HomeMy WebLinkAboutWINDSONG AT ROCK CREEK - FDP - FDP160010 - CORRESPONDENCE - REVISIONS03/30/2016: Please show all monuments as found or set. See redlines.
Response: Addressed
Comment Number: 8
Comment Originated: 03/30/2016
03/30/2016: If the Eye Center Of Northern Colorado plat is filed before this,
please make changes as shown. See redlines.
Response: Addressed
Comment Number: 9 Comment Originated: 03/30/2016
03/30/2016: All easements must be labeled & locatable. See redlines.
Response: Reception numbers yet to be assigned
Topic: Site Plan
Comment Number: 10 Comment Originated: 03/30/2016
03/30/2016: No comments.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221.6887, mwilkinson(a)fcgov.com
Topic: General
Comment Number: 1 Comment Originated
03/30/2016: Sheet 18 - for the EB turn lane on Rock Creek Drive, there should
be two left turn arrows, one at start of full turn lane, and the other as shown. The
arrows should be preformed thermoplastic, not paint.
Response: Addressed
Department: Water -Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamargueapfcgov.com
Topic: General
Comment Number: 1 Comment Originated
03/3012016: The proposed 24-inch water line connection to the existing main in
Ziegler needs to be north of the connection valve with FCLWD.
Response: Addressed
Comment Number: 2 Comment Originated
03/30/2016. Water lines that are crossing under other utilities greater than 24
inches need to be sleeved. Please provide the sleeving detail in the plans as
well.
Response: detail and casing added.
03/30/2016
03/30/2016
03/30/2016
9
Comment Number: 16 Comment Originated:
03/30/2016: There is text that needs to be rotated 180 degrees. See redlines.
Response: Addressed
Comment Number: 17 Comment Originated:
03/30/2016: There are sheet number issues. See redlines.
Response: Addressed
Comment Number: 18
03/30/2016: There are cut off text issues. See redlines.
Response: Addressed
Topic: Landscape Plans
Comment Number: 11
03/3012016: There are line over text issues. See redlines.
Response: These issues have been corrected.
Comment Number: 12
03/30/2016
03/30/2016
Comment Originated: 03/30/2016
Comment Originated: 03/30/2016
Comment Originated: 03/30/2016
03/30/2016: There is text that needs to be masked. Mask all text in hatched
areas. See redlines.
Response: The hatch has been removed to correct this issue.
Topic: Plat
Comment Number: 1 Comment Originated: 03/30/2016
03/30/2016: Please make sure all plat language is the most current City
language.
Response: Addressed
Comment Number: 2 Comment Originated:
03/30/2016
03/30/2016: Are there any Lienholders for this property? If so, please add a
signature block. If not, please add a note stating there are none, and include
response in written comments.
Response: Addressed
Comment Number: 3 Comment Originated:
03/30/2016
03/30/2016: Does the South Fort Collins Sanitation District need to sign?
Response: Awaiting South Fort Collins Sanitation District response.
Comment Number: 4 Comment Originated:
03/30/2016
03/30/2016: Please provide current acceptable monument records for the
aliquot comers shown. These should be emailed directly to Jeff at
*county()Jcgov.com
Response: Addressed
Comment Number: 5 Comment Originated:
03/30/2016
03/30/2016: Please add dedication information for all street rights of way. See
redlines.
Response: More research needed
Comment Number: 6 Comment Originated:
03/30/2016
03/30/2016: Please show tie bearing as noted in the legal description. See
redlines.
Response: Addressed
Comment Number: 7 Comment Originated:
03/30/2016
8
03/30/2016: Please label longitudinal slope of the detention pond bottoms.
Response: Added longitudinal slope arrows for detention Pond A.
Comment Number: 4 Comment Originated: 03/30/2016
03/30/2016: Please label public or private for all storm sewers on the storm
sewer plan & profile sheets.
Response: Addressed
Comment Number: 5 Comment Originated: 03/30/2016
03/3012016: Please add a pond summary tables to the Drainage Plan.
Response: Addressed
Comment Number: 6 Comment Originated: 03/30/2016
03/30/2016: Please add a detention pond depth gauge to the main pond.
Response: Detail and location added to plans
Comment Number: 7
Comment Originated: 03/30/2016
03/30/2016: The pavers appear to have a greater area draining over them than
3:1 when the roof area in that particular basin is included in the run-on
calculation. Additional pavers may be required to lower the run-on area or a
revision of sub -basins.
