2015: The street cut to Precision Drive, in addition to the standard
excavation permit fee, will require a triple impact fee due to the newness of the
road.
Comment Number: 110
Comment Originated: 12/31/2015
12/31/2015: The 34 foot curb opening behind the sidewalk at the north end of
the detention pond indicates that the pond spills to the drive. Is this in overflow
situation only? Does the curb opening at least allow for sheet flow of drainage
off the driveway to not flow across the Precision Drive sidewalk?
Comment Number: 115
Comment Originated: 12/31/2015
12/31/2015: It is presumed that with future submittals and/or time of final plan,
that sheets for standard construction notes and construction details will be
included in the civil set for review and approval.
Topic: General
Comment Number: 200 Comment Originated: 12/31/2015
12/31/2015: The plans don't seem to be coordinated with Windsong at Rock
Creek Drive in terms of how the north -south private drive is designed as this
project has it angled to the southeast, while Windsong appears to be aligned
directly north -south. The access easements depicted on the plats for the two
projects are also in different locations.
Comment Number: 205 Comment Originated: 12/31/2015
12/31/2015: The intent of the north -south driveway for Windsong at Rock Creek
south of the property, is to act as a driveway that can be shared between that
project and the undeveloped property to the east. This proposal has the
driveway access onto Precision Drive, close to the eastern boundary of its
property, yet does not provide access easement to the eastern boundary to
potentially allow for shared access to the undeveloped property to the east.
Ideally, we should be exploring how access points can be consolidated/shared
across adjoining properties, as depending on future development, their access
options may be hampered by not being able to share/consolidate.
Comment Number: 210 Comment Originated: 12/31/2015
12/31/2015: The traffic study shows as part of its analysis that secondary
access is secured to Rock Creek Drive for this site through a north -south drive
aisle. This would appear to make it dependent upon the development that this
connection out to Rock Creek Drive be made, if not already built by the
Windsong at Rock Creek project. Operating under that presumed perspective,
this project would need to ensure that the offsite easements for construction of
the private drive connection out to Rock Creek Drive, as well as its design is in
place prior to approval of this plans/project. If this project were to move ahead of
Windsong at Rock Creek, then the construction of this connection out to Rock
Creek Drive would need to be made, note that this would include restriping of
Rock Creek Drive (and potential reworking of the roadway) if not done by
Windsong at Rock Creek.
4
site improvemen,_ Jong the sidewalk designed for pedestrian ,.,erest, comfort
and visual continuity." While the physical space of the two plazas appears
sufficient, the details described above are lacking. Please supplement the two
plazas with additional required features in order to justify the exception to the
build -to line.
Comment Number: 10. Comment Originated: 12/30/2015
12/30/2015: The detail for the three Entry Portals is not provided. Perhaps the
team would be interested in the "Column, Beam and Trellis" detail that has been
designed by Windsong. If so, staff recommends that the base treatment match
the stone on the building to unify the site.
Comment Number: 11.
Comment Originated: 12/30/2015
12/30/2015: The Planning Objectives indicate that there may be up to 105
employees. With such a high number, please consider adding site details for
an outdoor employee break area and, perhaps, a picnic table or two for lunch
breaks.
Comment Number: 12.
Comment Originated: 12/30/2015
12/30/2015: On the Site Plan, please use heavier line for the Trash and
Recycling Enclosure.
Comment Number: 13. Comment Originated: 12/30/2015
12/30/2015: On the Lighting Plan Schedule, please make an adjustment to the
Kelvin temperature. As specified, the fixtures are listed as having a 4,000
Kelvin temperature. This temperature should be adjusted downward to 3,000 to
minimize the harsh glare and excessive brightness associated with high Kelvin
LED lighting. Please note that the same comment has been forwarded to
Windsong.
Comment Number: 14.
Comment Originated: 12/30/2015
12/30/2015: As noted, parking lot light fixtures must be shifted out of the
landscape islands so illumination is not diminished over time as the trees
mature. But, the Lighting Plan indicates that six of these fixtures feature dual
heads. Staff recommends that since these fixtures must now be distributed
throughout the parking lot, these fixtures should be reduced to single head and
the quantity adjusted accordingly.
Comment Number: 15. Comment Originated: 12/30/2015
12/30/2015: Since the site has the advantage of having a southern exposure,
the mechanical systems of the facility should be designed to be "solar ready"
should the decision be made to install solar equipment.
Comment Number: 16.
Comment Originated: 12/30/2015
12/30/2015: A roof plan would be helpful in determining compliance with
screening mechanical equipment.