Response: Pavers along north end of site have been removed and roof runoff is now being treated by sand
filters. See LID plan for additional info.
Comment Number: 8 Comment Originated:
03/30/2016
03/3012016: Is any erosion protection required at the pipe outlets?
Response: Riprap added see calculations in drainage report.
Comment Number: 9 Comment Originated:
03/30/2016
03130/2016: The WQ outlet structure needs to be modified due to no standard
WQ being provided.
Response: Addressed
Comment Number: 10 Comment Originated:
03/30/2016
03/30/2016: Please label that seed is required on top of the soft pan and label.
Response: Addressed
Comment Number: 11 Comment Originated:
03/30/2016
03/30/2016. Please provide the sand filter detail from Urban Drainage.
Response: Addressed
Department: Technical Services
Contact: Jeff County, 970.221.6588, 'count fc ov.com
Topic: Building Elevations
Comment Number: 13
03/30/2016: No comments.
Topic: Construction Drawings
Comment Number: 14
Comment Originated: 03/30/2016
Comment Originated: 03/30/2016
03130/2016: All benchmark statements must match on all sheets.
Response: Addressed
Comment Number: 15 Comment Originated: 03/30/2016
03/30/2016: There are line over text issues. See redlines.
Response: Addressed
7
Contact: Jim Lynxwiler, 970-416-2869, jynxwiler@poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 03/30/2016
03/30/2016: EMERGENCY ACCESS EASEMENT & FIRE
ENGINE/AMBULANCE ACCESS TO FRONT DOOR
The EAE stub on the south side may be omitted however the issue of engine
and ambulance response to this facility does not appear to have been
addressed yet. A parking/staging area should be provided for near the front
door for emergency services responding to medical calls.
Response: Emergency access easement on the south side removed. Onsite emergency access easement
extended west to provide staging area near entry.
Comment Number: 2
Comment Originated: 03/30/2016
03/30/2016. FIRE LANE SIGNAGE
Fire lane - No Parking signs will be required along the fire lane. Locations
should be shown on the Signage and Striping Plans. Code language provided
below.
Response: Parking signs added along fire lanes.
> IFC D103.6: Where required by the fire code official, fire apparatus access
roads shall be marked with permanent NO PARKING - FIRE LANE signs
complying with Figure D103.6. Signs shall have a minimum dimension of 12
inches wide by 18 inches high and have red letters on a white reflective
background. Signs shall be posted on one or both sides of the fire apparatus
road as required by Section D103.6.1 or D103.6.2.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, ischlam(a)fcgov.com
Topic: Erosion Control
Comment Number: 1
Comment Originated: 03/08/2016
03/08/2016: Erosion Control Report and Plans have redlines that will need to
be addressed.
12/07/2015: The site disturbs more than 10,000 sq-ft, therefore Erosion and
Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted do not meet requirements. Please submit; Erosion Control Plan,
Erosion Control Report, and an Escrow / Security Calculation. If you need
clarification concerning the erosion control section, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ ischlam(a)fcgov.com
Response: Addressed
Contact: Wes Lamarque, 970-416-2418, wlamargueMcgov.com
Topic: General
Comment Number: 2
Comment Originated: 03/30/2016
03/30/2016: The porous paver underdrain needs to be extended to capture a
greater area of the paver section. Also, please show cleanout locations.
Response: Addressed
Comment Number: 3
11
Comment Originated: 03/30/2016
Department: Light And Power
Contact: Rob Irish, 970-224-6167, rirish(a)fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 03/29/2016
03/29/2016: Light & Power will have to extend electric facilities along the N.
side of Rock Creek Dr. from Technology Parkway to feed this site. Power into
this site will come from the Southeast corner of the site and extend North
through this site to feed the future parcel to the North. With the nearest electric
facilities at the Northwest corner of Rock Creek & Technology Pkwy providing
temporary construction power to this site will be problematic until the permanent
system can be installed.
Response: Noted
Comment Number: 2 Comment Originated: 03/29/2016
03/29/2016: Transformer location looks good. Thank you.
Response: Noted
Comment Number: 3 Comment Originated: 03/29/2016
03/29/2016: A C-1 Form and a One -line diagram will need to be submitted to
Light & Power Engineering for review. Please click on the following link for the
C-1 Form.
http://www.fcgov.com/utilities/business/builders-and-developers/development-fo
rms-guidelines-regulations
Resoonse Noted
Comment Number: 4
Comment Originated: 03/29/2016
03/29/2016: Electric Capacity Fee and Building Site charges will apply to this
development. Please click on the following link for Estimated Light & Power
charges and the Light & Power Fee calculator.
http://www.fcgov.com/utilities/business/builders-and-developers/plant-investmen
t-development-fees
Response: Noted
Comment Number: 5
Comment Originated: 03/29/2016
03/29/2016: Please contact Light & Power Engineering if you have any
questions at 221-6700. Please reference our policies, development charge
processes, and use our fee estimator at
hfto://www.fcaov.com/utilities/business/builders-and-developers.
Response: Noted
Comment Number: 6
Comment Originated: 03/30/2016
03/30/2016: A CAD version of the APPROVED Site & Utility plan must be
submitted to CJHousley@fcgov.com before any electric design can begin.
Response. Noted
Department: PFA
5
Planning's build -to lines under the Land Use Code?
Response: All lots east of Windsong should be able to meet 25' build -to line.
Topic: Plat
Comment Number: 10 Comment Originated:
03/29/2016: The plat language on the cover sheet appears to be outdated and
will need to be updated to our current requirements. I can email the current
version separately.
Response: Addressed
Comment Number: 11 Comment Originated:
03/29/2016: The plat language on the cover sheet appears to be outdated and
will need to be updated to our current requirements. I can email the current
version separately.
Response: Addressed
Department: Environmental Planning
Contact: Rebecca Everette, 970-416-2625, reverettea()fc_qov.com
Topic: Lighting Plan
Comment Number: 1
03/29/2016
03/29/2016
Comment Originated: 03/23/2016
03/23/2016: Please provide a revised lighting plan that responds to the
following comment provided during the PDP review:
"l2/09/2015: For the light fixtures, please clarify the intended color temperature
for each fixture. The labels do not appear to match up between the lighting plan
and the cut sheets that were provided. Cooler color temperatures are harsher at
night and cause more disruption to circadian rhythms for both humans and
wildlife. Please use warmer color temperature options (2700K or 3000K) for the
LED light fixtures. Please also consider fixtures with dimming capabilities."
Response: Addressed
Department: Forestry
Contact: Tim Buchanan, 970-221.6361, tuchanan@fcgov.com
Topic: Landscape Plans
Comment Number: 5
Comment Originated: 03/30/2016
03/30/2016:
Continued:
12/23/2015:
A redbud tree is shown in the parking lot peninsula at the North East section of
the project. The Land Use code standard is for use of canopy shade tree in
these parking lot locations. Please review this landscape area for a canopy
shade tree.
Response: The redbud tree has been replaced with a canopy shade tree. On previous plan the planter
island was of insufficient area to accommodate a shade tree.
4
Topic: General
Comment Number: 1
Comment Originated: 03/29/2016
03/29/2016: There appears to have been a change between PDP to Final
regarding the widths of the sidewalks on Ziegler Road (from 6 feet to 7 feet) and
Rock Creek Drive (from 5 feet to 6 feet). Just wondering how this came about
(and perhaps I may have not recalled a conversation regarding the increase in
sidewalk widths.) The street classifications for Ziegler and Rock Creek have
sidewalk width requirements of 6 feet and 5 feet respectively. The additional 1
foot provided on both streets would not be eligible for street oversizing
reimbursement and with that in mind, I would question perhaps whether the
additional width adds much value to the pedestrian given proposed (Eye
Center), to be constructed (Mainstreet) and existing (Intel) sidewalks on Ziegler
Road are at 6 feet, and similarly existing sidewalk along Rock Creek is 5 feet.
Response: Sidewalk was widened to 7 per Sheri Langenberger comment 08/07/15.
Comment Number: 2
Comment Originated: 03/29/2016
03/29/2016: The construction of directional access ramps at the Rock
Creek/Ziegler intersection abutting the site is not depicted on the plans and
needs to be designed on the civil plans from both a horizontal and vertical
perspective with spot elevations, grades, widths, etc. The access ramps need
to show how they align with existing crosswalks across Rock Creek and Ziegler.
Additionally the access ramps and sidewalk system need to show how they
function in relation to existing infrastructure (or relocated infrastructure
accordingly) -- there appears to be the existing signal pole that would be in
conflict with the sidewalk design, as well as an existing control box that's not
depicted on the plans and may be in conflict as well.
Response: Ramp added per LCUASS detail 1604, existing infrastructure will remain in place.