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: Construction Drawings
Comment Number: 100 Comment Originated: 12/31/2015
12/31/2015: The 8" water shown on the plans heading southeast, indicates that
it is to connect to a waterline on the south property line, which I presume is part
3
Comment Number: 3. comment Originated: 12/30/2015
12/30/2015: The site plan needs to call out and graphically indicate the location
and the dimensions of all Emergency Access Easements.
Comment Number: 4. Comment Originated: 12/30/2015
12/30/2015: Either a Context Plan or an Enlarged Site Plan is needed to show
how the site (particularly the driveway location on Precision) aligns with both
Main Street Health and Wellness to the north Windsong at Rock Creek to the
south (particularly the new southwest E.A.E.).
Comment Number: 5. Comment Originated: 12/30/2015
12/30/2015: Staff is coordinating the streetscaping along Ziegler Road
between both Eye Center of Northern Colorado and Windsong in order to
establish a high quality landscape between Precision Drive and Rock Creek
Drive. Combined, this streetscape is 800 feet in length. Toward this end,
please additional Wichita Blue Black Hills Spruce to the streetscape. Please
note that we are asking Windsong to add Fastigiate Norway Spruce to match
Eye Care.
Comment Number: 6.
Comment Originated: 12/30/2015
12/30/2015: Staff is concerned about the length of the northerly parking lot that
parallels Precision Drive. Please note that Section 3.2.1(E)(4) — Parking Lot
Perimeter Landscaping — requires that this lot be screened by landscaping,
earthen berms or low screen walls, or any combination thereof, such that there
be sufficient opacity to block at least 75% of the lights from vehicle headlights.
The minimum height is 30-inches in height. As shown, the amount of
landscaping is insufficient for screening purposes. Please add additional plant
material in this area to help screen the parking lot from the public street.
Comment Number: 7.
Comment Originated: 12/30/2015
12/30/2015: The Landscape Plan indicates, in ghosted line, that there are
contours along Ziegler Road. Staff is assuming that these are a series of
undulating earthen berms that are intended to match the treatment being
provided by Windsong. Please graphically depict the treatment in heavier line
and call out the height of the berms.
Comment Number: 8. Comment Originated:
12/30/2015: Just as we are asking that the landscape design along Ziegler is
coordinated with Windsong, so too must the landscape design of the
stormwater detention pond also match Windsong. Staff will provide the team
the Windsong Landscape Plan. Please note that in combination, the Eye
Center and Windsong detention ponds exceed one -quarter of an acre in land
area. If designed properly, the two ponds could become eligible to be
designated as a Certified Natural Area. Please contact Karen Manci, senior
environmental planner, 221-6310 for further information. Please also see the
information provided at http://www.fcgov.com/naturalareas/certified.php).
Comment Number: 9. Comment Originated:
12/30/2015: As discussed at Preliminary Design Review, the site layout is
subject to the exceptions available in lieu of strict compliance with the build -to
line standard (which would otherwise require the building to be brought up to the
immediate corner of Ziegler and Precision). These exceptions, as described in
Section 3.5.3(C)(2)(d), require that the proposed plazas must have
"...landscaping, low walls, fencing or railings, a tree canopy and/or other similar
2
12/30/2015
12/30/2015
Fort Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins. CO 80522
970.221.6750
970.224.6134 - fax
fcgov.com/deve/opmentreview
January 04, 2016
Cathy Mathis
TB Group
444 Mountain Ave
Berthoud, CO 80513
RE: Eye Center of Northern Colorado, PDP150029, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Ted Shepard, at 970-221-6343ortshepard@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Ted Shepard, 970-221-6343, tshepard@fcgov.com
Topic: General
Comment Number: 1.
Comment Originated: 12/30/2015
12/30/2015: We have two plats in at the same time. Windsong at Rock Creek
contains 18.7 acres and includes Outlot A at 15.36 acres. But, concurrently, we
have a plat in for Eye Center of Northern Colorado, immediately north of
Windsong, which is a portion of Outlot A, but does not indicate in its title block
that it is a "Replat of a Portion of Outlot A of Windsong at Rock Creek." Both
plats include overlapping land area. The plats indicate that the owner is
Harmony Technology Park LLC. The owner should be aware that these two
plats need to be rectified. Perhaps one plat could take precedence over. Or,
has the owner considered consolidating these two plats into one?
Comment Number: 2.
Comment Originated: 12/30/2015
12/30/2015: A second point of access for Poudre Fire Authority is needed in
the southwest comer of the site. This emergency access drive will connect to
the emergency access drive that is being dedicated and shown in the northwest
comer of the Windsong at Rock Creek P.D.P. This Emergency Access
Easement is shown as being 24 feet wide. Please adjust the parking lot and