Comment Number: 3 Comment Originated: 03/29/2016
03/29/2016: A receiving access ramp needs to be provided on the east side of
the private drive intersecting Rock Creek Drive, designed on the civil plans and
depicted on the plans.
Response: Ramp Added
Comment Number: 4 Comment Originated: 03/29/2016
03/29/2016: A $250 deed of dedication Transportation Development Review
Fee is needed with the offsite drainage easement, with the actual dedication
needing to be provided along with recording fees prior to approval of the plans.
SFCSD's approval of their easement and recordation needs to similarly occur
prior to plan approval (with reception numbers on both easements indicated on
the subdivision plat). If the boundary of the drainage easement is considered in
its final form with Stormwater, the legal description for the drainage easement
can be reviewed by Technical Services. Since the SFCSD easement isn't
conveyed to the City, fees and review of the easement isn't required.
Response: Noted
Comment Number: 5
Comment Originated: 03/29/2016
03/2912016: Does the offsite drainage pipe and its associated easement
potentially make it more difficult for future properties to the east to meet
3
03/30/2016: Please add all signature blocks and standard notes to the site
plan cover sheet and label site, landscape, architectural, lighting sheets
sequentially. I can provide standard notes in a word document.
Response: Addressed
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata(a)fcgov.com
Topic: Construction Drawings
Comment Number: 6 Comment Originated: 03/29/2016
03/29/2016: The private drive intersecting Rock Creek Drive should not be built
as a public street intersection, which is implied with the cross plan depicted on
the plans and the inclusion of LCUASS Detail 708. This driveway should be
depicted and built either as LCUASS 707.1 or 707.2, utilizing concrete fully in
the right-of-way. (It would seem that 707.1 could be the design parameter with
less concrete along the curb returns.)
Response: Redesigned per LCUASS 707.1
Comment Number: 7 Comment Originated: 03/29/2016
03/29/2016: 1 don't believe the traffic control sheets should be part of the civil
plan set (unless otherwise desired by Traffic Operations) and should be
removed.
Response: Removed from Utility Plans
Comment Number: 8
Comment Originated: 03/29/2016
03/29/2016: On Sheet 4 of the civil plans please add the following information
to Note #1 referenced for the street cuts to Rock Creek Drive: "Limits of street
cut are approximate. Final limits are to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City street repair
standards." I will look to get input on the approximate patching limits depicted,
as the oddity of the striping for Rock Creek Drive would appear to make
defining the patching more difficult. Sheet 5 also needs the same note for the
street cut shown to Precision Drive. Note that the street cut to Precision Drive
will require a triple penalty fee in addition to the typical street cut fee due to the
roadway being new.
Response: Addressed
Comment Number: 9 Comment Originated: 03/29/2016
03/29/2016: There doesn't appear to be grading information for the offsite utility
work shown on Sheet 17 (or perhaps the site is very flat?) Regardless contour
elevation information and complete contours themselves should be depicted.
Response: Addressed
2
City of
Fort Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins. CO 80522
970.221.6750
970.224.6134 - fax
tcgov. com/developmentreview
April 01, 2016
Tim Halopoff
JR ENGINEERING
2900 SOUTH COLLEGE AVE, SUITE 3D
Fort Collins, CO 80525
RE: Windsong at Rock Creek, FDP160010, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Ted Shepard, at 970-221-6343 or tshepard@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Ted Shepard, 970-221-6343, tshepardajcgov.com
Topic: General
Comment Number: 1
Comment Originated: 03/30/2016
03/30/2016: We will need a Lighting Plan prior to mylars to confirm final
compliance and to make sure that for L.E.D. fixtures, the Kelvin temperatures
do not exceed a range of 2,700 and 3,000 degrees.
Response: Noted
Comment Number: 2
Comment Originated: 03/30/2016
03/30/2016. On the Landscape Plan and the Hydrozone Plan, please use
heavier line to depict the berms and call out the height. The Drainage and
Erosion Control Plan, Utility Plan Sheet 16 of 32, depicts the berms very clearly.
We want to make sure that for construction plans, bid documents and for
contractors, the design is clear and unambiguous.
Response A heavier line weight has been used and berm heights have been added to these plans.
Comment Number: 3
Comment Originated: 03/30/2016
03/30/2016: The trash enclosure is specified to be 7'6" in height which seems
a bit high. Perhaps this can be lowered to six feet so it is not as imposing with
no loss of screening capability.
Response -Addressed
Comment Number: 4 Comment Originated: 03/30/2016